You are on page 1of 13

Part II Annexure 1

N.C.Railway Month: 5/2019


PERFORMANCE PROGRESS REPORT
Cum. Up to the
S. No. Item From the month month
Current year
1 Track renewal (TRR units) P
Track renewal (TSR units) P
Track renewal (TRR units) S
Track renewal (TSR units) S
2 Ballast Supply ( Thou. Com )
3 Ballast inserted in track
4 Turn round of hoppers (days)
5 Deep Screening (Kms.)
I By M/C
II Manually
Total
III Mid Term Maintenance
IV With Track Renewal
6 Accident on Engg. Account (No)
I Prima facie cause
II Final cause
7 Laying of PSC turnout sleepers (Total)
I By M/C
II Manually
8a Output of CSM Machine (kms.)
8b Output of Unimat ( Nos of T/Out)
8c Output of BCM (Nos of T/Out)
9 Record by OMS-2000 (Km)
10 Rail/Weld failures ( Total Nos)
I Rail Failure
II Weld Failure
III Other Failures
IV Aoidable
11 Output of USFD Machine ( Km)
12 Welding ( no. of joints)
I FBWP
II AT welds
13 REhabilation of bridges ( Nos)
Replacement of girder bridges by ballasted deck
14
Strengthening of major bridge approaches ( Nos)
15
16 Scap offered to stores ( in MT) 0
17 Tree Plantation (in Lakhs) (a) Genl. (Babool) 0
(b) Jatropha --
(c) Began Beliya 0
18a Toe load measurement of ERC (Km) --
18b Greasing ofERC (Km) --
18c Painting of rail corrosion prone area (Km) --
19 Construction of boundary wall (RM) 0 0
20 Provision of channel sleepers -- --
North Central Railway
ANNEXURE-29

CAREGORY - WISE TRAINEES COMPLETED TRANING


PCDO for the month :- 5/2019 Railway / Unit--Sse/W/ALJN
INITIAL REFRESHER PROMOTIONAL DISETER MANAGEMENT OTHER SPECIALIZED TOTAL
COURSES
DEPARTMENT CATEGORY
Joined the Completed Joined the Completed Joined the Completed Joined the Completed Joined the Completed Joined the Completed
training training training training training training training training training training training training
ADMIN Not Concern
ACCT Not Concern
CIVIL Group-c -- -- -- -- -- -- -- -- -- -- -- --
MECH Not Concern
TPT Not Concern
COMML Not Concern
S&T Not Concern
MED Not Concern
PERS Not Concern
STORES Not Concern
RPF Not Concern
TOTAL 0 0 0 0 0 0 0 0 0 0 0 0
N.C.Railway
Month : 5/2019

Absentee Position of Group C & D staff under DEN/NCR/ALJN.


Absentee position of staff
S. No Type of Staff
Above 90 days Above 180 days Above 240 days Above 365 days

1 Group C --- --- --- ---

2 Group D --- --- --- ---


North Central Railway

TARGET OF VARIOUS WORKS OVER ALLAHABAD DIVISION FOR - 2017-18


DEN/ALJN PROGRESS
For the month Up to the
S.No Items Units
TARGET of month

5/2019 5/2019
(B) LEVEL CROSSING Nos.
1 (A) Closure of unmanned level crossing
2 (B) Improvement in infrastructure of unmanned level crossing
(C( Upgradation of level crossing 20 LC- 113, 115, 116,
118, 124, 130, 138,
142, 143, 145, 148,
3 150, (PB/865) 128,
134, 144, 151, (PB/77)
79, 80, 83, (PB/78) =
20
4 (F) Road widenning of LC 0
( C ) BRIDGE
5 (A) Rehabilitation of bridges Nos. 0
6 (B) Completion plans Nos. 0
7 ( C) Subway Nos 0
(D) PASSENGER AMENITY
8 Extension of plateforms for 24 coaches trains Stations 0
9 Devlopment of modal station (Civil Engg. Work) Nos 0
10 Washablen apron Stations 0
11 Raicing of platform to high level Stations 0
ACTION PLAN & TARGET OF CE/General
12 Disposal of scrap (C) works MT
(A) Quarters NO 0
(B) Sheds NO 0
(C) Cabins NO 0
(D) Water tanks NO 0
73.905 Tonne
(E) Other structures NO 0
Improvement of front/back doors including doors of bath / NO of
13 10 20
Latrine. doors 100
NO of 2 5
14 Treatment of roofs leakage of staff qtrs. quarters 100
NO of
50 (PB-514) In progress
15 Construction of new qtrs in replcement of abandoned qtrs. quarters
16 (A) Levelling & dressing of grounds (a) Around qtrs. Sqm (lac) 0.2
(B) Levelling & dressing of grounds (a) Around service bldgs. 0.2 0.2
17 Certication of mossing land plan 2 6
18 Removal of encroachment 10
North Central Railway
Period ending : 5/2019

Monthly progress of multi functional complex ( under execution by railway )

Progress Target date


Target date for
Site Contract of
Year of Area No. of Product Cost of fixing agency
S.No. Station idntified awarded Physical Detailed completion for O& M by Remarks
sanction ( Sqm) floors mix. MFC
(Yes/No) (Yes/No) (%) progress for MFC Commercial
building
Dept.

Nil
ANNEXURE : L&A-15

North Central Railway Month: 5/2019

REALISATION OF LICENSE FEE/LEASING CHARGES/WAY LEAVE CHARGES

(Figures in Crores of Rupees )


License fee/charges realized during
Previous year arrear
current year
To be Total
Realised at balance to
Realised Realised Realised
the end of Balance to During the Balance if be realised
during the during the during the
the previous month be realised month any
Year year
year
a b c d=(a-c) e f g h=(d-g)
Nil
North Central Railway
Annexure L&A-9
Month- 5/2019

Progress of plantation on Railway land


Boundary plantation Block position
Total
Plantation done Plantation done progresss (No.
Target Cumulative progress Target Cumulative progress of trees
during the month during the month

In route In route In route


No. trees No. trees No. trees In Ha. No. trees In Ha. No. trees In Ha. No. trees
km km km

1 2 3 4 5 6 7 8 9 10 11 12 13=(6+12)

0 0 0 0 0 0 0 0 0 0 0 0 0

Total 0
ANNEXURE: L&A-14

North Central Railway


Month: 5/2019
LAND PLANS

Balance as Completed
on 31 st
S.No. Description During the Up to the Balance
March of
month month
every year
Land plans to be authenticated by
1 6 - - 6
Revenue Authority
2 Scanning of Authenticated land plan - - - -

3 Uploading of scsnned land plans - - - -


North Central Railway
Annexure- A-6
Month: 5/2019
PROGRESS OF QUARTERS
PH-51

NOS. of Quarters NOS. of Quarters NOS. of Quarters Scanctioned as


NOS. of Quarters Constructed during the NOS. of Quarters under
Scanctioned as on 1st Scanctioned During on 31st March of previous Year
Current Year (D) Constructed (In Progress) (E)
Typeof April of Current Year (A) Current Year (B) (Out of (A) ) ( C)

During the month During the month Up to the month


CAP DRF Total CAP DRF Total CAP DRF Total
CAP DRF Total CAP DRF Total CAP DRF Total
II - - - - - - - - - - - - - 12 12 - 50 50
III - - - - - - - - - - - - - - - - - -
IV - 5 5 - - - - - - - - - - - - - - -
V - - - - - - - - - - - - - - - - - -

FOR PH OTHER THAN 51 (as a part of other works under PH-42, 64 etc)
Annexure: L&A1
North Central Railway Month: 5/2019

PROGRESS FOR ELIMINATION OF DEFICIENCIES IN MINIMUM ESSENTIAL AMENITITIES AT STATION


(RAILWAY BOARD'S CIRCULAR NO. 2012/LM (PA) /3/5 DATED 11.09.12)

No. of Station provided with MEA Cumulative No. of


Category Names of stations
Total No. of Stations provided with MEA up
of Station Up to end of previous During the current year indicated in column (4)
During the month to the month
year up to month
1 2 3 4 5 6=3+5 7
A-1 -

A-1 1 1
B -

C 1 1
D 5 5

E 8 8

F 4

Total 19 15

Note: Railway to ensure that PAMS Data on IRPSM Portal is updated accordingly.
ANNEXURE: L&A-12
North Central Railway
Month: 5/2019

STATUS OF LEASING/ LICENSING AGREEMENTS

No. of agreements No. of pending No. of pending No. of pending No. of Fresh
Balance pending
Total no. of to be executed at agreements agreement agreements agreements
agreements at the
agreements the end of the executed during executed during executed during executed during
end of the month
previous year the month the year the month the year

a b c d E=(b-d) F g
Nil
ANNEXXURE: L&A3
North Central Railway
Month: 5/2019
ADARSH STATIONS : MONTHLY PROGRESS REPORT - NCR

Cumulative Remarks
% progress Whether
year. of # Target* progress up (incl.
S. No. Name of Station Category during the developed
identification Month/ Year to the reasons for
month (Y/N)
month (%) delay, if any)

*. Target to be advised by 05.06.2014.


#. All remaining stations identified up to 2012-13 and 4 stations out of 6 stations in 2013-14 on NCR
are targeted for development during 2014-15 vide Board's letter No.2012/ LM(PA) 03/09/Adarsh for
stations dated 29.04.14.
North Central Railway
ANNEXURE L&A 8
Month: 5/2019
REMOVAL OF ENCROACHMENTS

Part "A" - Railway land including safety zone


Area of responsibility in Number of Number of
Existing
terms of joint procedure Encroachment/area Encroachment/area Resultatant
Encroachments As
S.No. order as per boards letter added(+) or removed added(+) or removed encroachment
on April-14
No. 98/LML/14/156 dated (-) during the month (-)
25.09.01 Number Area (ha) Number Area (ha) Number Area (ha) Number Area (ha)
(a) Within Station
1 67 0.989
permises (SSand RPF)
(b) Within/ around colony
2
permises (SE9w) and RPF
( C) In between station
3
(SE(P.Way) and RPF)
(d) In/around loco Sheds
4
(SE/Loco shed) and RPF)
(e) In/around carrige and
5
wagon depot
(f) In/around workshops
6
(SE(workshop) and RPF)
Total= 67 0.989

Part "B" Railway land in safety Zone alone


Number of
Existing Encroachments/area Resultant
S.No.
Encroachments added (+) or removed encroachment
(-)
Number Area (ha) Number Area (ha) Number Area (ha)
Nil

You might also like