You are on page 1of 8

National Safety Council

Data Sheet 565 Rev. March 2007

Handling steel plate for fabrication

S teel plate, used in the construction of


vessels and machinery, presents prob-
lems in safe handling and storing at the fab-
ricators’ plants and warehouses. This data
sheet discusses safe handling practices for
steel plate of more than 8 1⁄16 inches in width
and from 3⁄16 or more inches in thickness.

Hazards
2. The greatest hazard in handling steel
plates is dropping the load because of
slipped or failed lifting attachments, over-
loaded equipment or improperly balanced
loads. In addition, personnel may be struck Figure 1. Hooks lift plates in areas where a dropped
by swinging hooks, chains or cables. load would be disastrous. Cars are used to transport
3. Associated hazards include: plate long distances and across areas where there is
• Handling of lifting devices no crane.
• Contact with sharp edges of plates
• Loss of control of heavy material or 6. Electromagnets (Figure 2) provide the
equipment as it is lifted and being moved quickest and most economical method of
• Electrical shock from powered hoists or unloading and handling steel plates. The
lifting electromagnets hazard of dropping plates is generally great
enough to restrict their usage to open stor-
Equipment for handling age areas and other locations where per-
4. Overhead traveling cranes, jib cranes, sonnel are not at risk from a dropped or
mobile cranes or forklift trucks are general- shifted load (Figure 3). Occasionally they
ly used to unload steel plate and to handle can be adapted for use in the shop areas
it throughout the fabrication process. In where personnel and equipment will not be
addition, small material handling cars and endangered should a load be dropped.
dollies are used (Figure 1). 7. Capacities should be clearly indicated on
5. Lifting devices used with cranes include the magnets. Crane operators and rigging per-
electromagnets, vacuum pods, automatic sonnel must be familiar with the weight of the
wedge clamps, screw clamps, hooks and lift so that magnet capacities are not exceed-
slings and horizontal plate lifting clamps. ed. Electromagnets must be equipped with
Careful selection of the proper lifting battery backup in case of power outage.
device will ensure maximum safety where 8. For a vacuum pod-lifting device to hold
personnel may be injured or equipment properly, plate surfaces must be clean
damaged by a falling load. and free from all foreign matter. A reserve

1
National Safety Council
Data Sheet 565 Rev. March 2007

Figure 2. Electromagnets provide the easiest and Figure 3. When using electromagnets, plates can be
most economical means of handling steel plate. stored without cribbed blocks.

vacuum tank should be attached to assist material. In order for clamps to grip secure-
the lowering of the load in the event of ly, plates must be clean (i.e., free of oil,
vacuum pump failure. grease, mud and other foreign material).
9. When not in use, vacuum pod lifting 13. For very thick plates, clamps may be
devices must be stored in manner to pre- impractical. In this case, lifting lugs can be
vent pod deformation. Once the vacuum attached to the plate using proper welding
pod has become deformed, it will no longer procedure. The size and weight of the
grip properly and must be removed from plate must be taken into consideration in
service. Inspect vacuum pods before use.
10. Automatic wedge clamps are generally
used when plates are to be lifted by their
edges (Figure 4). Automatic clamps may be
used with either wire ropes or chains.
Clamps with either one or two pairs of grip-
ping jaws may be used for lifting. Make sure
all clamps are equipped with lock-closing
devices that cannot be inadvertently disen-
gaged. All clamps with two pairs of jaws
must be attached with the jaws trued to the
surface of the plate. (Clamps with a single
pair of jaws automatically align themselves.)
11. Serrations of the wedged-clamped
jaws and the cups must be inspected fre-
quently and kept clean and sharp. Paint or
other foreign matter will reduce the grip
capacity of the jaws.
12. Screw clamps (Figure 5) must be tight
enough that the cup of the setscrew cuts
into the plate. The cups must be examined
frequently to make sure that none is bro- Figure 4. Automatic clamps are attached so that the
ken or filled with dirt, scale or other foreign jaws take the strongest possible grip.

2
National Safety Council
Data Sheet 565 Rev. March 2007

Figure 6. Thick plates need at least four lugs, two


welded at each end, if they are to be lifted while in a
Figure 5. Screw clamps must be tight enough to cut horizontal position.
into the plate. Note the use of safety hook.
limits for both wire rope slings and alloy
determining the number of lifting lugs steel chain slings used should be readily
required. Generally, lugs positioned to lift a available and easily accessible for the crane
horizontal load should not be used to lift a operators and rigging personnel. Crane
vertical load and vice versa (Figure 6). operators must be trained in accordance
When long plates are to be moved, it is with OSHA Regulations.
usually necessary to use a spreader beam 15. All electric crane and hoist installations
in the hookup (Figure 7). must conform to the requirements of the
National Electrical Code. Only qualified per-
Crane safety sonnel should work on the electrical sys-
14. A plate or tag showing the safe load tems. Where possible, use only enclosed
limit must be posted on every crane, and it runway conductors.
must be clearly visible to rigging personnel 16. Crane parts subject to impact, wear and
on the ground. Charts showing safe load rough usage should have a safety factor of

Figure 7. Balance beams and slings provide safe lifts for long, flexible plates.

3
National Safety Council
Data Sheet 565 Rev. March 2007

five to one. (A factor of safety is the number operating condition and must be tested at
of times that the breaking strength exceeds the start of each shift. If a switch fails to
the safe load limit.) function, remove the crane from service
• The load hook; immediately and do not use it until the nec-
• Hoisting cables, gears and other parts essary repairs have been made.
subject to wear; 22. When cars or dollies are used to trans-
• All other parts, including the structural port plate, the workers moving the load
steel; must sound a horn or other audible signal.
• The frequency of inspections of the If it is not possible to utilize audible signal
crane and its equipment, plus the record- devices, have a signalman in front of the
keeping, must conform to OSHA (and car or dolly while it is being moved.
state, if any) requirements.
Storage yards
Lifting and transporting plates 23. To provide adequate working space,
17. Personnel involved in the moving of provide a minimum of 4 feet of clearance
steel plate must be properly trained. They along either side of railroad tracks in the
should be aware of and instructed in the material storage yard. Also, provide a clear-
hazards involved. These hazards include: ance of at least 30 inches from the outside
• Location of hands and feet while moving rails of an opening buggy track. If the 30-
plates; inch clearance cannot be maintained,
• Attaching lifting devices to plates; “close clearance” signs must be installed.
• Swinging hooks; 24. All access lanes used by trucks should
• Chains and cables. be at least 11 feet wide. When practical,
18. Center crane hooks over loads before make walkways a minimum of 30 inches
lifts are made. Place lifting devices so that wide when used for access to the forward
(a) loads will be balanced and (b) minimum (marked ends) of piled materials.
damage to the plate will occur from lifting
attachments. Storage areas
19. Before a lift is made and while it is in 25. Be sure storage areas are level, well-
progress, a siren, bell, horn or other audible compacted or paved, and free of obstruc-
signals and visual flashing lights must be tions. When used non-permanent skids
used to warn workers to stay out from must be adequate to support the maximum
under the load. Loads must never be car- anticipated loads. Inspect support skids for
ried over workers. stability during weather conditions involv-
20. Signalmen must use only standard signals ing either heavy rainfall or freezing and
to guide riggers and crane operators. (See thawing (when ground heave or settlement
Figures 25-5 and 25-6 in Accident Prevention may occur).
Manual for Industrial Operations, 12th edition,
Engineering and Technology volume, 2000.) Timber blocking and cribbing
Improvised signals are prohibited. 26. Use sound lumber for receiving or
21. Crane operators must use extreme shipping yard blocking. Recommended
caution when making lifts, and they must sizes include three by four inches, four by
never rely on limit switches to stop loads. four inches, four by six inches and six by
Limit switches must be maintained in good eight inches, with the lengths as needed.

4
National Safety Council
Data Sheet 565 Rev. March 2007

27. Generally, blocks are placed directly Table 1.


over points of skid support. Place rectangu- Plate Thickness Allowable Overhang
lar shaped blocks that support steel with (in inches) (in approximate feet)
their long dimension horizontal. Do not 1⁄4 to 1⁄2 6
extend blocking beyond the piles of steel More than 1⁄2 to 3⁄4 9
so as to interfere with adjacent lifts. More than 3⁄4 to 1 12
More than 1 15
Piling steel plate
28. It is important to practice good use of er precautions when cutting steel banding.
yard storage in piling material to obtain 30. Be sure the widths and lengths of the
both the greatest yield (in tons per square plates in any one lift are approximately the
foot) that is compatible with good safety same size for safe handling. For pile stabil-
practice an the most expeditious handling ity, it is recommended that, before lifting,
to and from the shop. This can be best the width and length of the plates from the
accomplished by constructing solid single bottom to the top of the pile be diminished,
piles. (See Safety Requirements for Shops as in a pyramidal arrangement. Vertically
fabricating Structural Steel and Steel Plate, align head (marked) end of plates when
ANSI Z 229.1-1982 for general rules that adjacent to walkways. Plate may be offset
list recommended limits for the pile’s or stepped endwise to uncover identifica-
height and methods of nesting, interlocking tion marks (Figure 9).
and blocking different shapes and sizes of 31. Spacing of 7 to 10 feet between skids
structural and plate material.) is usually sufficient to support plates with-
29. Plates that are 6 to 30 inches wide can out excessive sagging. When plates are
be stacked safely in a variety of ways unsupported by the skids and extending
(Figure 8). Plates up to approximately 12 beyond the tail end of a pile, support them
inches wide are usually received in banded from the ground or pavement by cribbed
or wired bundles. Never lift or pull banded blocks (Figure 9). This is necessary when
or wired bundles by the strap or wire. They the plate overhangs more than 25 percent
should remain this way unless they need to of its length and when the overhang
be broken to sort for handling. Follow prop- exceeds the value given in Table 1. Do not

Figure 8. Various ways of stacking flat plates (6 to 30 inches wide): A (solid), B (multiple), C (blocked and
tiered), D (single tiered) and E (single blocked).

5
National Safety Council
Data Sheet 565 Rev. March 2007

Figure 9. The offset or “step” method of stacking plates to reveal identification marks. Note the use of
cribbed blocks to support two plates that have significant overhang.

set the cribbed blocks on end to support skids safely on temporary timber, and tier
overhanging plates either from the ground these piles with timber blocks between
or from plates below. each plate or lift of plates. Small invento-
32. Plates over 30 inches wide can form ries of plate can be stored on edge in racks
stable piles to any convenient height. If as shown in Figure 12.
piled solid, succeeding lifts may be stag-
gered laterally to aid handling (Figure 10). Housekeeping and inspection
33. Where width variations occur and 35. Sound housekeeping and inspection
plates are handled with hooks, place the procedures will contribute greatly to the
widest plate at the bottom of the lift. prevention of accidents. Good housekeep-
Extend the edges of this plate beyond the ing on crane runways, in crane cabs, and in
edge of the plates above it (Figure 11). If storage areas is especially important.
magnets or vacuum pods are used for lift- Check all work areas regularly to ensure
ing, plates can be piled solid without spac- that good housekeeping practices are
ers. If lifting clamps are used, place wood being followed.
strips or blocks between plates to permit 36. All equipment must be inspected on a
easy clamp entry. regular basis as outlined in Federal OSHA
34. Pile plates and slabs too short to span or state regulations. Defective equipment

Figure 10. For plates more than 30 inches wide, Figure 11. When the widths of the plates vary, the
each lift of a solid pile can be staggered laterally. bottom plate of each lift should be the widest.

6
National Safety Council
Data Sheet 565 Rev. March 2007

Figure 12. Racks for stacking plates on edge.

must be removed from service and proper- ty, safety glasses with side shields or gog-
ly tagged out. Make sure recordkeeping gles with a shade-two filter lens should be
meets all federal and state requirements. worn to provide protection from stray flash-
37. Hammers, steel wedges, pry bars and es and reflected radiation. Wherever possi-
other hand tools must be maintained in safe ble, shield welding operations.
working condition. Hammers with cracked 40. For protection against burrs, sharp
handles or loose heads must either be edges and similar hazards presented by the
repaired immediately or be tagged “out of steel plates, use hand protection such as
service.” Inspect steel wedges for mush- leather gloves or arm guard hand leathers.
roomed heads and dull or chipped points at These gloves can be metal reinforcements.
regular intervals. Remove from use pry bars 41. Depending upon the hazards created
that have been moderately bent. by nearby operations, other specific items
of protective apparel may be needed. For
Personal protective equipment instance, if the noise level is sufficiently
38. Unloading and moving steel plate is high and cannot be reduced, hearing pro-
largely overhead work, so hard hats must tection must be used.
be worn at all times. Foot protection must
also be worn. Safety shoes with metatarsal Sources of information
guards are recommended. Shin and leg American National Standards Institute, 1430
Broadway, New York, NY 10018: Slings, ANSI/ASME
protective devices may also be advisable. B30.9-2003.
39. As a matter of general practice, eye
National Fire Protection Association, Batterymarch
protection must be worn. In storage areas, Park, Quincy, MA 92269:
coverall goggles can help prevent eye
National Electrical Code, NFPA 70.
injuries caused by windblown scale and
dust. If welding is to be done in the vicini- U.S. Department of Labor, Occupational Safety and

7
National Safety Council
Data Sheet 565 Rev. March 2007

Health Administration (OSHA): Code of Federal Acknowledgment


Regulations, Title 29- Labor Chapter XVII, Part 1910,
Subpart N: Section 1910.179, “Overhead and This data sheet was revised by the AMPS
Gantry Cranes,” Subsection (j), “Inspections” and
Section of the Industrial Division, National
Section 1910.180, “Crawler, Locomotive, and Truck Safety Council, 1121 Spring Lake Drive,
Cranes,” Paragraph (d) (6), “Inspection Records.” Itasca, IL 60143-3201
National Safety Council, 1121 Spring Lake Drive,
Itasca, IL 60143-3201 Accident Prevention Manual Copyright ©2008 National Safety Council.
for Industrial Operations, 12th edition, Engineering All rights reserved.
and Technology volume, 2000.
American National Standards Institute, 1430 Although the information and recommendations con-
Broadway, New York, NY 10018: Safety
Requirements for Shops fabricating Structural Steel tained in this publication have been compiled from
and Steel Plate, ANSI Z 229.1-1982. sources believed to be reliable, the National Safety
Council makes no guarantee as to, and assumes no
Bibliography
American National Standards Institute, 1430 responsibility for, the correctness, sufficiency or
Broadway, New York, NY 10018: Safety Codes for completeness of such information or recommenda-
Cranes, Derricks, Hoists, Jacks and Slings, B30 Series. tions. Other or additional safety measures may be
Greiner, H.G., editor, Crane Handbook, 2nd edition, required under particular circumstances.
1955. Whiting Corporation, Harvey, IL 60426.
National Safety Council, 1121 Spring Lake Drive,
Itasca, IL 60143-3201: Electromagnets Used with
Crane Hoists, Data Sheet 359.

You might also like