Proposed Project: GOLDEN HERON POULTRY FARM Date: 22-May-19

Owner: RONALDO LAGUADOR


Location: ONISAN, QUEZON

GOLDEN HERON SITE ACCOMPLISMENT REPORT


Date Date Estimated
Item Works Component / Activity % Complete Remarks and Pictures
Started Finished Amount
1 MOBILIZATION
Opening and grading of access road (right of way) from
3/14/2019 3/28/2019 700,000.00 100%
barangay road to the site (400 meters and mobilization of
equipment).

2 SITE DEVELOPMENT and EARHWORKS


Levelling and layout of the propose site of poultry houses, 3/28/2019 Ongoing 1,300,000.00 97.00%
slopes preparation and drainage ( Bulldozer, backhoe Rental).

3 WATER SYSTEM
Construction of Elevated water Tank (including mobilization of
a 4/1/2019 Ongoing 1,700,000.00 95.00%
materials and welders generator, foundation, steel structure
and water tank)

Prepared by: ENG'R. ELMER P. ATUN JR


CIVIL ENGINEER
PRC No.: 92467 - 01/25/2020 Approved by: RONALDO LAGUADOR
Page 1 of 2
Date Date Estimated
Item Works Component / Activity % Complete Remarks and Pictures
Started Finished Amount
Digging of deepwell (including motor pump and materials,
b 3/28/2019 5/20/2019 600,000.00 100.00%
labor for the construction of the pump house)

4 ELECTRIC POWER SYSTEM


Electric power system ( Electric posts from the barangay road
a to the site, procurement of transformer including labor and 4/7/2019 5/7/2019 750,000.00 100.00%
materials)

b Generator ( 125kva and 165 kva ) 3,062,000.00 100.00%

OVERALL PROGRESS OF ALL WORKS


8,112,000.00 98.67%
(total amount and percentage)

Prepared by: ENG'R. ELMER P. ATUN JR


CIVIL ENGINEER
PRC No.: 92467 - 01/25/2020 Approved by: RONALDO LAGUADOR
Page 2 of 2