PETRONAS GAS DEHYDRATION PLANT PHASE 2

TECHNICAL REQUISITION FOR


ENGINEERING SERVICES
REV.: A Attachment-3

ATTACHMENT-3

DEVIATION LIST

DEVIATIONS LIST
PETRONAS GAS DEHYDRATION PLANT PHASE 2
TECHNICAL REQUISITION FOR
ENGINEERING SERVICES
REV.: A Attachment-3

Sr. Document Clause Abstract of Description of Reason/ Alternate


No No. & Title No / Requiremen Deviation Justification Proposal
Section / t against for Deviation
Para which
deviation is
presented
1 FDP-113-52- 4.1 To be added CO2 Corrosion Factors
PRS-RE- to existing also depends on affecting CO2
GE-003 para. following factors corrosion are
1. Water wetting to be listed in
characteristics description to
2. Hydrocarbon CO2
Characteristics Corrosion.
3. Top of the line
wetting .
4. Partial
Pressure of
CO2
5. Temperature
6. pH
7. Carbonate
scale
2 FDP-113-52- 7.2 To be added CS+ CA 3 mm for
PRS-RE- to existing aboveground Not
GE-003 para. portion mentioned

3 FDP-113-52- 7.3 Zinc To be removed Sacrificial HC is not a


PRS-RE- Sacrificial anode will not good
GE-003 anode work at Hot Electrolyte.
located at the oil/Diesel
tank base for
mitigation of
corrosion
4 FDP-113-52- 7.11 SS 316L may To be added Basic material
PRS-RE- be used
GE-003
5 FDP-113-52- 8.4 Monitoring Frequency to be As per bast Frequency
PRS-RE- frequency for changed from international may be
GE-003 Cl,Dissolved monthly to 3-4 practices. increased /
metals, pH, times per week. decreased
Fe count, after
suspended corrosion
solids and rates are
chemical verified
residual-
Monthly
PETRONAS GAS DEHYDRATION PLANT PHASE 2
TECHNICAL REQUISITION FOR
ENGINEERING SERVICES
REV.: A Attachment-3

6 FDP-113-52- 8.4 NDE Frequency to be As per Frequency


PRS-RE- Methods-UT fixed on corrosion international may be
GE-003 on Annual rate half life best practices increased /
Basis philosophy or on decreased
RBI frequency or after
proposed by corrosion
Corrosion rates are
Specialist verified by
Corrosion
Specialist
7 FDP-113-52- 8.4 Guided wave Proposed As per Frequency
PRS-RE- frequency of frequency is 5 international may be
GE-003 2.5 years years or as per best practices increased /
Guided wave decreased
recommendations after
corrosion
rates are
verified by
Corrosion
Specialist
8 FDP-113-52- 8.4 CP TR Monitoring - As per Frequency
PRS-RE- inspection Monthly Basis. international may be
GE-003 Frequency of best practices increased /
2 years Potential survey- decreased
Bi annually after
corrosion
rates are
verified by
Corrosion
Specialist
PETRONAS GAS DEHYDRATION PLANT PHASE 2
TECHNICAL REQUISITION FOR
ENGINEERING SERVICES
REV.: A Attachment-3