The Cess shall be added to each bill @ 1% and then recovered from the Contractors bill.

The Cess so
recovered from the work bills has to be remitted by way of Cross Demand Draft in favour of A.P Building and
Other construction workers welfare board

DECLARATION

I, M/s. Siddhardha Constructions Private Limited, do hereby solemnly affirm and declare that I /
We own/lease the following equipment for using on the subject work and also declare that I / We
will abide by any action such as disqualification or determination of Contract or blacklisting or
any action deemed fit, if the department detects at any stage that I / We do not possess the
equipment listed below.

Sl. Name of the Equipment Availability Proposals Agt. Remarks


No. Owned Leased To be Condition
procured
1 2 3 4 5 6 7
1 Tar Boiler 2 No’s Good
2 Hot Mix Plant 1 No Good
3 Paver Finisher 1 No Good
4 Buildozer 2 No’s Good
5 Excavator 2 No’s Good

6 Air Compressor 2 N0’s Good


7 Concrete Mixers 2 No’s Good

8 Water Tankers 4 No’s Good


Contd…p/2….
:2:

9 Water Tanker with 2 no’s Good


Sprinklers
10 Power Road Rollers 2 No’s Good
11 Smooth Wheeled Tandem 1 No’s Good
Tyred Rollers
12 Trucks 4 No’s Good
13 Tractors 4 No’s Good
14 Loaders 2 No’s Good
15 Tippers 4 No’s Good
16 Vehicle Mounted 1 No. Good
Mechanical sprayer
17 Vibratory Roller 1 No. Good

For Siddhardha Constructions Private Limited

(N. Surendra Babu)


Managing Director
DECLARATION

I, M/s. Siddhardha Constructions Private Limited, do hereby solemnly affirm and declare that I /
We own the following equipment for using on the subject work and also declare that I / We will
abide by any action such as disqualification or determination of Contract or blacklisting or any
action deemed fit, if the department detects at any stage that I / We do not possess the
equipment listed below.

Sl. Details of each equipment Year of Regn, No. Any other Is it in


No. purchase data working
condition
1 2 3 4 5 6
i) Paver Finisher 1 No Good
ii) 80/100 KN Static weight 1 No Good
rollers
iii) Vibratory road roller 1 No Good

For Siddhardha Constructions Private Limited

(N. Surendra Babu)


Managing Director
DECLARATION

I, M/s. Siddhardha Constructions Private Limited, do hereby solemnly affirm and declare that I /
We own the following equipment for using on the subject work and also declare that I / We will
abide by any action such as disqualification or determination of Contract or blacklisting or any
action deemed fit, if the department detects at any stage that I / We do not possess the
equipment listed below.

Sl. Details of each equipment Year of Regn, No. Any other Is it in


No. purchase data working
condition
1 2 3 4 5 6
i) Paver Finisher 1 No Good
ii) 80/100 KN Static weight 1 No Good
roller
iii) Vibratory road roller 1 No Good

For Siddhardha Constructions Private Limited

(N. Surendra Babu)


Managing Director
Sidcons/CGM (T)/HGCL/Labour Cess/2010-11 Date 19.10.2010

To
The Chief General Manager (Tech),
Hyderabad Growth Corridor Limited,
Tarnaka,
Secunderabad.

Sir,
Sub: 1. Radial Road No 4 from km 1.50 to 3.20
2. Radial Road No 4 from km 3.20 to 5.00
3. Radial Road No 3B from km 9.00 to 10.50 – Labour Cess – Reg.

Ref: 1. CGM (T)/HGCL/01/08-09 of 2008-09 dated 17.07.2008


2. CGM (T)/HGCL/01/08-09 of 2008-09 dated 17.07.2008
3. CGM (T)/HGCL/01/08-09 of 2008-09 dated 17.07.2008
4. Our Letter No Sidcons/R&B/Court Orders/2009/17 dated 02.06.09

***
With reference to the above subject works, we would like to inform you that the all the
above 3 works are nearing completion stage and the final bills is to be paid.

Regarding recovery of 1% Building Workers Welfare Cess, We have filed writ petition in
the Hon’ble High Court of Andhra Pradesh for relief and the Hon’ble Judges were kind
enough and issued interim orders as prayed by us. The same was brought to your kind
notice vide our letter reference 4th cited. But the department is still deducting the labour
Cess amount of 1% in our Running Bills.

Further we are going to submit the Running/Final bills. But the department is objecting
to pass the Running/Final bills as the final Judgment of labour Cess is pending in
Hon’ble High Court of Andhra Pradesh.

Hence we request you to kindly keep the Labour Cess amount in deposits and pass the
Running/Final bills.
Thanking you,

Yours faithfully,
For Siddhardha Constructions (P) Ltd.,

(N.Surender Babu)
Managing Director
Sidcons/SE(R&B) NH/HYD/HB Road/2010-11 Date 08.11.2010

To
The Superintending Engineer,
(R&B) NH Circle,
HYDERABAD.

Sir,
Sub: Widening to two lane & improvement from km 301/0 to 307/ on
Hyderabad – Bhoopalpatnam section on NH 202 under LWE
Project – Regarding.

Ref: Letter No 2762/T1/SENH/HYD/2010-11, 1692, DT 02.11.2010.

***

With reference to the above, we are here with enclose the following two site
Engineers Qualification certificates as desired by you.
1. P.Ganesh – B.Tech. (Civil)
2. G.Rajashekar – B.E (Civil)

Thanking you,

Yours faithfully,
For Siddhardha Constructions (P) Ltd.,

(N.Surender Babu)
Managing Director

Encl: A/a
FINANCIAL SITUATION:

Should have made profit in any 3 years out of last 5 years


 The Lead Partner needs not to meet requirement.
 The document of Form FIN – I with attachments is required

TURNOVER:
 Minimum average annual Turnover is to be 1584 Millions or say
158.40 Crores.
 The lead Partner must meet 50% of the requirement.
 The document of Form FIN – 2 with attachments is required

CASH FLOW:
 Minimum cash flow requirement is 264 Millions or say 26.40 Crores.
 The Lead Partner shall meet 50% of the requirement i.e.13.20 Crores.
 The document of Form FIN – 3 (a) with attachments is required

EXPERIENCE:
 1584 Millions Or 158.40 Crores contract with in the last five years.
 The Lead Partner need not meet the requirement.

QUANTITYS:
 Earthwork/Embankment/Sub Grade : 4,76,700 Cum
 GSB : 70,900 Cum
 WMM : 65,600 Cum
 BM/SDBC/BC/DBM : 56,200 Cum
 The lead partner shall meet 50% of the requirement quantities

Sidcons/SE(R&B) NH/HYD/HB Road/2010-11 Date 08.11.2010

To
The Superintending Engineer,
(R&B) NH Circle,
HYDERABAD.

Sir,
Sub: Widening to two lane & improvement from km 301/0 to 307/ on
Hyderabad – Bhoopalpatnam section on NH 202 under LWE Project
& Widening to two lane with paved shoulders from km 169/7 to183/5
of Vijayawada – Jagadalpur road on NH 221 - Authorization – Reg.

Ref: 1. Letter No 2709/TO/SENH/HYD/2010-11, DT 08.11.2010.


2. Letter No 2762/T1/SENH/HYD/2010-11, DT 08.11.2010.
***

With reference to the above we here by authorize Sri. M.Vinod Kumar Reddy to
attend price bid meeting and his specimen signature is attested below.

Thanking You,

Yours faithfully,
For Siddhardha Constructions (P) Ltd.,
//Attested//

(N.Surender Babu) For Siddhardha Constructions (P) Ltd.,


Managing Director

(N.Surender Babu)
Managing Director
Sidcons/EE(R&B) Sangareddy/2010-11 Date .11.2010

To
The Executive Engineer,
(R&B) Division,
SANGAREDDY.

Sir,
Sub: Improvements to carriageway from Km.0/0 to 25/0 of Jogipet –
Vatpally road in Medak District. (Work in km.0/8 to 4/2).

Ref: SE LS AB No 117/2008-09, dt.04.02.2009


..
***

With reference to the above we request you kindly issue VAT 501 certificate for
2nd & part bill at the earliest.
Thanking You,

Yours faithfully,
For Siddhardha Constructions (P) Ltd.,

(M.Vinod Kumar Reddy)


Sidcons/Court case/VAT/2010-11 Date: 18.11.2010

To
Sri. P.Gireesh Kumar,
Advocate,
Khairatabad,
HYDERABAD.

Sir,
Sub: Withdraw of W.P No 14026 of 2009

***

With reference to the above W.P.No of 14026 we here by withdraw as the


respondents are agreed to pay the VAT difference amounts in future bills.
Hence we are withdrawn the W.P.No of 2009.

Thanking You,

Yours faithfully,
For Siddhardha Constructions (P) Ltd.,

(N.Surender Babu)
Managing Director