HIRARC (Rev:_01_Year:_2018___)
PROJECT NAME: LARAK DEVELOPMENT PROJECT
ACTIVITY OR PROCESS CRITICAL / COMPLEX LIFTING Date :
Department (HIRARC owner): LARAK DEVELOPMENT PROJECT HIRARC No :
TANDEM LIFTING OF LARAK CELLAR DECK Location: SECTOR 1
Task/Process :
USING 2 UNITS OF MANITOWOC 16000 CRANE (400T) CONFIGURED WITH 72m BOOM LENGTH Larak Topside Consctruction Area
Specific Work area:
Explosive gas Working at height √ Work near crane walkway Traffic management Extreme weather √ Soil disturbance / erosion
Flammable materials Elevated work platform √ Slippery surface Moving parts Reduced visibility
Combustible materials Potential for difficult rescue Manual handling √ Unauthorized persons √ Communication √
Difficult entry/exit
Hazardous substances Noise - plant & equipment Air emissions - dust, fumes Lighting
✘ ✘ ✘ ✘ ✘ ✘
Penyediaan alatan
mengangkat seperti kren, site verification / suggestion on particular site verification / audit
gear mengangkat, wayar RISK date by PE, Supervisor or Foreman by HSE
sling dan shackles. LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
2. Obstruction with fabrication equipment To ensure crane pathway is clear and no
e.g. welding machine, gases rack or other obstruction from any object before lifting activity.
structure. RIGGER
Halangan dari alatan seperti mesin Memastikan laluan kren agar tidak terhalang B 2 RIGGER FOREMAN
welding, rak gas, dan struktur lain. oleh mana-mana objek yang boleh LIFTING SUPERVISOR
mengganggu semasa aktiviti mengangkat
dijalankan.
3. Pinch Point. Those rigger who are involved to have complete
Kecederaan pada jari. PPE before start the activity.impact resistance
glove
RIGGER
Rigger yang terlibat dalam aktiviti ini B 2 RIGGER FOREMAN
hendaklah memakai peralatan perlindungan LIFTING SUPERVISOR
yang lengkap.
4. Unfit Crane Operator Crane Operator to do Drug and Alcohol Test prior
Kren Operator tidak layak to Lifting Activity
Performing the lifting and manuevering of load (pick and carry) from initial position onto final position
3 Lifting, manuevering and final 1. Communication Failure. Toolbox & 4 point check briefing shall be Radio communication should be established to dedicated radio
positioning activity of load Komunikasi gagal. conducted before start the lifting activity. channel 3
(Cellar Deck from temporary RIGGER
support onto main support using Melakukan "Toolbox & 4 Point Check" sebelum Komunikasi menggunakan radio dengan menggunakan RIGGER FOREMAN
2 units of 400T Crane) aktivity dijalankan. B 4 saluran yang telah ditetapkan channel 3. LIFTING SUPERVISOR
RIGGING ENGINEER
HSE
Aktivity mengangkat,
membawa dan "positioning"
beban (Cellar Deck daripada 2. Crane breakdown. Ensure the cranes are inspected and accepted as Inspection checklist to be complete, PMA should be valid.
support sementara kepada Kren rosak. per inspection check sheet.
support utama menggunakan Senarai pemeriksaan harus lengkap, PMA harus disahkan . CRANE OPERATOR
2 unit 400T Kren) Pastikan kren telah diperiksa sebelum aktiviti B 4
LIFTING SUPERVISOR
mengangkat dijalankan.
3. Load Discrepancy Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to Personel from Engineering shall present at site during lifting activity to
Perbezaan berat beban Analisis vs be lifted at minimum height and reading of load acknowledge and approve decision made by Rigging Team to mitigate
Sebenar from Crane LMI shall be established. the Load Discrepency (if any)
RIGGING ENGINEER
"Test Lift" perlu dilakukan sebelum "Actual B 4 Wakil dari Engineering perlu berada di site ketika aktiviti lifting LIFTING SUPERVISOR
Lift", beban diangkat pada ketinggian minima untuk mengesahkan keputusan yang dilakukan oleh Rigging Team ENGINEERING
dan bacaan beban dari LMI Kren harus bagi menangani masalah Perbezaan Beban (jika ada)
dikenalpasti
beban (Cellar Deck daripada
support sementara kepada
support utama menggunakan
2 unit 400T Kren)
5. Uneven ground may cause unbalanced To ensure sufficient soil bearing capacity at lifting To put steel plate underneath crawler crane track if the soil bearing
condition to the crane during lifting area and determine the levelness of ground to insufficent / soft spot / water ponding.
operation. ensure stability of crane while lifting taken placed. RIGGER
Keadaan permukaan tanah yang tidak Sediakan / gunakan plat besi pada trek kren semasa bekerja di RIGGER FOREMAN
rata mengakibatkan kren tidak stabil Semak dan kenalpasti keadaan kekuatan tanah B 4 kawasan yang tidak rata/ kawsan lopak air atau permukaan tanah LIFTING SUPERVISOR
semasa bekerja mengangkat berdasarkan soil bearing data dan periksa yang lembut. RIGGING ENGINEER
permukaan tanah supaya sesuai dengan kerja
mengangkat
7. Unstable load. a) To ensure the wire slings get the tension first Hold for 2 minutes after lifting at minimum height above ground to
Beban tidak stabil. and trial lifting to check the COG (level of the load) ensure load is stable.
prior to start. RIGGER
Berhenti 2 minit selepas mengangkat beban tinggi minima dari RIGGER FOREMAN
Melakukan percubaan mengangkat dahulu B 3 bawah, untuk memastikan beban stabil. CRANE OPERATOR
beban, untuk melihat kestabilan beban LIFTING SUPERVISOR
sebelum aktiviti diteruskan.
8. Slewing too fast Crane operator need to follow instruction from Load travel at the minimum height (site justification) and speed.
"Slewing" teralu laju Supervisor / Signalman.
Perjalanan & kelajuan beban adalah pada ketinggian & kelajuan
Kren operator perlu mengikut arahan dari yang minimum.
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR
9. Traveling too fast. Crane operator need to follow instruction from Load travel at the minimum speed.
Bergerak terlalu laju. Supervisor / Signalman.
Perjalanan & kelajuan beban dalam kelajuan yang minimum.
Kren operator perlu mengikut arahan dari
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR
11. Wrong positioning Refference marking/indicator for final positioning Production personel shall be present during Lifting Toolbox to brief the
Salah posisi. shall be done by Prouction Team prior to Lifting team on Cellar Deck Positioning.
Activity
Wakil dari Production perlu hadir untuk Lifting Toolbox dan PRODUCTION
Tanda rujukan untuk kedudukan akhir perlu C 3 menjelaskan kepada Rigging Team berkenaan "Cellar Deck LIFTING ENGINEER
dilakukan oleh Production Team sebelum Positioning" LIFTING SUPERVISOR
aktiviti mengangkat dilakukan
12. Bad weather. Check weather forecast first before perform the Shall worst weather (lightning) during load lift/suspend, all operation
Cuaca buruk. lifting activity. shall stop and Crane Safety Pawls shall be activated.
Pastikan aktiviti mengangkat tidak dijalankan Sekiranya keadaan ribut petir ketika beban sedang diangkat, CRANE OPERATOR
semasa cuaca buruk. Periksa "Weather B 2 semua operasi haruslah dihentikan dan Crane Safety Pawls harus LIFTING SUPERVISOR
Forecast" terlebih dahulu sebelum memulakan digunakan. RIGGING ENGINEER
aktiviti ini.
site verification / suggestion on particular site verification / audit
RISK date by PE, Supervisor or Foreman by HSE
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
4 Dismantle the lifting gear after 1. Falling load. Slow down to lower the sling wire & ensure the
the load are secured / safely Beban terjatuh. load are fully secured / safely landing on the
landing on the Main Support support RIGGER
(Rigging Gear shall be release RIGGER FOREMAN
after 20% of Root Weldment for Perlahan-lahan menurunkan wayar sling dan A 2
CRANE OPERATOR
each column diameter) pastikan objek sudah selamat & stabil LIFTING SUPERVISOR
diletakkan di atas "support"
Membuka gear mengangkat
selepas beban selamat 2. Pinch point. Those rigger who are involved to have complete
diletakkan di atas Support Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
Utama gear & to avoid touching the load.
(Rigging Gear dilepaskan
selepas 20% daripada Root RIGGER
Rigger yang terlibat dalam aktiviti ini B 3 RIGGER FOREMAN
Weldment selesai untuk hendaklah memakai peralatan perlindungan
setiap column) LIFTING SUPERVISOR
yang lengkap & elakkan dari memegang
beban.
Completion of activity
5 Lifting activity completed. 1. Trip and fall Conduct proper housekeeping.
Tersadung dan jatuh. RIGGER
Aktiviti mengangkat selesai. Lakukan pembersihan dengan betul. A 1 RIGGER FOREMAN
LIFTING SUPERVISOR
2. Rigging gear left at work area. Supervisor to ensure all riggers to do proper
Alatan tidak si kemas / di simpan. housekeeing and no rigging gear & tools left at
work place.
RIGGER
Supervisor perlu memastikan semua pekerja A 1 RIGGER FOREMAN
melakukan pembersihan dan tiada alatan
mengangkat yang tertinggal di kawasan kerja.
Day 6 Day 7
Prepared by: Reviewed by: Approved by:
PROCESS OWNER HSE OFFICER / ENGINEER CONSTRUCTION MANAGER
Signature:
Signature: ________________ Signature:
Name :
Name: ________________ Name:
Designation: Designation: ________________ Designation:
Date :
Date: _________________ Date:
By By By By By By By
Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________
Sapura Fabrication Sdn. Bhd. (83307-K)
(Formerly known as SapuraKencana HL Sdn. Bhd.)
Plot D1, Lumut Port Industrial Park, Kg Acheh, Mukim of Lumut,
32000 Sitiawan, Perak Darul Ridzuan.
Tel : 05-692 3071 Fax : 05-6922609
HIRARC (Rev:_01_Year:_201
PROJECT NAME: PEGAGA DEVELOPMENT PROJECT
ACTIVITY OR PROCESS NON-ROUTINE (SIMPLE LIFT) Date :
Department (HIRARC owner): PEGAGA DEVELOPMENT PROJECT HIRARC No :
LIFTING AND FLIP OVER OF PEGAGA LAUNCH CRADLE Location:
Task/Process : USING OVERHEAD TRAVELLING CRANE (25T)
Specific Work area:
Explosive gas Working at height √ Work near crane walkway Traffic management Extreme weather
Flammable materials Elevated work platform √ Slippery surface Moving parts Reduced visibility
Combustible materials Potential for difficult rescue Manual handling √ Unauthorized persons √ Communication
Difficult entry/exit
Hazardous substances Noise - plant & equipment Air emissions - dust, fumes Lighting
✘ ✘ ✘ ✘ ✘ ✘
SECTOR 1
WORKSHOP 2
azard Source (√) Hazard Source (√) (Other hazard sources than stated)
material √ Vibration √
ed space General waste
e or isolated work Hazardous waste
me temperature Hydrocarbon / chemical spill
ed visibility
unication √
✘
Signalman √ Spill Kit
Briefing of HIRADC at work site (Prior to starting work for critical activity only)
Perkongsian HIRADC di tapak kerja kerja (sebelum memulakan aktiviti kritikal sahaja)
Note 1: ALARP - As Low As Reasonably Practicable - Where risk levels have been reduced to as safe level as possible but as to allow the completion of the task or activity.
Note 2: If high risk work is being performed, stop work. Management intervention is required if additional control measure (s) is/are unable to reduce the risk level.
Day 6 Day 7
e task or activity.
he risk level.
HAZARD IDENTIFICATION RISK ASSESSMENT
Pengenalpastian Hazad Penilaian Hazad
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
3. Pinch Point. Those rigger who are involved to have complete
Kecederaan pada jari. PPE before start the activity.impact resistance
glove
Performing the lifting and manuevering of load (pick and carry) from initial position onto final position
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE
RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR
RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR
RIGGER
RIGGER FOREMAN
CRANE OPERATOR
LIFTING SUPERVISOR
RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
3 Lifting, manuevering, flip-over 1. Communication Failure. Toolbox & 4 point check briefing shall be
and final positioning activity of Komunikasi gagal. conducted before start the lifting activity.
load (Launch Cradle using 25T
Overhead Travelling Crane) Melakukan "Toolbox & 4 Point Check" sebelum
aktivity dijalankan. B 4
Aktivity mengangkat,
membawa, memusing, dan
menempatkan beban (Launch
Cradle menggunakan 25T 2. Crane breakdown. Ensure the cranes are inspected and accepted as
Overhead Travelling Crane) Kren rosak. per inspection check sheet.
3. Load Levellness Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to
Perbezaan level Analisi vs Sebenar be lifted at minimum height and levelnes should
be established.
The load shall be set back to initial position and rigging arrangement
(add/remove shackles) shall be adjusted based on actual load
levellness (if any)
LIFTING SUPERVISOR
Beban dikembalikan ke kedudukan asal dan "rigging arrangment" RIGGING FOREMAN
(menambah / mengurangkan shackle) dilakukan berdasarkan RIGGING ENGINEER
keadaan levellness sebenar
BANKSMAN
SIGNALMAN
LIFTING SUPERVISOR
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
5. Unstable load. a) To ensure the wire slings get the tension first
Beban tidak stabil. and trial lifting to check the COG (level of the load)
prior to start.
10. Bad weather. Check weather forecast first before perform the
Cuaca buruk. lifting activity.
4 Dismantle the lifting gear after 1. Falling load. Slow down to lower the sling wire & ensure the
the load are secured / safely Beban terjatuh. load are fully secured / safely landing on the
landing on the Main Support support
(Rigging Gear shall be release
after load is securely position Perlahan-lahan menurunkan wayar sling dan A 2
onto final position) pastikan objek sudah selamat & stabil
diletakkan di atas "support"
Membuka gear mengangkat
selepas beban selamat
diletakkan di atas Support
Utama
(Rigging Gear dilepaskan
selepas beban telah
diletakkan pada posisi
terakhir)
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE
RIGGER
RIGGER FOREMAN
SIGNALMAN
LIFTING SUPERVISOR
Wakil dari Production perlu hadir untuk Lifting Toolbox dan PRODUCTION
menjelaskan kepada Rigging Team berkenaan "Cellar Deck LIFTING ENGINEER
Positioning" LIFTING SUPERVISOR
Sekiranya keadaan ribut petir ketika beban sedang diangkat, CRANE OPERATOR
semua operasi haruslah dihentikan dan Crane Safety Pawls harus LIFTING SUPERVISOR
digunakan. RIGGING ENGINEER
RIGGER
RIGGER FOREMAN
CRANE OPERATOR
LIFTING SUPERVISOR
4 Dismantle the lifting gear after
the load are secured / safely
landing on the Main Support
(Rigging Gear shall be release RISK
after load is securely position LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No onto final position) OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
Membuka gear mengangkat RISIKO
selepas beban selamat 2. Pinch point. Those rigger who are involved to have complete
diletakkan di atas Support Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
Utama gear & to avoid touching the load.
(Rigging Gear dilepaskan
selepas beban telah Rigger yang terlibat dalam aktiviti ini
diletakkan pada posisi B 3
hendaklah memakai peralatan perlindungan
terakhir) yang lengkap & elakkan dari memegang
beban.
Completion of activity
5 Lifting activity completed. 1. Trip and fall Conduct proper housekeeping.
Tersadung dan jatuh.
Aktiviti mengangkat selesai. Lakukan pembersihan dengan betul. A 1
2. Rigging gear left at work area. Supervisor to ensure all riggers to do proper
Alatan tidak si kemas / di simpan. housekeeing and no rigging gear & tools left at
work place.
Date :
Date: _________________ Date:
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE
RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR
RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR
RIGGER
RIGGER FOREMAN
Approved by:
CONSTRUCTION MANAGER
Signature:
Designation:
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
By By By By
Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE
Day 4 Day 5
Day 6 Day 7
By By By
_________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________
Sapura Fabrication Sdn. Bhd. (83307-K)
(Formerly known as SapuraKencana HL Sdn. Bhd.)
Plot D1, Lumut Port Industrial Park, Kg Acheh, Mukim of Lumut,
32000 Sitiawan, Perak Darul Ridzuan.
Tel : 05-692 3071 Fax : 05-6922609
HIRARC (Rev:_01_Year:_2018___)
PROJECT NAME: PEGAGA DEVELOPMENT PROJECT
ACTIVITY OR PROCESS CRITICAL / COMPLEX LIFTING Date :
Department (HIRARC owner): PEGAGA DEVELOPMENT PROJECT HIRARC No :
TANDEM LIFTING AND FLIP OVER OF PEGAGA LAUNCH CRADLE Location: SECTOR 1
Task/Process :
USING 2 UNITS OF OVERHEAD TRAVELLING CRANE (25T) WORKSHOP 2
Specific Work area:
Explosive gas Working at height √ Work near crane walkway Traffic management Extreme weather √ Soil disturbance / erosion
Flammable materials Elevated work platform √ Slippery surface Moving parts Reduced visibility
Combustible materials Potential for difficult rescue Manual handling √ Unauthorized persons √ Communication √
Difficult entry/exit
Hazardous substances Noise - plant & equipment Air emissions - dust, fumes Lighting
✘ ✘ ✘ ✘ ✘ ✘
Penyediaan alatan
mengangkat seperti kren, site verification / suggestion on particular site verification / audit
gear mengangkat, wayar RISK date by PE, Supervisor or Foreman by HSE
sling dan shackles. LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
2. Obstruction with fabrication equipment To ensure crane pathway is clear and no
e.g. welding machine, gases rack or other obstruction from any object before lifting activity.
structure. RIGGER
Halangan dari alatan seperti mesin Memastikan laluan kren agar tidak terhalang B 2 RIGGER FOREMAN
welding, rak gas, dan struktur lain. oleh mana-mana objek yang boleh LIFTING SUPERVISOR
mengganggu semasa aktiviti mengangkat
dijalankan.
3. Pinch Point. Those rigger who are involved to have complete
Kecederaan pada jari. PPE before start the activity.impact resistance
glove
RIGGER
Rigger yang terlibat dalam aktiviti ini B 2 RIGGER FOREMAN
hendaklah memakai peralatan perlindungan LIFTING SUPERVISOR
yang lengkap.
4. Unfit Crane Operator Crane Operator to do Drug and Alcohol Test prior
Kren Operator tidak layak to Lifting Activity
Performing the lifting and manuevering of load (pick and carry) from initial position onto final position
3 Lifting, manuevering, flip-over 1. Communication Failure. Toolbox & 4 point check briefing shall be Radio communication should be established to dedicated radio
and final positioning activity of Komunikasi gagal. conducted before start the lifting activity. channel 3
load (Launch Cradle using 2 RIGGER
units of 25T Overhead Travelling Melakukan "Toolbox & 4 Point Check" sebelum Komunikasi menggunakan radio dengan menggunakan RIGGER FOREMAN
Crane) aktivity dijalankan. B 4 saluran yang telah ditetapkan channel 3. LIFTING SUPERVISOR
RIGGING ENGINEER
HSE
Aktivity mengangkat,
membawa dan "positioning"
beban (Launch Cradle 2. Crane breakdown. Ensure the cranes are inspected and accepted as Inspection checklist to be complete, PMA should be valid.
menggunakan 2 unit 25T Kren rosak. per inspection check sheet.
Overhead Travelling Crane) Senarai pemeriksaan harus lengkap, PMA harus disahkan . CRANE OPERATOR
Pastikan kren telah diperiksa sebelum aktiviti B 4
LIFTING SUPERVISOR
mengangkat dijalankan.
3. Load Discrepancy Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to Personel from Engineering shall present at site during lifting activity to
Perbezaan berat beban Analisis vs be lifted at minimum height and reading of load acknowledge and approve decision made by Rigging Team to mitigate
Sebenar from Crane LMI shall be established. the Load Discrepency (if any)
RIGGING ENGINEER
"Test Lift" perlu dilakukan sebelum "Actual B 4 Wakil dari Engineering perlu berada di site ketika aktiviti lifting LIFTING SUPERVISOR
Lift", beban diangkat pada ketinggian minima untuk mengesahkan keputusan yang dilakukan oleh Rigging Team ENGINEERING
dan bacaan beban dari LMI Kren harus bagi menangani masalah Perbezaan Beban (jika ada)
dikenalpasti
beban (Launch Cradle
menggunakan 2 unit 25T
Overhead Travelling Crane)
6. Unstable load. a) To ensure the wire slings get the tension first Hold for 2 minutes after lifting at minimum height above ground to
Beban tidak stabil. and trial lifting to check the COG (level of the load) ensure load is stable.
prior to start. RIGGER
Berhenti 2 minit selepas mengangkat beban tinggi minima dari RIGGER FOREMAN
Melakukan percubaan mengangkat dahulu B 3 bawah, untuk memastikan beban stabil. CRANE OPERATOR
beban, untuk melihat kestabilan beban LIFTING SUPERVISOR
sebelum aktiviti diteruskan.
7. Slewing too fast Crane operator need to follow instruction from Load travel at the minimum height (site justification) and speed.
"Slewing" teralu laju Supervisor / Signalman.
Perjalanan & kelajuan beban adalah pada ketinggian & kelajuan
Kren operator perlu mengikut arahan dari yang minimum.
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR
8. Traveling too fast. Crane operator need to follow instruction from Load travel at the minimum speed.
Bergerak terlalu laju. Supervisor / Signalman.
Perjalanan & kelajuan beban dalam kelajuan yang minimum.
Kren operator perlu mengikut arahan dari
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR
10. Wrong positioning Refference marking/indicator for final positioning Production personel shall be present during Lifting Toolbox to brief the
Salah posisi. shall be done by Prouction Team prior to Lifting team on Cellar Deck Positioning.
Activity
Wakil dari Production perlu hadir untuk Lifting Toolbox dan PRODUCTION
Tanda rujukan untuk kedudukan akhir perlu C 3 menjelaskan kepada Rigging Team berkenaan "Cellar Deck LIFTING ENGINEER
dilakukan oleh Production Team sebelum Positioning" LIFTING SUPERVISOR
aktiviti mengangkat dilakukan
11. Bad weather. Check weather forecast first before perform the Shall worst weather (lightning) during load lift/suspend, all operation
Cuaca buruk. lifting activity. shall stop and Crane Safety Pawls shall be activated.
Pastikan aktiviti mengangkat tidak dijalankan Sekiranya keadaan ribut petir ketika beban sedang diangkat, CRANE OPERATOR
semasa cuaca buruk. Periksa "Weather B 2 semua operasi haruslah dihentikan dan Crane Safety Pawls harus LIFTING SUPERVISOR
Forecast" terlebih dahulu sebelum memulakan digunakan. RIGGING ENGINEER
aktiviti ini.
4 Dismantle the lifting gear after 1. Falling load. Slow down to lower the sling wire & ensure the
the load are secured / safely Beban terjatuh. load are fully secured / safely landing on the
landing on the Main Support support RIGGER
(Rigging Gear shall be release RIGGER FOREMAN
after load is securely position Perlahan-lahan menurunkan wayar sling dan A 2
CRANE OPERATOR
onto final position) pastikan objek sudah selamat & stabil LIFTING SUPERVISOR
diletakkan di atas "support"
Membuka gear mengangkat
selepas beban selamat
diletakkan di atas Support
Utama
(Rigging Gear dilepaskan
selepas beban telah
diletakkan pada posisi
terakhir)
4 Dismantle the lifting gear after
the load are secured / safely
landing on the Main Support site verification / suggestion on particular site verification / audit
(Rigging Gear shall be release RISK date by PE, Supervisor or Foreman by HSE
after load is securely position LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No onto final position) H/M/L/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE
GKALIAN KAN
Membuka gear mengangkat RISIKO
selepas beban selamat 2. Pinch point. Those rigger who are involved to have complete
diletakkan di atas Support Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
Utama gear & to avoid touching the load.
(Rigging Gear dilepaskan
selepas beban telah RIGGER
Rigger yang terlibat dalam aktiviti ini B 3 RIGGER FOREMAN
diletakkan pada posisi hendaklah memakai peralatan perlindungan
terakhir) LIFTING SUPERVISOR
yang lengkap & elakkan dari memegang
beban.
Completion of activity
5 Lifting activity completed. 1. Trip and fall Conduct proper housekeeping.
Tersadung dan jatuh. RIGGER
Aktiviti mengangkat selesai. Lakukan pembersihan dengan betul. A 1 RIGGER FOREMAN
LIFTING SUPERVISOR
2. Rigging gear left at work area. Supervisor to ensure all riggers to do proper
Alatan tidak si kemas / di simpan. housekeeing and no rigging gear & tools left at
work place.
RIGGER
Supervisor perlu memastikan semua pekerja A 1 RIGGER FOREMAN
melakukan pembersihan dan tiada alatan
mengangkat yang tertinggal di kawasan kerja.
Date :
Date: _________________ Date:
By By By By By By By
Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________