Professional Documents
Culture Documents
Activity based costing (ABC) assigns manufacturing overhead costs to products in a more logical manner than the
traditional approach of simply allocating costs on the basis of machine hours. Activity based costing first assigns costs
to the activities that are the real cause of the overhead. It then assigns the cost of those activities only to the products
that are actually demanding the activities.
Let's discuss activity-based costing by looking at two products manufactured by the same company. Product PQR is a
low volume item which requires certain activities such as special engineering, additional testing, and many machine
setups because it is ordered in small quantities. A similar product, Product XYZ, is a high-volume product—running
continuously—and requires little attention and no special activities. If this company used traditional costing, it might
allocate or "spread" all of its overhead to products based on the number of machine hours. This will result in little
overhead cost allocated to Product PQR, because it did not have many machine hours. However, it did demand lots of
engineering, testing, and setup activities. In contrast, Product XYZ will be allocated an enormous amount of overhead
(due to all those machine hours), but it demanded little overhead activity. The result will be a miscalculation of each
product's true cost of manufacturing overhead. Activity based costing will overcome this shortcoming by assigning
overhead on more than the one activity, running the machine.
Activity based costing recognizes that the special engineering, special testing, machine setups, and others are activities
that cause costs—they cause the company to consume resources. Under ABC, the company will calculate the cost of
the resources used in each of these activities. Next, the cost of each of these activities will be assigned only to the
products that demanded the activities. In our example, Product PQR will be assigned some of the company's costs of
special engineering, special testing, and machine setup. Other products that use any of these activities will also be
assigned some of their costs. Product XYZ will not be assigned any cost of special engineering or special testing, and
it will be assigned only a small amount of machine setup.
Activity based costing has grown in importance in recent decades because (1) manufacturing overhead costs have
increased significantly, (2) the manufacturing overhead costs no longer correlate with the productive machine hours or
direct labor hours, (3) the diversity of products and the diversity in customers' demands have grown, and (4) some
products are produced in large batches, while others are produced in small batches.
Let's illustrate the concept of activity-based costing by looking at two common manufacturing activities: (1) the setting
up of a production machine for running batches of products, and (2) the actual production of the units of product. We
will assume that a company has annual manufacturing overhead costs of $2,000,000—of which $200,000 is directly
involved in setting up the production machines. During the year the company expects to perform 400 machine setups.
Let's also assume that the batch sizes vary considerably, but the setup efforts for each machine are similar. The cost
per setup is calculated to be $500 ($200,000 of cost per year divided by 400 setups per year). Under activity-based
costing, $200,000 of the overhead will be viewed as a batch-level cost. This means that $200,000 will first be
allocated to batches of products to be manufactured (referred to as a Stage 1 allocation), and then be assigned to the
For our simple two-activity example, let's see how the rates for allocating the manufacturing overhead would look with
activity-based costing and without activity-based costing:
Next, let's see what impact these different allocation techniques and overhead rates would have on the per unit cost of
a specific unit of output. Assume that a company manufactures a batch of 5,000 units and it produces 50 units per
machine hour, here is how the cost assigned to the units with activity-based costing and without activity based costing
compares:
If a company manufactures a batch of 50,000 units and produces 50 units per machine hour, here is how the cost
assigned to the units with ABC and without ABC compares:
As the tables above illustrate, with activity-based costing the cost per unit decreases from $0.46 to $0.37 because the
cost of the setup activity is spread over 50,000 units instead of 5,000 units. Without ABC, the cost per unit is $0.40
regardless of the number of units in each batch. If companies base their selling prices on costs, a company not using
an ABC approach might lose the large batch work to a competitor who bids a lower price based on the lower, more
accurate overhead cost of $0.37. It's also possible that a company not using ABC may find itself being the low bidder
for manufacturing small batches of product, since its $0.40 is lower than the ABC model of $0.46 for a batch size of
This reading was recuperated on AccountingCoach PRO. Available in:
https://www.accountingcoach.com/activity-based-costing/explanation
https://www.accountingcoach.com/activity-based-costing/explanation/2
5,000 units. With its bid price based on manufacturing overhead of $0.40—but a true cost of $0.46—the company may
end up doing lots of production for little or no profit.
Our example with just two activities (production and setup) illustrates how the cost per unit using the activity-based
costing method is more accurate in reflecting the actual efforts associated with production. As companies began
measuring the costs of activities (instead of focusing on the accountant's departmental classifications), they began
using ABC cost information to practice activity based management. For example, with the cost of setting up a machine
now being measured and discussed, managers began to ask questions such as:
Why is the cost of setting up a production machine so expensive?
What can be done to reduce the setup cost?
If the setup costs cannot be reduced, are the selling prices adequate to cover all of the company's costs—including
the setup cost that was previously buried in the overall machine-hour overhead rate?
The company determines that $300,000 of its annual manufacturing overhead is associated with procurement and
material handling. As a result, the company removes $300,000 from the manufacturing overhead that will be allocated
via machine hours, and instead plans to allocate the $300,000 to the products based on the weight of the materials
used. The company expects that during the year it will procure and handle 3,000,000 pounds of material. Under activity-
based costing, the company will assign $0.10 ($300,000 divided by 3,000,000 pounds) per pound of product weight to
each unit manufactured. The end result is that the heavier parts will not only have more direct material cost, they will
also be assigned more factory overhead than the lighter parts. By assigning some manufacturing overhead to a product
based on the product's weight, the remaining manufacturing overhead assigned via machine hours will be reduced.
These points are illustrated in the following table:
In the table below, we can see how ABC would assign costs to the following:
1. A product that weighs 0.5 pound and is produced in a batch of 50,000 units at a rate of 50 per hour.
2. A product that weighs 1.5 pounds and is produced in a batch of 50,000 units at a rate of 50 per hour.
3. No activity-based costing allocations—all manufacturing overhead costs are allocated entirely via machine hours.