Page 65, Shipping, imports and Custom Formalities: Sipping, imports and Custom Formalities:
section 6.14, The CONTRACTOR shall be responsible for line pipe logistics from arrival The CONTRACTOR shall be responsible for line pipe logistics from
onboard at Gabes port to the SITE including but not limited: COMPANY storage yard in Bouchemma (Gabes) to the SITE including
- Coordination with Freight forwarder. but not limited to:
- Line pipe Handling. - Line pipe Handling.
- Line Pipe warehouse until the construction phase. - Line Pipe temporary storage during construction phase.
- Line pipe transportation from the Port to the SITE to be convened with - Line pipe transportation from the COMPANY yard to the SITE to be
COMPANY. The site would be one of the project's construction locations convened with COMPANY. The site would be one of the project's
in Tataouine. The CONTRACTOR shall be responsible for complying with construction locations in Tataouine. The CONTRACTOR shall be
the current Tunisian legislation. responsible for complying with the current Tunisian legislation.
TATAOUINE GAZ PROJECT
TATAOUINE BRANCH LINE TBL
Page 70, Line pipe clearance, Gabes harbor reception, transportation and storage Line pipe transportation and storage :
section 7.2.2 : Contractor shall be responsible for supplying all required material,
Contractor shall be responsible for supplying all required material, warehouse, equipment and personnel to perform the following:
warehouse, equipment and personnel to perform the following: - Line Pipe Transportation to Warehouse,
- Line Pipe Clearance, - Line Pipe storage.
- Gabes Harbor Reception,
- Line Pipe offloading,
- Libe Pipe Transportation to Warehouse,
- and Line Pipe storage.