You are on page 1of 3

technical

overhead absorption
relevant to CAT Scheme Papers 2 and 4

allocate, apportion,
absorb
This article focuses on production overhead PRODUCTION OVERHEAD ALLOCATION, re-apportionment of service cost centre
absorption using, as an illustration, a question APPORTIONMENT, AND ABSORPTION overheads to production cost centres.
from the December 2005 CAT Scheme Production overheads are a popular topic in Products/services pick up overhead costs
Paper 4 examination. It also considers study materials and examination questions. At out of the production cost centres via
the wider context of overhead allocation, the very least, costs have to be shared among overhead absorption, as production occurs.
apportionment, and absorption. products in order to value work-in-progress
The cost accounting for overheads and finished goods stocks. By refining what Absorption
(indirect costs) is an element in the CAT may otherwise be an arbitrary process, establishing an absorption rate for each
Paper 2 Study Guide. Sub-section 8(g) states accountants can provide useful information production cost centre
that students are required to ‘explain and that will help management in cost control and absorption of overheads into cost units.
illustrate the process of cost apportionment profitability analysis.
and absorption for indirect costs (excluding An important part of such refinement The key issue in establishing how to apportion,
reciprocal services)’. This topic is explored involves the establishment of cost centres re-apportion, and absorb overheads is fairness.
further in CAT Scheme Paper 4, where two (both production cost centres and service cost When considering cost apportionment/
sections of the Study Guide are devoted centres) in order to: re-apportionment for each overhead cost type
to overhead allocation, apportionment and delegate management responsibility for (or service cost centre) that has to be shared,
absorption, including Sub-section 9(a), which costs incurred the important principle is to identify the key
states that students are required to ‘justify, increase the accuracy of cost sharing driver of the cost. In other words, what is the
calculate, and apply production cost centre by allocating costs at a lower level and main cause of the cost incurred?
overhead absorption rates using labour hour sharing them on different bases. The same general principle applies
and machine hour methods’. to overhead absorption. There are many
A further refinement is the use of budgets to different causes, and thus many drivers,
OVERHEAD COST SHARING facilitate cost control and the sharing of costs that traditionally have been encapsulated
Overheads are those costs that cannot be in advance. (for each production cost centre) in a single
directly allocated to any of the products There are three main steps in the basis for overhead absorption. Typically, this
or services provided by a business to its process of production overhead cost sharing: is achieved by using an activity measure
customers. These costs, therefore, have to be allocation, apportionment, and absorption. based on direct labour hours or machine
shared out in some way among the various hours, because the production activity of
products or services in order to establish Allocation each product can be measured in this way
product/service costs. Overhead costs must collection of costs by type and used to absorb overheads. More than
be shared: allocation of as many costs as possible one basis could be used in each cost centre if
as fairly as possible over the different directly to cost centres. there are clearly different drivers.
cost centres and cost units that use the If overhead cost budgets are prepared,
particular resources in question Apportionment then predetermined absorption rates can
in ways that are administratively feasible apportionment to cost centres of be established and used. This gives rise
so that the benefits from having and using establishment costs – those costs that to production overhead over-absorption or
the information (ideally) exceed the cost of cannot be allocated directly to individual under-absorption in each production cost
its provision. cost centres centre resulting from the comparison of

50 student accountant August 2006


the actual overhead costs allocated and Production cost centre Production cost centre
apportioned with the total costs absorbed. X Y X Y
Budget £161,820 £97,110 Machine hours:
QUESTION Actual £163,190 £96,330 Budget 8,700 1,760
Question 2(b), in Section B of the December Actual 8,960 1,725
2005 Paper 4 examination, tested candidates’ Overheads are absorbed using predetermined Direct labour hours:
ability to calculate and use predetermined rates. A machine hour rate is used in production Budget 6,220 8,300
production overhead absorption rates when the cost centre X and a direct labour hour rate in Actual 6,276 7,870
allocation and apportionment of the overheads production cost centre Y. Machine and direct
had already taken place. Part (b) of the labour activity in each production cost centre is: Required:
question was as follows: Calculate for each production cost centre for
the period:
Overheads allocated, apportioned, and i the predetermined production overhead
re-apportioned to the two production cost absorption rate
centres in a factory for a period were: ii the production overheads absorbed

August 2006 student accountant 51


technical

iii the over/under-absorption of production The key issue in establishing how Many candidates were able to calculate
overhead. the required overhead absorption rates in Part
to apportion, re-apportion, and (i), although several calculated other rates
Answer (with explanation) absorb overheads is fairness. When as well (for example, labour hour rate and
The first stage in production overhead machine hour rate for each cost centre and/or
absorption is to calculate absorption rates
considering cost apportionment/ on actual costs and hours). Apart from not
using budgeted data (ie predetermined rates). re-apportionment for each overhead answering the question, which clearly stated
The question states that a machine hour rate cost type (or service cost centre) the basis for calculating the predetermined
is to be applied in production cost centre X, rate to be used in each of the cost centres,
and a direct labour hour rate in production that has to be shared, the important a lot of time was wasted on unnecessary
cost centre Y. Thus: principle is to identify the key driver calculations. This was often carried over to
Parts (ii) and (iii) where further incorrect and
Production cost centre X:
of the cost. unnecessary calculations were made. There
£161,820 ÷ 8,700 machine hours = £18.60 were also many scripts where candidates
per machine hour overhead control account) and the overheads added hours to £ or added labour hours and
absorbed into product costs in machine hours together.
Production cost centre Y: work-in-progress (credited to individual Where candidates calculated the correct
£97,110 ÷ 8,300 direct labour hours = cost centres and, in total, to the production rates in Part (i), and no further rates, they
£11.70 per direct labour hour overhead control account). Any difference will were frequently unable to apply the rates to
be either an under-absorption or an answer Parts (ii) and (iii). Many, seemingly,
These predetermined rates are then used over-absorption depending on whether more or could not calculate the overheads that would
throughout the budget period to absorb less has been incurred than absorbed. So: be absorbed in each cost centre. A common
overheads on the basis of actual hours worked; error in Part (ii) was the calculation of further
overheads are transferred (absorbed) from the Production cost centre X: absorption rates, this time on the actual
production overhead accounts to the actual £163,190 - absorbed £166,656 = data (costs and hours). A very common error
work-in-progress accounts on a regular £3,466 over-absorbed (less incurred than to Part (iii) was the comparison of actual
basis. Over the whole period, the total of the absorbed) and budgeted costs. A few candidates even
production overhead absorbed from each cost compared actual and budgeted hours.
centre is: Production cost centre Y: Not infrequently, candidates calculated
actual £96,330 - absorbed £92,079 = absorption rates in answer to Part (i) using
Production cost centre X: £4,251 under-absorbed (more incurred than the actual figures, rather than the budgeted
8,960 machine hours @ £18.60 per machine absorbed) figures, and got an answer for each cost
hour = £166,656 centre which they rounded. In answer to Part
Any under-absorption is a further charge that (ii), they then simply multiplied the actual
Production cost centre Y: reduces profit: any over-absorption is added absorption rate by the number of hours they
7,870 direct labour hours @ £11.70 per back to increase profit. had divided by in Part (i) – the resulting
direct labour hour = £92,079 number was inevitably very similar to the
Examiner’s comments actual costs they had started with in Part (i).
The amount of overheads have therefore A number of candidates were well-prepared Finally, in Part (iii), candidates compared the
been transferred into the cost of the different and scored full marks on this question. two numbers (actual and absorbed) to produce
products manufactured (along with the However, a serious lack of understanding of a very small over/under-absorption due to the
allocated direct materials and direct labour absorption costing was demonstrated by many. rounding in Part (i).
costs), and subsequently into cost of sales Candidates need to appreciate that overhead It is disappointing that coverage of this
when the products are sold. absorption rates are typically established in topic in Paper 2, as well as Paper 4, did not
Ultimately, however, it is the actual advance of a period on the basis of budgeted produce good results in the Paper 4 exam. I
production overhead costs incurred that are data. Overheads are then absorbed during hope that candidates now have a better idea
charged against sales, along with all the other the period using the predetermined rates about production overhead absorption and its
actual costs, to determine profit. The final but this time on the basis of actual activity. role in the overhead allocation, apportionment
stage in the overhead absorption process is, Over/under-absorption of overheads arises and absorption process.
therefore, to make a comparison between the due to differences between overheads actually
actual costs incurred (debited to individual incurred in the period and those absorbed into Nigel Coulthurst is examiner for CAT Scheme
cost centres and, in total, to the production the cost of work done in the period. Papers 2 and 4

52 student accountant August 2006

You might also like