1 2 3 4 5

Monitoring and
Knowledge Area/Process Group Intiating Planning Excecuting Control Closing

1 Project Integration Mangement ü ü ü ü ü 5

2 Project Scope Management ü ü 2

3 Project Schedule Management ü ü 2

4 Project Cost Management ü ü 2

5 Project Quality Management ü ü ü 3

6 Project Resource Management ü ü ü 3

7 Project Communication Management ü ü ü 3

8 Project Risk Management ü ü ü 3

9 Project Procurement Management ü ü ü 3

10 Project Stakeholder Management ü ü ü ü 4


1 2 3 4 5
Monitoring and
Knowledge Area/Process Group Participate Intiating Planning Excecuting Control Closing No of Process

1 Project Integration Mangement 5


1 1 2 2 1 7

2 Project Scope Management 2


4 2 6

3 Project Schedule Management 2


5 1 6

4 Project Cost Management 2


3 1 4

5 Project Quality Management 3


1 1 1 3

6 Project Resource Management 3


2 3 1 6

7 Project Communication Management 3


1 1 1 3

8 Project Risk Management 3


5 1 1 7

9 Project Procurement Management 3


1 1 1 3

10 Project Stakeholder Management 4


1 1 1 1 4

2 24 10 12 1 49
1 2 3 4 5
Monitoring and
Knowledge Area/Process Group Participate Intiating Planning Excecuting Control Closing No of Process

1 Project Integration Mangement 5


1 1 2 2 1 7

2 Project Scope Management 2


4 2 6

3 Project Schedule Management 2


5 1 6

4 Project Cost Management 2


3 1 4

5 Project Quality Management 3


1 1 1 3

6 Project Resource Management 3


2 3 1 6

7 Project Communication Management 3


1 1 1 3

8 Project Risk Management 3


5 1 1 7

9 Project Procurement Management 3


1 1 1 3

10 Project Stakeholder Management 4


1 1 1 1 4

2 24 10 12 1 49
Knowledge Area/Process Group Initiating

1 Project Integration Management 5


1
2 Project Scope Management 2

3 Project Schedule Management 2

4 Project Cost Management 2

5 Project Quality Management 3

6 Project Resouce Management 3

7 Project Communication Management 3

8 Project Risk Management 3

9 Project Procurement Mangement 3

10 Project Stakeholder Management 4


1
30 2
Monitoring and
Planning Excecuting Closing
Controlling

1 2 2 1 7

4 2 6

5 1 6

3 1 4

1 1 1 3

2 3 1 6

1 1 1 3

5 1 1 7

1 1 1 3

1 1 1 4

24 10 12 1 49