Aurora

1. Fire safety
a. Remove roof of office
i. RS spoke to SFO2 Canapi and we purchase fire extinguisher for PHP 20k with
receipt
b. Dismantle the roof of workshop
i. Same as above
2. Deliveries of equipment
a. Red Viper – ICE416
i. Saturday ready trucking on us
ii. BBS contact Miles and co-ordinate with their appointed site personnel at Manila
port at tondo
b. EF Chua – SG45V
i. Lando fabricating the adaptor plate
ii. Waiting for their advise on commissioning
c. GF Fabian – Installation of the SG45
i. He will send both excavator n SG45 to us to assemble
ii. BBS will followup on the date
d. Venray – HD30
i. Venray contact person: Engr. Eldie
ii. Waiting for their piles to be ready on site before sending man for
commissioning at Cebu
iii. Sidro is sick and well next week to go with Dennis Tagalog
e. Venray – BM700 at CDO
i. Venray contact : Engr. Ronnie
ii. Waiting for crane to move to site
iii. RS is in touch with Engr, Ronnie
f. ABG construction and general services – Used D25-32 at Ilocos
i. Calling for commissioning
ii. Sidro has to travel by bus over 10 hours
iii. If he gets well can send him on Sunday
g. Montano – HD36
i. Shipment : BBS has referred to Ernest Logistics to contact directly for shipment
to Dipolog
h. UBI
i. TGS FM23
1. Waiting for funds b4 depositing the check
ii. LS 218RH5
1. Interested but waiting for order
i. ECG – HR300
i. Commissioning – estimated schedule mid Feb
j. ACME builders drilling bucket
i. Delivery is ready
ii. Waiting for balance payment before pickup
k. Roland Gapuz - SV500T
i. Waitng for deposit
ii. Need to purchase valve block to install
iii. RS will advise the part to purchase – 2 nos – one to replace GF Fabian
l. Cavdeal
i. DTC80 commissiong
ii. At macapagal site
iii. ETA mania port 17 Feb
iv. Expect to clear custom 25th Feb
v. Commissioning end Feb
3. REPAIRS
a. EK40 – andy incharge
i. Crown pulley bearing repaired
ii. Swivel – replace bearing and seal – yet to be done
iii. Main winch cable replacement to follow after the swivel is repaired
iv. Complete by 9th Feb
b. HR45
i. Repairs
1. After EK40 is done
2. HR45 repairs start 11 Feb – end Feb
3. Operational repairs are priority
4. Body repairs will follow if no rental or if sales
c. PTC25H1 – returned from VR Patron
i. Open up the gear box to check alignment of eccentric bearings
d. HPSI 260 – belongs to Cavdeal
i. Open up gear box check bearings and service
ii. Clean up the T bars from weldings
iii. Check and replace seals on clamps
iv. We agreed to charge labour and time only
e. Roland Gapuz – K35 ram piston repair
i. Only commence after purchase of SV500T
ii. Also need to collect downpayment for the ram repairs before commencing.
f. Servicing and repairs of company vehicles and equipment
i. Hylux
1. Replace steering ball joints
2. Replace suspension supports
3. Check engine supports
ii. Fortuner
1. Reface brake disc and drum
2. Replace brake shoes
iii. Forklift
1. Replace tires
iv. Terex
1. Need to repair the rear hyd steering
v. Generator
1. Mcweld
a. Change oil
4. Procurements
a. Vehicle
i. Sell Revo for Toyota Hiace commuter
1. To canvass for prices 3 n 5 years old vehicles
ii. Purchase a new Starex for SP
1. SP will followup
b. Gen set
i. Single phase 40kva genset
1. Surplus denyo
ii. 3 phase Mcweld 260KVA from Singapore
1. SP
iii. Welding set – 300 amp min
1. SP co-ordinate from Singapore
2. Get MIG type
c. Bottle jack
i. Handpump type – 50ton and up
ii. 4 nos – european or japan made
d. Chain block
i. Good brand
1. 1 x 1ton
2. 1 x 3 ton
3. 1 x 5 ton
e. Hand pump for fuel
i. Get locally
f. Industrial grade pressure washer
i. Source from Singapore
g. Personal tools for mechanics
i. RS BBS and Marvin to work on it

C6 requirements
1. Demolitions end this week end
a. RS to remind the encroachers
2. FSCC work
a. Earthwork to start asap
b. Illegal squatter
i. RS to chase violy if the house is not transferred yet by Monday
c. RS to negotiate 35% disc from 4.1M
d. Rear earthwork to be added in total package
e. Priority to fence off the rear
f. Front gate
i. Temporary solution to be erected by next wed if not earlier

3. Water well drilling


a. RS to enquire
4. Water supply for now
a. Get from violy
b. Fill up our tank with filtratiion before entering the tank of 2 cu.metre
5. Purchase
a. Sub-meter for electricity
b. Prepaid submeters for residence- apply to Meralco