Professional Documents
Culture Documents
--------------------------------------------------------x
Perini/Tompkins Joint Venture : CIVIL ACTION NO.:
:
Plaintiff, :
:
v. :
:
ACE American Insurance Company : DECEMBER 13, 2010
:
Defendant, :
--------------------------------------------------------x
THE PARTIES
1. At all relevant times, Plaintiff Perini/Tompkins Joint Venture (“PTJV”) was a joint
of business in Nevada;
3. This Court has jurisdiction over this matter pursuant to 28 U.S.C. § 1332 (a)(1)
insofar as this is a diversity action between the citizens of different states and the amount in
a substantial part of the events and omissions which give rise to this legal action occurred in
this District.
FACTUAL BACKGROUND
The Contract
Exhibit A, Gaylord National, LLC (“Gaylord”) hired PTJV to, inter alia, serve as Construction
Manager in connection with the construction of the Gaylord National Resort and Hotel in Oxon
Owner Controlled Insurance Program in connection with the Project that would provide PTJV
The Policies
from ACE, No. HDO G16800703 (the “Primary Policy”), attached hereto as Exhibit B, and an
Excess Liability Policy from ACE, No. XLX G22909964 (the “Excess Policy”), attached hereto
and, as a result of said endorsement, automatically added as a named insured on the Excess
Policy.
9. The Excess Policy applies to injury or damage covered by the Primary Policy in
2
Case 8:10-cv-03494-PJM Document 1 Filed 12/13/10 Page 3 of 8
The Collapse
10. A significant portion of the Project involved the construction of a glass roof
atrium. The atrium was composed of numerous subsections, called trusses, that were
preassembled on the ground and lifted via crane into place. Each truss contained several
components, including supportive tension rods that were connected by rod/clevis junctures.
11. The atrium was under construction on or about August 28, 2007 while Truss H4
was lifted into position and, on or about August 31, 2007, certain components were added to
the atrium that placed additional pressure and tension on Truss H4, causing, unbeknownst to
12. On September 5, 2007, the rod/clevis juncture on Truss H4, which began eroding
no later than August 31, 2007, failed. That failure caused a loss of tension that substantially
13. The Collapse caused damage to various components of the Project and required
a temporary suspension of the Project and such damages were neither expected nor intended
14. As a direct and proximate result of the Collapse, Gaylord suffered damages and,
in subsequent litigation, asserted claims against PTJV for those damages including, but not
limited to costs to repair the atrium beyond the failed rod/clevis connection and increased costs
3
Case 8:10-cv-03494-PJM Document 1 Filed 12/13/10 Page 4 of 8
The Claim
15. A representative from ACE was onsite at the Project on September 5, 2007
during the Collapse and thereafter, received timely updates regarding the reason for the
Collapse, the scope and extent of related damages and the method and cost of repair.
effort to have the claim properly and timely adjusted and resolved.
17. After much negotiation, ACE formally accepted the claim and agreed to handle
18. Thereafter, PTJV made multiple requests to ACE regarding the status of the
claim and demanding that ACE make payment and ACE continually represented it would work
19. Contrary to its representations, however, ACE failed and/or refused to make any
reversed its position and refused to make any payment on the claim on the basis that it had
been directed not to do so by Gaylord and the broker for the Policies.
21. In connection with that e-mail, ACE represented it would retain counsel to review
the claim and assist in reaching a resolution, however, did not do so until approximately one
22. Yet, as of December 2, 2010, such counsel had not received any materials from
4
Case 8:10-cv-03494-PJM Document 1 Filed 12/13/10 Page 5 of 8
23. ACE has continually represented to PTJV its intent to adjust this claim in good
faith yet, at every critical juncture, has failed and/or refused to do so.
24. PTJV repeats and re-alleges all of the allegations contained in Paragraphs 1
25. Despite demand, ACE has failed, refused and/or neglected to pay any portion of
the Collapse Claims pursuant to the Primary Policy or the Excess Policy and is in breach of its
27. Further, the Policies are contractual agreements which contain an implied
covenant of good faith and fair dealing requiring ACE to deal honestly and in good faith with
PTJV.
28. ACE has breached its duty of good faith and fair dealing owed to PTJV under the
Policies by and through its conduct, which includes, but is not limited to:
insured to deny PTJV’s claim and thereby wrongfully put its own interests
5
Case 8:10-cv-03494-PJM Document 1 Filed 12/13/10 Page 6 of 8
designed to frustrate PTJV’s rights pursuant to the OCIP such as, inter
alia, representing it was adjusting the claim though it was not, failing
claims;
29. As a result of ACE’s breach of contract and breach of the implied covenant of
good faith and fair dealing, PTJV has suffered, and continues to suffer, damages.
30. PTJV repeats and re-alleges all of the allegations contained in Paragraphs 1
31. ACE is obligated to indemnify PTJV, pursuant to the Policies, for the Collapse
Claims.
32. An actual and justiciable controversy exists regarding ACE’s obligations under
the Primary Policy and the Excess Policy to pay PTJV for the Collapse Claims, and a
declaratory judgment is necessary and appropriate to determine the rights and duties of PTJV
and ACE pursuant to the Primary Policy and the Excess Policy.
34. PTJV repeats and re-alleges all of the allegations contained in Paragraphs 1
6
Case 8:10-cv-03494-PJM Document 1 Filed 12/13/10 Page 7 of 8
35. ACE has acted in bad faith in connection with respect to PTJV’s rights pursuant
to the Policies, which actions include, but are not limited to:
insured to deny PTJV’s claim and thereby wrongfully put its own interests
designed to frustrate PTJV’s rights pursuant to the OCIP such as, inter
its counsel and concealing its position regarding coverage despite request
PTJV’s claims;
36. As a result of ACE’s bad faith conduct, PTJV has suffered, and continues to
suffer, damages.
1. An Order from this Court declaring and setting forth ACE’s duties and obligations
7
Case 8:10-cv-03494-PJM Document 1 Filed 12/13/10 Page 8 of 8
2. Judgment from this Court in favor of PTJV and against ACE in an amount equal
ii. Attorneys’ fees and costs incurred by PTJV in this coverage dispute;