What do we need to know?

Dates:-

Order Date

Date on which the sales order is entered. System proposes the current date by default.

Material Availability Date

The date on which the material must be available. On the material availability date, the vendor
must start the activities relevant for delivery, such as picking and packing the goods. The material
availability date must be sufficiently early enough so that the goods are prepared by the loading
date.

Transportation Planning Date

We must arrange transportation by this date, so that the delivery can be sent to the customer. The
date from which the organization of goods transport must begin. The transportation planning date
must be selected early enough so that the transport is available on the loading date to load the
goods.

Loading Date

Picking and packing must be completed by this date so that the goods are ready for loading.

Goods Issue Date

Goods must physically leave the shipping point by this date. The date on which the goods must
leave the company to arrive at the customer location in time.

Delivery Date

Customer should receive delivery of the goods by this date. The date on which goods are to arrive at
the customer's premises. Example: The delivery date can be the delivery date requested by the
customer (desired delivery date) or the date confirmed in the vendor's order acknowledgment or
shipping confirmation (confirmed or acknowledged delivery date).

Times:-

Pick/Pack Time

Difference between the material availability date and loading date.

Transportation Lead Time

Number of days required for organizing a shipment for an item to be delivered.

Loading Time
Difference between loading date and goods issue date.

Transit Time

Number of days required for delivering an item from your company to the customer via a certain
route.

How do we View Availability Situation?


Run Transaction: CO09

Enter Plant & Checking Rule, against which the Availability is to be checked. For Sales Order
Checking Rule = A, Delivery = B, Back Order = BO

In this screen, we can see:


• Availability Checking Group (Avail Check): 02
• Check Rule : A
• End Lead Time Refers to the end of Replenishment Lead Time. If that is not included in the
Configuration, then this field is not visible.
• Totals Display:** Receipts = Sum of all +ve Quantities in Rec./Reqd qty Column
(Leave out the last row, MRP Element 001, since it is a total)
These are all the Planned Incoming Movements
• Issues = Sum of all -ve Quantities in Rec./Reqd qty Column
These are all the Planned Outgoing Movements
• Confirmed issues = Sum of all (+ve) Quantities in Confirmed Column
These are the confirmations against ATP.

When is Availability Check Triggered?


While creating a Sales Order, Production Order, Delivery, etc. Below is a screen from Sales Order. At
the bottom is a button for Check Material Availability. Also while creating the order, if the Availability
situation cannot meet the requested delivery date, the system goes to Availability screen
automatically. (Discussed later)
Run Transaction: VA01

How we arrive at a Confirmed Delivery Date?

Below is the logic the system uses to check availability:


• Using the Scheduling data from Delivery & Transportation Scheduling, the system does the
backward calculation from the Requested Delivery Date. This is used to arrive at Material
Availability Date.
• On the Material Availability Date, system checks the Available Qty, as seen in CO09 in
column Cum. ATP Qty. If the Available Qty is > than Required Qty, Requested Delivery
Date is confirmed. Otherwise,
• System moves into the future till it finds the required Available Qty. The new date is then
the new Material Availability Date.
• On getting the confirmed Material Availability Date, system does the Forward Scheduling to
arrive at a Confirmed Delivery date.

Backwards Scheduling
Control of Availability Check
Forward Scheduling
Result of Availability Check: Some Sample Scenarios
Above is the Availability Screen as seen in Sales Order. It has following Buttons:

One-time delivery

In the results of Availability, we have 3 options to choose from. This is Case 1, when we can confirm
the Customer's Requested delivery Date. The details of this are visible in the first sub screen below.

Complete dlv.
This is Case 2, when we can confirm the Customer's Requested complete delivery at a future Date.
The details of this are visible in the second sub screen below.

Delivery proposal

This is Case 3, when we can confirm the Customer's Requested delivery in partial quantities at
future dates. The details of this are visible in the third sub screen below.

Continue

If we select one of the above options, the same gets saved in the ATP results. Otherwise, we can
select this button. In that case, system leaves the ATP screen without saving the ATP results.

Case: Confirmation on Requested Delivery Date


Case: Confirmation after Requested Delivery Date (Complete
Delivery)
Case: Confirmation after Requested Delivery Date (Partial
Delivery)
See the screens below corresponding to this situation.

The first screen shows the Availability (CO09) Overview. We have an incoming PO on 19 Jan.
!image034.jpg!In the second screen
We have created a SO (VA01) on 09 Feb, with requested Delivery date for 09 Feb.

Now we change the Availability situation, by changing the PO Date to 12


Feb. See the screens below corresponding to this situation.

The first screen shows the Availability (CO09) Overview. We have an incoming PO on 12 Feb. See
the new Cum ATP qty. date wise accordingly.

!image038.jpg!In the second screen


We have created a SO on 09 Feb, with requested Delivery date for 09 Feb.
See that the Delivery got staggered according to the new Availability situation.

Case: Confirmation after Requested Delivery Date (Replenishment


Lead Time)
In the screens below, we have simulated the RLT.
In the first scenario RLT is not activated, see below: 'Check without RLT'. The system considers
only the confirmed inward movements. So out of 500 only 21 is confirmed.
See IMG Guide > SD > BF > AC & TOR > AC > AC with ATP > Control of Availability Check
See VA01

In the second scenario RLT is activated, but corresponding data in material master is not
maintained. Material is procured In-House (E), but In-house Production time (1st screenshot) & RLT
(2nd screenshot) are not maintained. The system assumes both these times as Zero. So, complete
500 are confirmed immediately. See MM01
In the third scenario RLT is activated, corresponding data in material master is maintained.
Material is procured In-House (E), In-house Production time (10 days) & RLT (not maintained). The
system confirms 21 on basis of incoming material. Rest 479 is confirmed after 14 days. This is
because 10 working days for in-house production + 4 holidays (Sat-Sun).
In the fourth scenario RLT is activated, corresponding data in material master is maintained.
Material is procured In-House (E), In-house Production time (10 days) & RLT (20 days). The system
confirms 21 on basis of incoming material. Rest 479 is confirmed after 14 days. This is because 20
working days for in-house production + 8 holidays (Sat-Sun).

What Configuration & Data do we need?

Controlling Elements:-

Requirements Type

Requirements Class
Schedule Line Category

Delivery Item Category

Checking Group

Checking Rule

Scope of Check

Strategy Group

Partial Delivery Agreement

Replenishment Lead Time

Material Master Data:-

MRP 1 > MRP Group

MRP 2 > Planned Delivery Time

MRP 2 > GR Processing Time

MRP 3 > Checking Group for Availability Check

MRP 3 > Strategy Group

MRP 3 > Total Replenishment Lead Time

Scheduling Data:-

Transit Time

Loading Time

Pick/Pack Time

Transportation Planning Lead Time