You are on page 1of 4

Conflict Between mendous load on the cathodic protec-

tion (CP) system.


Most electrical engineers specify
copper for grounding electrodes be-
cause the metal is a good electrical con-

Copper Grounding ductor and because many perceive that


it does not corrode when buried in the
soil.3 Nevertheless, copper does cor-
rode when completely isolated. If it is

and CP in Oil & electrically connected to ferrous metal,


the copper will be cathodically pro-
tected at the expense of the ferrous
metal. Also, copper does not polarize
readily as does iron or steel. Conse-

Gas Production quently, it requires appreciably more


current to protect ferrous structures
connected to copper grounding than
to protect the ferrous structures alone.

Facilities Case History: Pakistani Oil &


Gas Production Facilities
Union Texas Pakistan (UTP) oper-
ates six major oil and gas production
EARL L. KIRKPATRICK, ELK Engineering Associates, Inc. facilities and a number of smaller fa-
cilities in the Badin Block, Sindh Prov-
ince. Figure 1 is an aerial view of one
The common bonding of underground ferrous of the larger production facilities.
structures to massive copper grounding grids These facilities are used to separate oil
creates problems for corrosion engineers and their and gas, remove water, ship natural gas
attempts to cathodically protect the ferrous structures. via pipeline, and store oil and distillate
This article discusses the impact of the design and production in aboveground tank farms
for later transport to refineries by
operation of massive copper grounding systems, ferrous tanker truck. Electrical power is gen-
underground piping, and cathodic protection in production erated on-site. The production facility
facilities. discussed here handles both crude oil
and natural gas and was brought online
in about 1990.

CATHODIC PROTECTION
Initially, there were three CP recti-
fier (T/R) units at the facility. T/Rs 1

T
raditional copper ground- and 2 powered a total of 30 vertically
ing systems are cost- installed distributed anodes around the
effective. They reduce haz- perimeter of nine production tanks.
ardous voltages associated T/R 3 powered a conventional remote
with lightning and fault vertical anode bed and was dedicated
currents or induced cur- to CP of the incoming flow lines and
rents in the earth to safe trunk lines from remote production
values. 1 Electrically interconnecting facilities. The three T/Rs, originally
many dissimilar metals in the soil, how- rated at 25 V 75 A direct current (DC),
ever, can lead to significantly increased were capable of protecting the under-
corrosion rates on some of the under- ground piping and minimal copper
ground structures2 and also places a tre- grounding system.
22 MATERIALS PERFORMANCE August 2002
FIGURE 1

COPPER GROUNDING
The original electrical grounding
grid was constructed utilizing poly-
vinyl chloride-insulated copper con-
ductor ranging in size from 16 to 95
mm2. Grid conductors (70 or 95 mm2)
were connected to driven copper clad
ground rods at 200 to 400 ft (61 to 122
m) spacing around the perimeter of the
plant, with a few supplemental ground
rods at major pieces of equipment.
Within the 5-year period prior to
mid-1996, the grounding system was
upgraded to “improve” the electrical
grounding at each of the production
facilities. This was considered neces-
sary to ensure adequate fault-current
protection should some electrical ele-
ment short to ground. The upgrade
consisted of bare-copper, 70- or 95- Aerial view of the Khaskeli Production Facility, which contains the Sindh Province discovery well.
mm2 cable laid in parallel with the ex-
isting insulated cable grounding grid.
Each bare-copper grid was supple- ing the grounding system upgrade. The trodes—would be beneficial if one
mented with additional copper ground majority of the underground piping ex- needed to lower the resistance-to-
rods, and a total of four “deep ground- hibited pipe-to-soil (P/S) potentials less remote earth of the overall grid. That
beds” were installed. The deep ground- negative than –0.85 V referenced to a was not the case.
beds consisted of a copper plate ~1 m2 copper-copper sulfate (Cu/CuSO 4)
in size and buried ~4 m deep. Three electrode (CSE). RESISTANCE-TO-REMOTE-EARTH
separate 95-mm2 bare-copper conduc- MEASUREMENTS
tors were exothermically welded to FIELD STUDY INITIATED The investigators attempted to mea-
the copper ground plate and were In late summer 1996, the author sure the combined plant/electrical
brought up to a bus bar installed in an collaborated with in-country CP sub- grounding grid resistance-to-remote
aboveground manhole. Given the very contractors and UTP personnel to con- earth at one of the production facili-
low electrical soil resistivity at this site duct a detailed CP/electrical grounding ties using the Institute of Electrical and
(90 to 200 Ω-cm), the grounding sys- survey of the major production facili- Electronics Engineers (IEEE) Fall of
tem upgrade seemed unnecessary. ties and most of the minor production Potential method.5 The resistance-to-
Following installation of the ground- facilities in Sindh Province. remote earth of the existing compos-
ing system upgrade, corrosion failures Prior to this study, the company and ite grounding grid and plant piping
became a serious problem at most of contractor personnel disconnected the network was so low that it precluded
the production facilities. In a few in- bonds to the perimeter fencing and dis- measurement with available instru-
stances, perimeter fencing fell down connected most of the bare-copper pe- mentation. Neither of the alternating
when the supporting poles corroded rimeter ground loop from the plant current ohmmeters available at the
in two at grade level or underground grid. Perimeter-fence bonding is re- time of the survey could accurately
because they had been bonded to the quired at electrical-generating stations measure a value of <0.005 Ω. There-
bare-copper grid. It was reported that and at locations where external power fore, an alternative DC method was
numerous corrosion leaks, produced is brought into a facility via overhead used. The differences in potential (∆E)
by active corrosion in flow lines, had conductors4 to protect personnel in between the “on” and the “off” remote
been repaired. In some instances, en- the event of a falling conductor. Be- P/S potentials, measured while simul-
tire segments of a pipeline were re- cause neither of these conditions exist taneously cycling the T/R units, were
placed with new pipe. Annual CP sur- at the production facilities, perimeter used to calculate the resistance of the
veys indicated that the vast majority of fence grounding is not required. A entire plant grounding grid to remote
the buried plant piping was not ad- perimeter-grounding conductor—with earth. These measurements were taken
equately cathodically protected follow- or without supplemental driven elec- using a single, remote CSE placed
August 2002 MATERIALS PERFORMANCE 23
FIGURE 2

dure disregarded the CP current that


was applied to the flow lines.
The calculated resistance-to-remote
earth of the production facility was
0.001294 Ω prior to removing the ad-
ditional copper grounding and
0.00139 Ω after removing as much of
the additional copper grounding as
was safe and practicable (Figure 2).
This represents a 7.7% increase in
overall plant resistance. The final over-
all plant grid is still more than three
orders of magnitude lower in resis-
tance-to-remote earth than is required
to operate a safe system, however. For
on-site electrical power generation, an
overall plant grounding grid resistance
in the range of 5 to 25 Ω is considered
adequate and safe. Therefore, the ex-
One of many excavations to disconnect bare copper conductors. Green PVC-insulated conductor in tensive grounding system upgrade was
foreground is part of the original grid. not necessary.

CP EVALUATION
FIGURE 3 The existing CP system was prefer-
entially protecting the fire water (FW)
loop and not providing enough CP cur-
rent to the plant piping that contains
the production fluids and gases. Dur-
ing the electrical grounding system dig-
outs, deliberate cross bonds were made
between FW piping and plant piping
and between insulated plant grounding
grid conductors and buried plant pip-
ing. This technique ensured adequate
electrical continuity among the various
systems—grounding grid conductors,
production piping, and FW mains—to
prevent cathodic interference prob-
lems. Cathodic interference had been
noted at several locations. It usually
occurred on the grounding grid that
earlier had not been deliberately con-
nected to the buried piping but was in-
terconnected only by aboveground
connections at various equipment
Technician servicing a resistor junction box at the Bukhari Gas Facility. skids. Approximately 890 lineal ft (271
m) of additional large-diameter, bare-
copper grounding conductor was dis-
8,500 ft (2,590 m) from the plant site. test site with the T/Rs both on and off. connected from the plant grid. As a
When the interrupted P/S potential An average of the remote P/S ∆Es was result of work done during this study,
survey was conducted, the close P/S divided by the portion of the T/R out- neither the perimeter fencing nor the
potential and the remote P/S potential puts that were contributing CP current perimeter bare-copper grounding loop
were measured and recorded at each to the plant piping only. This proce- remained connected to the plant grid.
24 MATERIALS PERFORMANCE August 2002
During the second survey, the re- The investigators recommended References
searchers noted an acceptable de- using additional cross bonds and re- 1. E.L. Kirkpatrick, “Electrical Grounding and Ca-
crease in P/S potentials on the FW lines moving some of the resistor junction thodic Protection Issues In Large Generating Stations,”
because of the deliberate cross-bond- MP 40. 11 (2001): p. 17.
boxes (RJBs) that were used to cross-
2. E.L. Kirkpatrick, “Effects of Electrical Ground-
ing among the FW system, the buried connect some of the plant piping (Fig- ing On Corrosion,” CORROSION/79, paper no. 53
plant piping, and the electrical ground- ure 3). Some of the RJBs were appro- (Houston, TX: NACE, 1979).
ing grid. At the same time, improve- priate to control P/S potentials on flow 3. ANSI/IEEE Standard 80-1986, “IEEE Guide for
ments were noted in plant piping and lines and other isolated piping. Within Safety in Substation Grounding” (New York, NY: The
grid-conductor potentials. Because the Institute of Electrical and Electronics Engineers, Inc.,
the plant site itself, however, the RJBs
1986).
remaining bare-copper grounding grid introduced unacceptably high resis- 4. E.L. Kirkpatrick, “Report of Cathodic Protec-
cannot be cut loose, the grid was tances into the bonding circuits; this tion and Grounding Study on Oil and Gas Production
bonded to the balance of the piping led to uneven P/S potentials and the Facilities in Pakistan,” ELK Engineering Associates,
system; this was done to eliminate ca- possibility of cathodic interference on Inc., 1750, March 21, 1997.
thodic interference and to produce 5. ANSI/IEEE Standard 81-1983, “IEEE Guide for
some of the underground structures.
Measuring Earth Resistivity Ground Impedance, and
more uniform P/S potentials. Improv- RJBs have also proven to be high-main- Earth Surface Potentials of a Ground System” (New
ing the cross-bonding and eliminating tenance items. York, NY: The Institute of Electrical and Electronics
some of the bare-copper grounding led Engineers, Inc., 1983).
to more uniform and somewhat im- 6. E.L. Kirkpatrick, M. Shamim, “Copper Ground-
RESULTS OF THE ing Systems Have a Negative Effect on Cathodic Pro-
proved P/S potentials on the buried
CP UPGRADE tection in Production Facilities,” CORROSION/2000,
plant piping and eliminated cathodic
The installation work for the CP sys- paper no. 743 (Houston, TX: NACE, 2000).
interference among various elements
tem upgrades started in late 1997 and
of the underground system.
was finished 1 year later. All of the fi- This work was presented by the author
nal data were gathered within a week at the 8th Middle East Corrosion Confer-
RECOMMENDATIONS
of commissioning, which did not allow ence (Bahrain, 1998) and the 2nd Elec-
Specific CP system upgrade recom-
sufficient time for full polarization.6 tric Power Research Institute (EPRI) Cor-
mendations were made for each Badin rosion & Degradation Conference (Key
Nevertheless, the vast majority of the
Block facility.4 They ranged from a few West, Florida, 2000).
buried piping was adequately pro-
zinc anode and test lead installations
tected with a combined T/R output of
in one remote production facility to the EARL L. KIRKPATRICK is President of ELK Engi-
196.4 A, excluding current to the flow
installation of one or two additional neering Associates, Inc., 8950 Forum Way, Fort
lines. The production facility covers a Worth, TX 76140-5017. He is a registered profes-
(and much larger) T/R units at some of
surface area of ~29.5 acres (12 ha). sional engineer with 43 years of experience in all
the larger facilities. No upgrade in CP
Therefore, the final average current phases of corrosion engineering, engineering man-
capacity was deemed necessary for agement, and construction management in indus-
density per unit area is ~6.658 A per
many of the facilities. Removing exces- tries that include oil & gas, electrical systems, air-
acre (0.4 A per ha).
sive bare-copper grounding at these ports, light rail, and industrial facilities. He received
facilities was sufficient to restore effec- a NACE Distinguished Service Award in 1990 and
tive levels of CP. Conclusions has been a NACE member since 1960.
Two additional T/R installations The grounding system upgrade,
were recommended at the plant dis- which was unnecessary from an elec- WANTED
cussed earlier. T/R 4 is a 10-V, 100-A trical safety standpoint, completely
Practical Technical Articles
unit powering a split horizontal distrib- overwhelmed the CP systems and led Distinctive Cover Photos
uted anode bed containing 11 anodes, to excessive corrosion failures of the News
installed on the west side of the plant. underground plant. As much bare cop- Product Releases
T/R 5 is a 10-V, 150-A T/R on the east per as practical was disconnected and/ Send corrosion-related articles, photos,
side of the plant. This unit powers a or physically removed from the grid. and other information for publication to:
16-anode horizontal anode bed, which Because of the presence of direct- MP Managing Editor
is fully remote from the plant piping. buried high-voltage cables, more bare NACE International
1440 South Creek Drive,
Thus, T/R unit capacity for the plant copper than was desirable remained in Houston, TX 77084-4906
piping in the production facility was the ground. The remaining bare cop-
For MP article submission guidelines
increased from 150 to 400 A—even per was successfully polarized by in- and more detailed information on
after removing as much of the exces- stalling additional T/R capacity. A 167% types of information sought,
sive bare-copper grounding as was increase in T/R and groundbed capac- call 281/228-6207 or e-mail:
gretchen.jacobson@mail.nace.org.
practicable. ity was required.
August 2002 MATERIALS PERFORMANCE 25

You might also like