Purpose
To discuss weekly FEIT issues, progress and action items.
Attendees
CBP
(b) (6) , SBI TI Technical/SME Manager
(b) (6) , Environmental
(b) (6) , Deputy PM
(b) (6) , SBI TI
(b) (6) SBI Project Support
(b) (6) , Risk Manager
(b) (6) , RE
(b) (6) , Public Outreach
(b) (6) , Business Manager
(b) (6)
(b) (6)
(b) (6)
(b) (6)
(b) (6) , PM
(b) (6)
(b) (6) , RE
(b) (6) , PF225 Project Manager
(b) (6) , PF225 Project Manager
CBP/SBInet
Meeting Minutes 11/9/2010 1
FME004085
Discussion Overview
Topics Covered during the Meeting
Discussion:
o Sector Book updates with USACE PM’s
o Make sure to identify any opportunity for an earlier construction date
o District Teams Status
o Del Rio
o M-1
Scheduled for legal review today for RFP release
This isn’t going to happen
o Baker can get the package for legal review April 1
Issue date for RFP April 4
Need real estate subject matter experts to provide input for change requests
There are two property owners involved that will be impacted by the toll
plaza project happening in two years
o OBP is concerned they may complain that they don’t have access
due to the fence
o We need a good understanding of all the implications of the fence
and extension
How will it work relative to the existing POE, relative to the
new POE and who it is going to impact
We need this before we are going to be comfortable
approving a change request
There are 7 residents south of the fence alignment
We could potentially set them up in another
temporary situation since they’re mobile homes
anyway
Estimated completion date for M-1 real estate certified is not correct in the
Sector Book
Add 3 months – real estate doesn’t match up
o M-2A & M-2B (Eagle Pass)
Occurring April 30
Believe is April 18 in Smart book
Real estate certified in Smart Book
End of July
Still maintains time – condemnation
M-2A
Building a retaining wall into an embankment
o Need to stay in the cliff and not outside
o Need to confirm the retaining wall is okay from a real estate
perspective
CBP/SBInet
Meeting Minutes 11/9/2010 2
FME004086
o K projects
Have either a real or environmental issue on each
USACE real estate is working diligently to put condemnation packages
together
o Concerned may take the same life of Columbus Cattle Company
K-3
o Review is finished and comments have been incorporated
o DOJ received package from CCC
Package is complete but hasn’t been approved for Robert
Jansen’s signature
Not aware of any problems
Need to give the contractor notice to proceed because they’re just
waiting
o Getting close to completing I-1A and need to keep them busy
o Marfa
o 1-1A & I-1B
Building a retaining wall into the levee
Concerned the concrete factories aren’t able to support the necessary
supply since the area is so remote
o There are two options:
Get batch plants set up – need a lot of money
Preferred option is to drive in corrugated sheet piles
Supply chain management
A MATOC
o Tucson
o Change request for access road request for D-5B, D-6
“A” Road – middle access road for the project
Wrong access road initially
o Redefined as “A” Road
o Coming this week
o D-5B and all-weather road
Change management will formally request the acquisition of more land
Road is an easement and ? south of road is f?
First mile completed on E-3
(b) (6) going to site tomorrow afternoon for a site visit
o C-1
Change on the staging area access
New Right of Way
o Yuma
o A change request may be submitted for the change in staging
o El Centro
o B-4 to go through La Playa
Don’t want to go through it because of species specific to that area
o New condemnation where the Roosevelt Reservation doesn’t exist
Issue of an unclear title and ownership dispute
CBP/SBInet
Meeting Minutes 11/9/2010 4
FME004088
CBP/SBInet
Meeting Minutes 11/9/2010 5
FME004089
Wait until Mr. Giddens meets with Congressman (b) (6) to do real estate
activities
O-4 – O-14
99% sure wall project will be approved this week
Move ahead with access roads and staging areas but not real estate
acquisition until that occurs
o Can do survey and exploration if we have ROE’s
o Department of the Army hasn’t formally accepted Delegation of
Authority
This has to occur to amend the Support Agreement
(b) (6) putting together a policy with OFAM on
how the document will be filed and handled for
permanent record
o Will be finalized the week after next
o Need costs from the spreadsheet (b) (6)
owns on tracking tool
o Need input on change requests for real
estate
o Need a handle on the change request review
process
(b) (6) keeps (b) (6) in
the loop and forwards to the local
USACE Pm
o PF225 schedule status
o Found glitches in the dates on Phase I projects
Getting issues fixed so that when the baseline is published it’s reliable
PM’s are doing sanity check and Ops Cell is doing sanity check on the
milestones
o Target completion dates
Need solid understanding of rollout of segments
What’s going to MATOC and what’s not
o Real estate database needs to be updated in TIPO
Polygons aren’t on access roads
Colors aren’t right for real estate
Public roads should be differentiated from private
CBP/SBInet
Meeting Minutes 11/9/2010 7
FME004091
CBP/SBInet
Meeting Minutes 11/9/2010 8