You are on page 1of 26

Sapura Fabrication Sdn. Bhd.

(83307-K)
(Formerly known as SapuraKencana HL Sdn. Bhd.)
Plot D1, Lumut Port Industrial Park, Kg Acheh, Mukim of Lumut,
32000 Sitiawan, Perak Darul Ridzuan.
Tel : 05-692 3071 Fax : 05-6922609
HIRARC (Rev:_01_Year:_2018___)
PROJECT NAME: LARAK DEVELOPMENT PROJECT
ACTIVITY OR PROCESS CRITICAL / COMPLEX LIFTING Date :
Department (HIRARC owner): LARAK DEVELOPMENT PROJECT HIRARC No :
TANDEM LIFTING OF LARAK CELLAR DECK Location: SECTOR 1
Task/Process :
USING 2 UNITS OF MANITOWOC 16000 CRANE (400T) CONFIGURED WITH 72m BOOM LENGTH Larak Topside Consctruction Area
Specific Work area:

HAZARD IDENTIFICATION - tick all that apply, add additional as necessary


Hazard Source (√) Hazard Source (√) Hazard Source (√) Hazard Source (√) Hazard Source (√) Hazard Source (√) (Other hazard sources than stated)
Trip hazards √ Radiation Suspended load √ Line of fire √ Sharp material √ Vibration √
Falling objects √ Electrical hazards - LV / HV Engulfment Pressurised fluid Confined space General waste
Oxygen deficiency/excess Multiple electrical feeds Live rails - gantry crane Pressurised air / gas Remote or isolated work Hazardous waste
Poisonous gas Ladders √ Working near crane √ Moving / mobile plant Extreme temperature Hydrocarbon / chemical spill

Explosive gas Working at height √ Work near crane walkway Traffic management Extreme weather √ Soil disturbance / erosion

Flammable materials Elevated work platform √ Slippery surface Moving parts Reduced visibility
Combustible materials Potential for difficult rescue Manual handling √ Unauthorized persons √ Communication √
Difficult entry/exit
Hazardous substances Noise - plant & equipment Air emissions - dust, fumes Lighting

CONTROLS: PPE - tick all that apply


OTHER PPE (if required):

✘ ✘ ✘ ✘ ✘ ✘

Safety equipment or controls required:


Fire Watcher Lock-out / tag out system Ventilation
Barriers √ Fire extinguishers √ Lighting
Warning signs √ Scaffolding tag √ Earthing
O
Banksman √ Pocket Dosimeter Fire Blanket N
Signalman √ Spill Kit -
Personal Film Badge First Aid Box S
Additional safety equipment/control measures if required: I
T
E
B
R
Briefing of HIRADC at work site (Prior to starting work for critical activity only) I
Perkongsian HIRADC di tapak kerja kerja (sebelum memulakan aktiviti kritikal sahaja) Day 6 Day 7
E
Note 1: ALARP - As Low As Reasonably Practicable - Where risk levels have been reduced to as safe level as possible but as to allowFthe completion of the task or activity.
Note 2: If high risk work is being performed, stop work. Management intervention is required if additional control measure (s) is/are
I unable to reduce the risk level.
N
G SITE VERIFICATION
DETERMINING CONTROL PBED
HAZARD IDENTIFICATION RISK ASSESSMENT Penentuan Langkah Kawalan Penilaian tapak kerja (JHA Audit)
(
Pengenalpastian Hazad Penilaian Hazad
P
R
I Elimination Substitution Engineering Administrative PPE
Penghapusan Penggantian Kejuruteraan Pentadbiran PPE
O site verification / suggestion on particular site verification / audit
R LIKELIH SEVER RISK date by PE, Supervisor or Foreman by HSE
Specific Activity Hazard Identified Existing Control Measures T OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada O KEBARAN KETERU PENILAIAN Saranan langkah keselamatan
GKALIAN KAN
S RISIKO

Preparation and setting of the lifting gear prior to lifting T


1 a) Preparation of the lifting 1. Wrong lifting gear (low capacity). To inspect lifting gear as per inspection check A Lifing plan to be established to determine the correct lifting gears to be
equipment e.g. crane, lifting Gear angkat yang salah (kapasiti sheet by relevant party & to ensure the capacity R
of used , the gears are to comply with SFSB colour coding inspection and
gear, sling wire, shackles. rendah). lifting gear as per approved procedure. TI to be visually inspected for damages before use.
N
Penyediaan alatan Periksa gear mengangkat seperti dalam Pelan mengangkat perlu dikeluarkan untuk mengenal pasti gear RIGGER
mengangkat seperti kren, senarai pemeriksaan dan diperiksa oleh pihak
G A 4 mengangkat yang digunakan adalah betul, dan selaras dengan RIGGER FOREMAN
gear mengangkat, wayar yang berkenaan untuk memastikan kapasiti W SFSB pemeriksaan kod warna dan lakukan pemeriksaan visual LIFTING SUPERVISOR
sling dan shackles. gear mengangkat seperti di dalam prosedur O untuk kerosakan sebelum digunakan.
yang telah diluluskan. R
K
F
O
R
C
R
IT
I
C
A
L
A
C
TI
1 a) Preparation of the lifting
equipment e.g. crane, lifting
gear, sling wire, shackles.

Penyediaan alatan
mengangkat seperti kren, site verification / suggestion on particular site verification / audit
gear mengangkat, wayar RISK date by PE, Supervisor or Foreman by HSE
sling dan shackles. LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
2. Obstruction with fabrication equipment To ensure crane pathway is clear and no
e.g. welding machine, gases rack or other obstruction from any object before lifting activity.
structure. RIGGER
Halangan dari alatan seperti mesin Memastikan laluan kren agar tidak terhalang B 2 RIGGER FOREMAN
welding, rak gas, dan struktur lain. oleh mana-mana objek yang boleh LIFTING SUPERVISOR
mengganggu semasa aktiviti mengangkat
dijalankan.
3. Pinch Point. Those rigger who are involved to have complete
Kecederaan pada jari. PPE before start the activity.impact resistance
glove
RIGGER
Rigger yang terlibat dalam aktiviti ini B 2 RIGGER FOREMAN
hendaklah memakai peralatan perlindungan LIFTING SUPERVISOR
yang lengkap.

4. Unfit Crane Operator Crane Operator to do Drug and Alcohol Test prior
Kren Operator tidak layak to Lifting Activity

Operator Crane perlu melalui ujian dadah dan


alkohol sebelum memulakan aktiviti B 2 CRANE OPERATOR
mengangkat

5. Miscommunication. Approved procedure to be cascade down to the


Salah faham. team involved in the activities.
RIGGER
Prosedur yang telah diluluskan perlulah B 2 RIGGER FOREMAN
diberitahu pada semua pekerja yang terlibat LIFTING SUPERVISOR
dalam aktiviti ini.

Installation / rig up the lifting gears


2 Installation or rig up the lifting 1. Falling load. Slow down to lower the sling wire & ensure the
gear prior to Critical Lifting Beban terjatuh. load are fully secured / safely landing on the
Activity support RIGGER
RIGGER FOREMAN
Memasang gear mengangkat Perlahan-lahan menurunkan wayar sling dan A 2
CRANE OPERATOR
sebelum menjalankan Aktiviti pastikan objek sudah selamat & stabil LIFTING SUPERVISOR
Kritical Lifting diletakkan di atas "support"

2. Pinch point. Those rigger who are involved to have complete


Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
gear & to avoid touching the load.
RIGGER
Rigger yang terlibat dalam aktiviti ini
B 3 RIGGER FOREMAN
hendaklah memakai peralatan perlindungan LIFTING SUPERVISOR
yang lengkap & elakkan dari memegang
beban.

Performing the lifting and manuevering of load (pick and carry) from initial position onto final position
3 Lifting, manuevering and final 1. Communication Failure. Toolbox & 4 point check briefing shall be Radio communication should be established to dedicated radio
positioning activity of load Komunikasi gagal. conducted before start the lifting activity. channel 3
(Cellar Deck from temporary RIGGER
support onto main support using Melakukan "Toolbox & 4 Point Check" sebelum Komunikasi menggunakan radio dengan menggunakan RIGGER FOREMAN
2 units of 400T Crane) aktivity dijalankan. B 4 saluran yang telah ditetapkan channel 3. LIFTING SUPERVISOR
RIGGING ENGINEER
HSE
Aktivity mengangkat,
membawa dan "positioning"
beban (Cellar Deck daripada 2. Crane breakdown. Ensure the cranes are inspected and accepted as Inspection checklist to be complete, PMA should be valid.
support sementara kepada Kren rosak. per inspection check sheet.
support utama menggunakan Senarai pemeriksaan harus lengkap, PMA harus disahkan . CRANE OPERATOR
2 unit 400T Kren) Pastikan kren telah diperiksa sebelum aktiviti B 4
LIFTING SUPERVISOR
mengangkat dijalankan.

3. Load Discrepancy Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to Personel from Engineering shall present at site during lifting activity to
Perbezaan berat beban Analisis vs be lifted at minimum height and reading of load acknowledge and approve decision made by Rigging Team to mitigate
Sebenar from Crane LMI shall be established. the Load Discrepency (if any)
RIGGING ENGINEER
"Test Lift" perlu dilakukan sebelum "Actual B 4 Wakil dari Engineering perlu berada di site ketika aktiviti lifting LIFTING SUPERVISOR
Lift", beban diangkat pada ketinggian minima untuk mengesahkan keputusan yang dilakukan oleh Rigging Team ENGINEERING
dan bacaan beban dari LMI Kren harus bagi menangani masalah Perbezaan Beban (jika ada)
dikenalpasti
beban (Cellar Deck daripada
support sementara kepada
support utama menggunakan
2 unit 400T Kren)

site verification / suggestion on particular site verification / audit


RISK date by PE, Supervisor or Foreman by HSE
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
4. Load Levellness Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to The load shall be set back to initial position and rigging arrangement
Perbezaan level Analisi vs Sebenar be lifted at minimum height and levelnes should (add/remove shackles) shall be adjusted based on actual load
be established. levellness (if any)
LIFTING SUPERVISOR
"Test Lift" perlu dilakukan sebelum "Actual B 4 Beban dikembalikan ke kedudukan asal dan "rigging arrangment" RIGGING FOREMAN
Lift", beban diangkat pada ketinggian minima (menambah / mengurangkan shackle) dilakukan berdasarkan RIGGING ENGINEER
dan levellness beban dikenalpasti keadaan levellness sebenar

5. Uneven ground may cause unbalanced To ensure sufficient soil bearing capacity at lifting To put steel plate underneath crawler crane track if the soil bearing
condition to the crane during lifting area and determine the levelness of ground to insufficent / soft spot / water ponding.
operation. ensure stability of crane while lifting taken placed. RIGGER
Keadaan permukaan tanah yang tidak Sediakan / gunakan plat besi pada trek kren semasa bekerja di RIGGER FOREMAN
rata mengakibatkan kren tidak stabil Semak dan kenalpasti keadaan kekuatan tanah B 4 kawasan yang tidak rata/ kawsan lopak air atau permukaan tanah LIFTING SUPERVISOR
semasa bekerja mengangkat berdasarkan soil bearing data dan periksa yang lembut. RIGGING ENGINEER
permukaan tanah supaya sesuai dengan kerja
mengangkat

6. Unathorised person. Unauthorised person are not allowed to stand


Pekerja yang tidak terlibat. nearby the lifting area. Put barricade & lifting
signage during to perform the activity.
BANKSMAN
Pekerja yang tidak terlibat tidak dibenarkan
B 2 SIGNALMAN
berada di kawasan mengangkat. Letakkan
LIFTING SUPERVISOR
penghadang & pamerkan papan tanda "Lifting
Area" semasa menjalankan aktiviti ini.

7. Unstable load. a) To ensure the wire slings get the tension first Hold for 2 minutes after lifting at minimum height above ground to
Beban tidak stabil. and trial lifting to check the COG (level of the load) ensure load is stable.
prior to start. RIGGER
Berhenti 2 minit selepas mengangkat beban tinggi minima dari RIGGER FOREMAN
Melakukan percubaan mengangkat dahulu B 3 bawah, untuk memastikan beban stabil. CRANE OPERATOR
beban, untuk melihat kestabilan beban LIFTING SUPERVISOR
sebelum aktiviti diteruskan.

8. Slewing too fast Crane operator need to follow instruction from Load travel at the minimum height (site justification) and speed.
"Slewing" teralu laju Supervisor / Signalman.
Perjalanan & kelajuan beban adalah pada ketinggian & kelajuan
Kren operator perlu mengikut arahan dari yang minimum.
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR

9. Traveling too fast. Crane operator need to follow instruction from Load travel at the minimum speed.
Bergerak terlalu laju. Supervisor / Signalman.
Perjalanan & kelajuan beban dalam kelajuan yang minimum.
Kren operator perlu mengikut arahan dari
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR

10. Working At Height Body Harness, Only authorized personnel shall be


Bekerja di tempat tinggi allowed to be working at height
RIGGER
Abah-abah. Hanya personel yang berkaitan RIGGER FOREMAN
sahaja dibenarkan bekerja di tempat tinggi B 2
SIGNALMAN
LIFTING SUPERVISOR

11. Wrong positioning Refference marking/indicator for final positioning Production personel shall be present during Lifting Toolbox to brief the
Salah posisi. shall be done by Prouction Team prior to Lifting team on Cellar Deck Positioning.
Activity
Wakil dari Production perlu hadir untuk Lifting Toolbox dan PRODUCTION
Tanda rujukan untuk kedudukan akhir perlu C 3 menjelaskan kepada Rigging Team berkenaan "Cellar Deck LIFTING ENGINEER
dilakukan oleh Production Team sebelum Positioning" LIFTING SUPERVISOR
aktiviti mengangkat dilakukan

12. Bad weather. Check weather forecast first before perform the Shall worst weather (lightning) during load lift/suspend, all operation
Cuaca buruk. lifting activity. shall stop and Crane Safety Pawls shall be activated.

Pastikan aktiviti mengangkat tidak dijalankan Sekiranya keadaan ribut petir ketika beban sedang diangkat, CRANE OPERATOR
semasa cuaca buruk. Periksa "Weather B 2 semua operasi haruslah dihentikan dan Crane Safety Pawls harus LIFTING SUPERVISOR
Forecast" terlebih dahulu sebelum memulakan digunakan. RIGGING ENGINEER
aktiviti ini.
site verification / suggestion on particular site verification / audit
RISK date by PE, Supervisor or Foreman by HSE
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
4 Dismantle the lifting gear after 1. Falling load. Slow down to lower the sling wire & ensure the
the load are secured / safely Beban terjatuh. load are fully secured / safely landing on the
landing on the Main Support support RIGGER
(Rigging Gear shall be release RIGGER FOREMAN
after 20% of Root Weldment for Perlahan-lahan menurunkan wayar sling dan A 2
CRANE OPERATOR
each column diameter) pastikan objek sudah selamat & stabil LIFTING SUPERVISOR
diletakkan di atas "support"
Membuka gear mengangkat
selepas beban selamat 2. Pinch point. Those rigger who are involved to have complete
diletakkan di atas Support Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
Utama gear & to avoid touching the load.
(Rigging Gear dilepaskan
selepas 20% daripada Root RIGGER
Rigger yang terlibat dalam aktiviti ini B 3 RIGGER FOREMAN
Weldment selesai untuk hendaklah memakai peralatan perlindungan
setiap column) LIFTING SUPERVISOR
yang lengkap & elakkan dari memegang
beban.

Completion of activity
5 Lifting activity completed. 1. Trip and fall Conduct proper housekeeping.
Tersadung dan jatuh. RIGGER
Aktiviti mengangkat selesai. Lakukan pembersihan dengan betul. A 1 RIGGER FOREMAN
LIFTING SUPERVISOR

2. Rigging gear left at work area. Supervisor to ensure all riggers to do proper
Alatan tidak si kemas / di simpan. housekeeing and no rigging gear & tools left at
work place.
RIGGER
Supervisor perlu memastikan semua pekerja A 1 RIGGER FOREMAN
melakukan pembersihan dan tiada alatan
mengangkat yang tertinggal di kawasan kerja.
Day 6 Day 7
Prepared by: Reviewed by: Approved by:
PROCESS OWNER HSE OFFICER / ENGINEER CONSTRUCTION MANAGER
Signature:
Signature: ________________ Signature:
Name :
Name: ________________ Name:
Designation: Designation: ________________ Designation:

Date :
Date: _________________ Date:

Debriefing of HIRARC at work site


Perkongsian HIRARC di tapak kerja setelah tamat kerja

Day 1 Day 2 Day 3 Day 4 Day 5

Date Date Date Date Date Date Date


Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : __________________

By By By By By By By
Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________
Sapura Fabrication Sdn. Bhd. (83307-K)
(Formerly known as SapuraKencana HL Sdn. Bhd.)
Plot D1, Lumut Port Industrial Park, Kg Acheh, Mukim of Lumut,
32000 Sitiawan, Perak Darul Ridzuan.
Tel : 05-692 3071 Fax : 05-6922609
HIRARC (Rev:_01_Year:_201
PROJECT NAME: PEGAGA DEVELOPMENT PROJECT
ACTIVITY OR PROCESS NON-ROUTINE (SIMPLE LIFT) Date :
Department (HIRARC owner): PEGAGA DEVELOPMENT PROJECT HIRARC No :
LIFTING AND FLIP OVER OF PEGAGA LAUNCH CRADLE Location:
Task/Process : USING OVERHEAD TRAVELLING CRANE (25T)
Specific Work area:

HAZARD IDENTIFICATION - tick all that apply, add additional as necessary


Hazard Source (√) Hazard Source (√) Hazard Source (√) Hazard Source (√) Hazard Source
Trip hazards √ Radiation Suspended load √ Line of fire √ Sharp material
Falling objects √ Electrical hazards - LV / HV Engulfment Pressurised fluid Confined space
Oxygen deficiency/excess Multiple electrical feeds Live rails - gantry crane Pressurised air / gas Remote or isolated work
Poisonous gas Ladders √ Working near crane √ Moving / mobile plant Extreme temperature

Explosive gas Working at height √ Work near crane walkway Traffic management Extreme weather

Flammable materials Elevated work platform √ Slippery surface Moving parts Reduced visibility
Combustible materials Potential for difficult rescue Manual handling √ Unauthorized persons √ Communication
Difficult entry/exit
Hazardous substances Noise - plant & equipment Air emissions - dust, fumes Lighting

CONTROLS: PPE - tick all that apply

✘ ✘ ✘ ✘ ✘ ✘

Safety equipment or controls required:


Fire Watcher Lock-out / tag out system Ventilation
Barriers √ Fire extinguishers √ Lighting
Warning signs √ Scaffolding tag √ Earthing
O
Banksman √ Pocket Dosimeter Fire Blanket N
-
S
I
T
(Rev:_01_Year:_2018___)

SECTOR 1
WORKSHOP 2

azard Source (√) Hazard Source (√) (Other hazard sources than stated)
material √ Vibration √
ed space General waste
e or isolated work Hazardous waste
me temperature Hydrocarbon / chemical spill

me weather √ Soil disturbance / erosion

ed visibility
unication √

OLS: PPE - tick all that apply


OTHER PPE (if required):


Signalman √ Spill Kit

Personal Film Badge First Aid Box

Additional safety equipment/control measures if required:

Briefing of HIRADC at work site (Prior to starting work for critical activity only)
Perkongsian HIRADC di tapak kerja kerja (sebelum memulakan aktiviti kritikal sahaja)
Note 1: ALARP - As Low As Reasonably Practicable - Where risk levels have been reduced to as safe level as possible but as to allow the completion of the task or activity.
Note 2: If high risk work is being performed, stop work. Management intervention is required if additional control measure (s) is/are unable to reduce the risk level.
Day 6 Day 7
e task or activity.
he risk level.
HAZARD IDENTIFICATION RISK ASSESSMENT
Pengenalpastian Hazad Penilaian Hazad

RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO

Preparation and setting of the lifting gear prior to lifting


1 a) Preparation of the lifting 1. Wrong lifting gear (low capacity). To inspect lifting gear as per inspection check
equipment e.g. crane, lifting Gear angkat yang salah (kapasiti sheet by relevant party & to ensure the capacity of
gear, sling wire, shackles. rendah). lifting gear as per approved procedure.

Penyediaan alatan Periksa gear mengangkat seperti dalam


mengangkat seperti kren, senarai pemeriksaan dan diperiksa oleh pihak A 4
gear mengangkat, wayar yang berkenaan untuk memastikan kapasiti
sling dan shackles. gear mengangkat seperti di dalam prosedur
yang telah diluluskan.

2. Obstruction with fabrication equipment To ensure crane pathway is clear and no


e.g. welding machine, gases rack or other obstruction from any object before lifting activity.
structure.
Halangan dari alatan seperti mesin Memastikan laluan kren agar tidak terhalang B 2
welding, rak gas, dan struktur lain. oleh mana-mana objek yang boleh
mengganggu semasa aktiviti mengangkat
dijalankan.
DETERMINING CONTROL SITE VERIFICATION PBED
Penentuan Langkah Kawalan Penilaian tapak kerja (JHA Audit)

Elimination Substitution Engineering Administrative PPE


Penghapusan Penggantian Kejuruteraan Pentadbiran PPE
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE

Lifing plan to be established to determine the correct lifting gears to be


used , the gears are to comply with SFSB colour coding inspection and
to be visually inspected for damages before use.

Pelan mengangkat perlu dikeluarkan untuk mengenal pasti gear RIGGER


mengangkat yang digunakan adalah betul, dan selaras dengan RIGGER FOREMAN
SFSB pemeriksaan kod warna dan lakukan pemeriksaan visual LIFTING SUPERVISOR
untuk kerosakan sebelum digunakan.

RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
3. Pinch Point. Those rigger who are involved to have complete
Kecederaan pada jari. PPE before start the activity.impact resistance
glove

Rigger yang terlibat dalam aktiviti ini B 2


hendaklah memakai peralatan perlindungan
yang lengkap.

4. Miscommunication. Approved procedure to be cascade down to the


Salah faham. team involved in the activities.

Prosedur yang telah diluluskan perlulah B 2


diberitahu pada semua pekerja yang terlibat
dalam aktiviti ini.

Installation / rig up the lifting gears


2 Installation or rig up the lifting 1. Falling load. Slow down to lower the sling wire & ensure the
gear prior to Critical Lifting Beban terjatuh. load are fully secured / safely landing on the
Activity support

Memasang gear mengangkat Perlahan-lahan menurunkan wayar sling dan A 2


sebelum menjalankan Aktiviti pastikan objek sudah selamat & stabil
Kritical Lifting diletakkan di atas "support"

2. Pinch point. Those rigger who are involved to have complete


Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
gear & to avoid touching the load.

Rigger yang terlibat dalam aktiviti ini


B 3
hendaklah memakai peralatan perlindungan
yang lengkap & elakkan dari memegang
beban.

Performing the lifting and manuevering of load (pick and carry) from initial position onto final position
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE

RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR

RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR

RIGGER
RIGGER FOREMAN
CRANE OPERATOR
LIFTING SUPERVISOR

RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
3 Lifting, manuevering, flip-over 1. Communication Failure. Toolbox & 4 point check briefing shall be
and final positioning activity of Komunikasi gagal. conducted before start the lifting activity.
load (Launch Cradle using 25T
Overhead Travelling Crane) Melakukan "Toolbox & 4 Point Check" sebelum
aktivity dijalankan. B 4

Aktivity mengangkat,
membawa, memusing, dan
menempatkan beban (Launch
Cradle menggunakan 25T 2. Crane breakdown. Ensure the cranes are inspected and accepted as
Overhead Travelling Crane) Kren rosak. per inspection check sheet.

Pastikan kren telah diperiksa sebelum aktiviti B 4


mengangkat dijalankan.

3. Load Levellness Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to
Perbezaan level Analisi vs Sebenar be lifted at minimum height and levelnes should
be established.

"Test Lift" perlu dilakukan sebelum "Actual B 4


Lift", beban diangkat pada ketinggian minima
dan levellness beban dikenalpasti

4. Unathorised person. Unauthorised person are not allowed to stand


Pekerja yang tidak terlibat. nearby the lifting area. Put barricade & lifting
signage during to perform the activity.

Pekerja yang tidak terlibat tidak dibenarkan


B 2
berada di kawasan mengangkat. Letakkan
penghadang & pamerkan papan tanda "Lifting
Area" semasa menjalankan aktiviti ini.
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE

Radio communication should be established to dedicated radio


channel 4 or Using Hand Signal.
RIGGER
Komunikasi menggunakan radio dengan menggunakan RIGGER FOREMAN
saluran yang telah ditetapkan channel 4 atau LIFTING SUPERVISOR
menggunakan isyarat tangan. RIGGING ENGINEER
HSE

Inspection checklist to be complete, PMA should be valid.

Senarai pemeriksaan harus lengkap, PMA harus disahkan . CRANE OPERATOR


LIFTING SUPERVISOR

The load shall be set back to initial position and rigging arrangement
(add/remove shackles) shall be adjusted based on actual load
levellness (if any)
LIFTING SUPERVISOR
Beban dikembalikan ke kedudukan asal dan "rigging arrangment" RIGGING FOREMAN
(menambah / mengurangkan shackle) dilakukan berdasarkan RIGGING ENGINEER
keadaan levellness sebenar

BANKSMAN
SIGNALMAN
LIFTING SUPERVISOR
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
5. Unstable load. a) To ensure the wire slings get the tension first
Beban tidak stabil. and trial lifting to check the COG (level of the load)
prior to start.

Melakukan percubaan mengangkat dahulu B 3


beban, untuk melihat kestabilan beban
sebelum aktiviti diteruskan.

6. Slewing too fast Crane operator need to follow instruction from


"Slewing" teralu laju Supervisor / Signalman.

Kren operator perlu mengikut arahan dari


Rigging Supervisor/signalman.
B 3

7. Traveling too fast. Crane operator need to follow instruction from


Bergerak terlalu laju. Supervisor / Signalman.

Kren operator perlu mengikut arahan dari


Rigging Supervisor/signalman.
B 3
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE

Hold for 2 minutes after lifting at minimum height above ground to


ensure load is stable.
RIGGER
Berhenti 2 minit selepas mengangkat beban tinggi minima dari RIGGER FOREMAN
bawah, untuk memastikan beban stabil. CRANE OPERATOR
LIFTING SUPERVISOR

Load travel at the minimum height (site justification) and speed.

Perjalanan & kelajuan beban adalah pada ketinggian & kelajuan


yang minimum.
SIGNALMAN
CRANE OPERATOR
LIFTING SUPERVISOR

Load travel at the minimum speed.

Perjalanan & kelajuan beban dalam kelajuan yang minimum.


SIGNALMAN
CRANE OPERATOR
LIFTING SUPERVISOR
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO
8. Working At Height Body Harness, Only authorized personnel shall be
Bekerja di tempat tinggi allowed to be working at height

Abah-abah. Hanya personel yang berkaitan


sahaja dibenarkan bekerja di tempat tinggi B 2

9. Wrong positioning Refference marking/indicator for final positioning


Salah posisi. shall be done by Production Team prior to Lifting
Activity

Tanda rujukan untuk kedudukan akhir perlu C 3


dilakukan oleh Production Team sebelum
aktiviti mengangkat dilakukan

10. Bad weather. Check weather forecast first before perform the
Cuaca buruk. lifting activity.

Pastikan aktiviti mengangkat tidak dijalankan


semasa cuaca buruk. Periksa "Weather B 2
Forecast" terlebih dahulu sebelum memulakan
aktiviti ini.

4 Dismantle the lifting gear after 1. Falling load. Slow down to lower the sling wire & ensure the
the load are secured / safely Beban terjatuh. load are fully secured / safely landing on the
landing on the Main Support support
(Rigging Gear shall be release
after load is securely position Perlahan-lahan menurunkan wayar sling dan A 2
onto final position) pastikan objek sudah selamat & stabil
diletakkan di atas "support"
Membuka gear mengangkat
selepas beban selamat
diletakkan di atas Support
Utama
(Rigging Gear dilepaskan
selepas beban telah
diletakkan pada posisi
terakhir)
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE

RIGGER
RIGGER FOREMAN
SIGNALMAN
LIFTING SUPERVISOR

Production personel shall be present during Lifting Toolbox to brief the


team on Cellar Deck Positioning.

Wakil dari Production perlu hadir untuk Lifting Toolbox dan PRODUCTION
menjelaskan kepada Rigging Team berkenaan "Cellar Deck LIFTING ENGINEER
Positioning" LIFTING SUPERVISOR

In case of worst weather (lightning) during load lift/suspend, all


operation shall stop and Crane Safety Pawls shall be activated.

Sekiranya keadaan ribut petir ketika beban sedang diangkat, CRANE OPERATOR
semua operasi haruslah dihentikan dan Crane Safety Pawls harus LIFTING SUPERVISOR
digunakan. RIGGING ENGINEER

RIGGER
RIGGER FOREMAN
CRANE OPERATOR
LIFTING SUPERVISOR
4 Dismantle the lifting gear after
the load are secured / safely
landing on the Main Support
(Rigging Gear shall be release RISK
after load is securely position LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No onto final position) OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
Membuka gear mengangkat RISIKO
selepas beban selamat 2. Pinch point. Those rigger who are involved to have complete
diletakkan di atas Support Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
Utama gear & to avoid touching the load.
(Rigging Gear dilepaskan
selepas beban telah Rigger yang terlibat dalam aktiviti ini
diletakkan pada posisi B 3
hendaklah memakai peralatan perlindungan
terakhir) yang lengkap & elakkan dari memegang
beban.

Completion of activity
5 Lifting activity completed. 1. Trip and fall Conduct proper housekeeping.
Tersadung dan jatuh.
Aktiviti mengangkat selesai. Lakukan pembersihan dengan betul. A 1

2. Rigging gear left at work area. Supervisor to ensure all riggers to do proper
Alatan tidak si kemas / di simpan. housekeeing and no rigging gear & tools left at
work place.

Supervisor perlu memastikan semua pekerja A 1


melakukan pembersihan dan tiada alatan
mengangkat yang tertinggal di kawasan kerja.

Prepared by: Reviewed by: Approved by:


PROCESS OWNER HSE OFFICER / ENGINEER CONSTRUCTION MAN
Signature:
Signature: ________________ Signature:
Name :
Name: ________________ Name:
Designation: Designation: ________________ Designation:

Date :
Date: _________________ Date:
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE

RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR

RIGGER
RIGGER FOREMAN
LIFTING SUPERVISOR

RIGGER
RIGGER FOREMAN

Approved by:
CONSTRUCTION MANAGER

Signature:

Designation:
RISK
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures RATING
No OOD / ITY/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU H/M/L/
GKALIAN KAN PENILAIAN
RISIKO

Debriefing of HIRARC at work site


Perkongsian HIRARC di tapak kerja setelah tamat kerja

Day 1 Day 2 Day 3

Date Date Date Date


Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : ___________________

By By By By
Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________
site verification / suggestion on particular site verification / audit
date by PE, Supervisor or Foreman by HSE
Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE

Day 4 Day 5
Day 6 Day 7

Date Date Date


_________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : __________________

By By By
_________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________
Sapura Fabrication Sdn. Bhd. (83307-K)
(Formerly known as SapuraKencana HL Sdn. Bhd.)
Plot D1, Lumut Port Industrial Park, Kg Acheh, Mukim of Lumut,
32000 Sitiawan, Perak Darul Ridzuan.
Tel : 05-692 3071 Fax : 05-6922609
HIRARC (Rev:_01_Year:_2018___)
PROJECT NAME: PEGAGA DEVELOPMENT PROJECT
ACTIVITY OR PROCESS CRITICAL / COMPLEX LIFTING Date :
Department (HIRARC owner): PEGAGA DEVELOPMENT PROJECT HIRARC No :
TANDEM LIFTING AND FLIP OVER OF PEGAGA LAUNCH CRADLE Location: SECTOR 1
Task/Process :
USING 2 UNITS OF OVERHEAD TRAVELLING CRANE (25T) WORKSHOP 2
Specific Work area:

HAZARD IDENTIFICATION - tick all that apply, add additional as necessary


Hazard Source (√) Hazard Source (√) Hazard Source (√) Hazard Source (√) Hazard Source (√) Hazard Source (√) (Other hazard sources than stated)
Trip hazards √ Radiation Suspended load √ Line of fire √ Sharp material √ Vibration √
Falling objects √ Electrical hazards - LV / HV Engulfment Pressurised fluid Confined space General waste
Oxygen deficiency/excess Multiple electrical feeds Live rails - gantry crane Pressurised air / gas Remote or isolated work Hazardous waste
Poisonous gas Ladders √ Working near crane √ Moving / mobile plant Extreme temperature Hydrocarbon / chemical spill

Explosive gas Working at height √ Work near crane walkway Traffic management Extreme weather √ Soil disturbance / erosion

Flammable materials Elevated work platform √ Slippery surface Moving parts Reduced visibility
Combustible materials Potential for difficult rescue Manual handling √ Unauthorized persons √ Communication √
Difficult entry/exit
Hazardous substances Noise - plant & equipment Air emissions - dust, fumes Lighting

CONTROLS: PPE - tick all that apply


OTHER PPE (if required):

✘ ✘ ✘ ✘ ✘ ✘

Safety equipment or controls required:


Fire Watcher Lock-out / tag out system Ventilation
Barriers √ Fire extinguishers √ Lighting
Warning signs √ Scaffolding tag √ Earthing
O
Banksman √ Pocket Dosimeter Fire Blanket N
Signalman √ Spill Kit -
Personal Film Badge First Aid Box S
Additional safety equipment/control measures if required: I
T
E
B
R
Briefing of HIRADC at work site (Prior to starting work for critical activity only) I
Perkongsian HIRADC di tapak kerja kerja (sebelum memulakan aktiviti kritikal sahaja)
E
Note 1: ALARP - As Low As Reasonably Practicable - Where risk levels have been reduced to as safe level as possible but as to allowFthe completion of the task or activity. Day 6 Day 7
Note 2: If high risk work is being performed, stop work. Management intervention is required if additional control measure (s) is/are
I unable to reduce the risk level.
N
G SITE VERIFICATION
DETERMINING CONTROL PBED
HAZARD IDENTIFICATION RISK ASSESSMENT Penentuan Langkah Kawalan Penilaian tapak kerja (JHA Audit)
(
Pengenalpastian Hazad Penilaian Hazad
P
R
I Elimination Substitution Engineering Administrative PPE
Penghapusan Penggantian Kejuruteraan Pentadbiran PPE
O site verification / suggestion on particular site verification / audit
R LIKELIH SEVER RISK date by PE, Supervisor or Foreman by HSE
Specific Activity Hazard Identified Existing Control Measures T OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada O KEBARAN KETERU PENILAIAN Saranan langkah keselamatan
GKALIAN KAN
S RISIKO

Preparation and setting of the lifting gear prior to lifting T


1 a) Preparation of the lifting 1. Wrong lifting gear (low capacity). To inspect lifting gear as per inspection check A Lifing plan to be established to determine the correct lifting gears to be
equipment e.g. crane, lifting Gear angkat yang salah (kapasiti sheet by relevant party & to ensure the capacity R
of used , the gears are to comply with SFSB colour coding inspection and
gear, sling wire, shackles. rendah). lifting gear as per approved procedure. TI to be visually inspected for damages before use.
N
Penyediaan alatan Periksa gear mengangkat seperti dalam Pelan mengangkat perlu dikeluarkan untuk mengenal pasti gear RIGGER
mengangkat seperti kren, senarai pemeriksaan dan diperiksa oleh pihak
G A 4 mengangkat yang digunakan adalah betul, dan selaras dengan RIGGER FOREMAN
gear mengangkat, wayar yang berkenaan untuk memastikan kapasiti W SFSB pemeriksaan kod warna dan lakukan pemeriksaan visual LIFTING SUPERVISOR
sling dan shackles. gear mengangkat seperti di dalam prosedur O untuk kerosakan sebelum digunakan.
yang telah diluluskan. R
K
F
O
R
C
R
IT
I
C
A
L
A
C
TI
1 a) Preparation of the lifting
equipment e.g. crane, lifting
gear, sling wire, shackles.

Penyediaan alatan
mengangkat seperti kren, site verification / suggestion on particular site verification / audit
gear mengangkat, wayar RISK date by PE, Supervisor or Foreman by HSE
sling dan shackles. LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
2. Obstruction with fabrication equipment To ensure crane pathway is clear and no
e.g. welding machine, gases rack or other obstruction from any object before lifting activity.
structure. RIGGER
Halangan dari alatan seperti mesin Memastikan laluan kren agar tidak terhalang B 2 RIGGER FOREMAN
welding, rak gas, dan struktur lain. oleh mana-mana objek yang boleh LIFTING SUPERVISOR
mengganggu semasa aktiviti mengangkat
dijalankan.
3. Pinch Point. Those rigger who are involved to have complete
Kecederaan pada jari. PPE before start the activity.impact resistance
glove
RIGGER
Rigger yang terlibat dalam aktiviti ini B 2 RIGGER FOREMAN
hendaklah memakai peralatan perlindungan LIFTING SUPERVISOR
yang lengkap.

4. Unfit Crane Operator Crane Operator to do Drug and Alcohol Test prior
Kren Operator tidak layak to Lifting Activity

Operator Crane perlu melalui ujian dadah dan


alkohol sebelum memulakan aktiviti B 2 CRANE OPERATOR
mengangkat

5. Miscommunication. Approved procedure to be cascade down to the


Salah faham. team involved in the activities.
RIGGER
Prosedur yang telah diluluskan perlulah B 2 RIGGER FOREMAN
diberitahu pada semua pekerja yang terlibat LIFTING SUPERVISOR
dalam aktiviti ini.

Installation / rig up the lifting gears


2 Installation or rig up the lifting 1. Falling load. Slow down to lower the sling wire & ensure the
gear prior to Critical Lifting Beban terjatuh. load are fully secured / safely landing on the
Activity support RIGGER
RIGGER FOREMAN
Memasang gear mengangkat Perlahan-lahan menurunkan wayar sling dan A 2
CRANE OPERATOR
sebelum menjalankan Aktiviti pastikan objek sudah selamat & stabil LIFTING SUPERVISOR
Kritical Lifting diletakkan di atas "support"

2. Pinch point. Those rigger who are involved to have complete


Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
gear & to avoid touching the load.
RIGGER
Rigger yang terlibat dalam aktiviti ini
B 3 RIGGER FOREMAN
hendaklah memakai peralatan perlindungan LIFTING SUPERVISOR
yang lengkap & elakkan dari memegang
beban.

Performing the lifting and manuevering of load (pick and carry) from initial position onto final position
3 Lifting, manuevering, flip-over 1. Communication Failure. Toolbox & 4 point check briefing shall be Radio communication should be established to dedicated radio
and final positioning activity of Komunikasi gagal. conducted before start the lifting activity. channel 3
load (Launch Cradle using 2 RIGGER
units of 25T Overhead Travelling Melakukan "Toolbox & 4 Point Check" sebelum Komunikasi menggunakan radio dengan menggunakan RIGGER FOREMAN
Crane) aktivity dijalankan. B 4 saluran yang telah ditetapkan channel 3. LIFTING SUPERVISOR
RIGGING ENGINEER
HSE
Aktivity mengangkat,
membawa dan "positioning"
beban (Launch Cradle 2. Crane breakdown. Ensure the cranes are inspected and accepted as Inspection checklist to be complete, PMA should be valid.
menggunakan 2 unit 25T Kren rosak. per inspection check sheet.
Overhead Travelling Crane) Senarai pemeriksaan harus lengkap, PMA harus disahkan . CRANE OPERATOR
Pastikan kren telah diperiksa sebelum aktiviti B 4
LIFTING SUPERVISOR
mengangkat dijalankan.

3. Load Discrepancy Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to Personel from Engineering shall present at site during lifting activity to
Perbezaan berat beban Analisis vs be lifted at minimum height and reading of load acknowledge and approve decision made by Rigging Team to mitigate
Sebenar from Crane LMI shall be established. the Load Discrepency (if any)
RIGGING ENGINEER
"Test Lift" perlu dilakukan sebelum "Actual B 4 Wakil dari Engineering perlu berada di site ketika aktiviti lifting LIFTING SUPERVISOR
Lift", beban diangkat pada ketinggian minima untuk mengesahkan keputusan yang dilakukan oleh Rigging Team ENGINEERING
dan bacaan beban dari LMI Kren harus bagi menangani masalah Perbezaan Beban (jika ada)
dikenalpasti
beban (Launch Cradle
menggunakan 2 unit 25T
Overhead Travelling Crane)

site verification / suggestion on particular site verification / audit


RISK date by PE, Supervisor or Foreman by HSE
LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
4. Load Levellness Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to The load shall be set back to initial position and rigging arrangement
Perbezaan level Analisi vs Sebenar be lifted at minimum height and levelnes should (add/remove shackles) shall be adjusted based on actual load
be established. levellness (if any)
LIFTING SUPERVISOR
"Test Lift" perlu dilakukan sebelum "Actual B 4 Beban dikembalikan ke kedudukan asal dan "rigging arrangment" RIGGING FOREMAN
Lift", beban diangkat pada ketinggian minima (menambah / mengurangkan shackle) dilakukan berdasarkan RIGGING ENGINEER
dan levellness beban dikenalpasti keadaan levellness sebenar

5. Unathorised person. Unauthorised person are not allowed to stand


Pekerja yang tidak terlibat. nearby the lifting area. Put barricade & lifting
signage during to perform the activity.
BANKSMAN
Pekerja yang tidak terlibat tidak dibenarkan
B 2 SIGNALMAN
berada di kawasan mengangkat. Letakkan
LIFTING SUPERVISOR
penghadang & pamerkan papan tanda "Lifting
Area" semasa menjalankan aktiviti ini.

6. Unstable load. a) To ensure the wire slings get the tension first Hold for 2 minutes after lifting at minimum height above ground to
Beban tidak stabil. and trial lifting to check the COG (level of the load) ensure load is stable.
prior to start. RIGGER
Berhenti 2 minit selepas mengangkat beban tinggi minima dari RIGGER FOREMAN
Melakukan percubaan mengangkat dahulu B 3 bawah, untuk memastikan beban stabil. CRANE OPERATOR
beban, untuk melihat kestabilan beban LIFTING SUPERVISOR
sebelum aktiviti diteruskan.

7. Slewing too fast Crane operator need to follow instruction from Load travel at the minimum height (site justification) and speed.
"Slewing" teralu laju Supervisor / Signalman.
Perjalanan & kelajuan beban adalah pada ketinggian & kelajuan
Kren operator perlu mengikut arahan dari yang minimum.
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR

8. Traveling too fast. Crane operator need to follow instruction from Load travel at the minimum speed.
Bergerak terlalu laju. Supervisor / Signalman.
Perjalanan & kelajuan beban dalam kelajuan yang minimum.
Kren operator perlu mengikut arahan dari
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR

9. Working At Height Body Harness, Only authorized personnel shall be


Bekerja di tempat tinggi allowed to be working at height
RIGGER
Abah-abah. Hanya personel yang berkaitan RIGGER FOREMAN
sahaja dibenarkan bekerja di tempat tinggi B 2
SIGNALMAN
LIFTING SUPERVISOR

10. Wrong positioning Refference marking/indicator for final positioning Production personel shall be present during Lifting Toolbox to brief the
Salah posisi. shall be done by Prouction Team prior to Lifting team on Cellar Deck Positioning.
Activity
Wakil dari Production perlu hadir untuk Lifting Toolbox dan PRODUCTION
Tanda rujukan untuk kedudukan akhir perlu C 3 menjelaskan kepada Rigging Team berkenaan "Cellar Deck LIFTING ENGINEER
dilakukan oleh Production Team sebelum Positioning" LIFTING SUPERVISOR
aktiviti mengangkat dilakukan

11. Bad weather. Check weather forecast first before perform the Shall worst weather (lightning) during load lift/suspend, all operation
Cuaca buruk. lifting activity. shall stop and Crane Safety Pawls shall be activated.

Pastikan aktiviti mengangkat tidak dijalankan Sekiranya keadaan ribut petir ketika beban sedang diangkat, CRANE OPERATOR
semasa cuaca buruk. Periksa "Weather B 2 semua operasi haruslah dihentikan dan Crane Safety Pawls harus LIFTING SUPERVISOR
Forecast" terlebih dahulu sebelum memulakan digunakan. RIGGING ENGINEER
aktiviti ini.

4 Dismantle the lifting gear after 1. Falling load. Slow down to lower the sling wire & ensure the
the load are secured / safely Beban terjatuh. load are fully secured / safely landing on the
landing on the Main Support support RIGGER
(Rigging Gear shall be release RIGGER FOREMAN
after load is securely position Perlahan-lahan menurunkan wayar sling dan A 2
CRANE OPERATOR
onto final position) pastikan objek sudah selamat & stabil LIFTING SUPERVISOR
diletakkan di atas "support"
Membuka gear mengangkat
selepas beban selamat
diletakkan di atas Support
Utama
(Rigging Gear dilepaskan
selepas beban telah
diletakkan pada posisi
terakhir)
4 Dismantle the lifting gear after
the load are secured / safely
landing on the Main Support site verification / suggestion on particular site verification / audit
(Rigging Gear shall be release RISK date by PE, Supervisor or Foreman by HSE
after load is securely position LIKELIH SEVER
Specific Activity Hazard Identified Existing Control Measures OOD / ITY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No onto final position) H/M/L/
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan tarikh oleh PE, Supervisor atau Foreman HSE
GKALIAN KAN
Membuka gear mengangkat RISIKO
selepas beban selamat 2. Pinch point. Those rigger who are involved to have complete
diletakkan di atas Support Kecederaan pada jari. PPE (impact glove) before dismantle the lifting
Utama gear & to avoid touching the load.
(Rigging Gear dilepaskan
selepas beban telah RIGGER
Rigger yang terlibat dalam aktiviti ini B 3 RIGGER FOREMAN
diletakkan pada posisi hendaklah memakai peralatan perlindungan
terakhir) LIFTING SUPERVISOR
yang lengkap & elakkan dari memegang
beban.

Completion of activity
5 Lifting activity completed. 1. Trip and fall Conduct proper housekeeping.
Tersadung dan jatuh. RIGGER
Aktiviti mengangkat selesai. Lakukan pembersihan dengan betul. A 1 RIGGER FOREMAN
LIFTING SUPERVISOR

2. Rigging gear left at work area. Supervisor to ensure all riggers to do proper
Alatan tidak si kemas / di simpan. housekeeing and no rigging gear & tools left at
work place.
RIGGER
Supervisor perlu memastikan semua pekerja A 1 RIGGER FOREMAN
melakukan pembersihan dan tiada alatan
mengangkat yang tertinggal di kawasan kerja.

Prepared by: Reviewed by: Approved by:


PROCESS OWNER HSE OFFICER / ENGINEER CONSTRUCTION MANAGER
Signature:
Signature: ________________ Signature:
Name :
Name: ________________ Name:
Designation: Designation: ________________ Designation:

Date :
Date: _________________ Date:

Debriefing of HIRARC at work site


Perkongsian HIRARC di tapak kerja setelah tamat kerja

Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7

Date Date Date Date Date Date Date


Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : _________________________ Tarikh : __________________

By By By By By By By
Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________

You might also like