You are on page 1of 14

Arbitration 2011

1. CHUNG FU INDUSTRIES v. CA Issue: Is the award beyond the power of judicial review on the basis
G.R. No. 96283 February 25, 1992 of a stipulation that the award is final and unapppealable?

Facts: Held: NO.


Chung Fu and private respondent Roblecor forged a construction
agreement 1 whereby respondent contractor committed to construct Pertinent topic: Evolution of arbitration as a mode of
Chung Fu COrp’s industrial/factory complex in Cavite for P42M. Two dispute settlement.
other construction contracts were enetered into. In the event of Legal history discloses that "the early judges called upon to solve
disputes arising from the performance of the contract, it was private conflicts were primarily the arbiters, persons not specially
stipulated that the issue(s) shall be submitted for resolution before trained but in whose morality, probity and good sense the parties in
an arbitrator chosen by both parties. Roblecor failed to complete the conflict reposed full trust. Thus, in Republican Rome, arbiter and
work despite the extension of time and so Chung Fu took over the judge (judex) were synonymous. The magistrate or praetor, after
construction when it had become evident that Roblecor was not in a noting down the conflicting claims of litigants, and clarifying the
position to fulfill its obligation. issues, referred them for decision to a private person designated by
the parties, by common agreement, or selected by them from an
Claiming an unsatisfied account of P10.5M and unpaid progress apposite listing (the album judicium) or else by having the arbiter
billings of P2.3 M, Roblecor filed a petition for Compulsory chosen by lot. The judges proper, as specially trained state officials
Arbitration with prayer for TRO before RTC. Chung Fu moved to endowed with own power and jurisdiction, and taking cognizance of
dismiss the petition and further prayed for the quashing of the litigations from beginning to end, only appeared under the Empire,
restraining order. by the so-called cognitio extra ordinem." 5

The parties entered into an arbitration agreement providing that: Sparse though the law and jurisprudence may be on the subject of
“The parties mutually agree that the decision of the arbitration in the Philippines, it was nonetheless recognized in the
arbitrator shall be final and unappealable. Therefore, there Spanish Civil Code and now reinstated in the present Civil Code. 9
shall be no further judicial recourse if either party disagrees
with the whole or any part of the arbitrator's award. Although early on, CA No. 103 (1936) provided for compulsory
f. As an exception to sub-paragraph (e) above, the parties arbitration administered by the CIR in case of labor-mgt disputes,
mutually agree that either party is entitled to seek judicial such was converted to voluntary arbitration. The Industrial Peace
assistance for purposes of enforcing the arbitrator's award;” Act which was passed in 1953 favoring the policy of free collective
bargaining, and resort to grievance procedure. It was accepted and
When the arbitrator ordered petitioners to pay respondent enunciated more explicitly in the present Labor Code.
contractor P16M and declared the award as final and unappealable
pursuant to the Arbitration Agreement, which precluded judicial RA No. 876 (1953) the Arbitration Law, was passed to regulate the
review of the award, Chung Fu moved to remand the case for arbitration process. "Said Act was obviously adopted to supplement
further hearing claiming (12) instances of grave error by — not to supplant — the New Civil Code on arbitration. It expressly
disregarding the provisions of the parties' contract. declares that "the provisions of chapters one and two, Title XIV,
Book IV of the Civil Code shall remain in force." 11
CA concurred with the RTC resolving that Chung Fu and its officers,
as signatories to the Arbitration Agreement are bound to observe In recognition of the pressing need for an arbitral machinery in the
the stipulations thereof providing for the finality of the award and construction industry, a Construction Industry Arbitration
precluding any appeal therefrom. Hence, the instant petition for Commission (CIAC) was created by Executive Order No. 1008,
certiorari to the SC. enacted on February 4, 1985.

Recourse to an extrajudicial means of settlement is not intended to


Page 1 of 14
Arbitration 2011
completely deprive the courts of jurisdiction. In fact, the early cases the award under Section 24 (d) of the Arbitration Law.
on arbitration carefully spelled out the prevailing doctrine at the But the respondent trial court's refusal to look into the merits of the
time, thus: ". . . a clause in a contract providing that all matters in case, despite prima facie showing of the existence of grounds
dispute between the parties shall be referred to arbitrators and to warranting judicial review, effectively deprived petitioners of their
them alone is contrary to public policy and cannot oust the courts of opportunity to prove or substantiate their allegations. In so doing,
Jurisdiction." But certainly, the stipulation to refer all future disputes the trial court itself committed grave abuse of discretion. Likewise,
to an arbitrator or to submit an ongoing dispute to one is valid. the appellate court, in not giving due course to the petition,
Being part of a contract between the parties, it is binding and committed grave abuse of discretion.
enforceable in court in case one of them neglects, fails or refuses to
arbitrate. In case of a declaration to refer their differences to WHEREFORE, the petition is GRANTED. Accordingly, this case is
arbitration first before taking court action, this constitutes a REMANDED to the court of origin for further hearing on this matter.
condition precedent, such that where a suit has been instituted
prematurely, the court shall suspend the same and the parties shall
be directed forthwith to proceed to arbitration.

Is the subject arbitration award indeed beyond the ambit of


the court's power of judicial review? NO.

Where the conditions described in Articles 2038, 2039 and 2040


applicable to both compromises and arbitrations are obtaining, the
arbitrators' award may be annulled or rescinded. 19 Additionally,
under Sections 24 and 25 of the Arbitration Law, there are grounds
for vacating, modifying or rescinding an arbitrator's award. 20
Similarly, the Construction Industry Arbitration Law provides that
the arbitral award "shall be final and inappealable except on
questions of law which shall be appealable to the Supreme Court." 16

If courts (such as RTC in this case) refuse or neglect to inquire into


the factual milieu of an arbitrator's award to determine whether it is
in accordance with law or within the scope of his authority, judicial
review be invoked through Rule 65 certiorari. However, the Court
will not engage in a review of the facts found nor even of the law as
interpreted or applied by the arbitrator unless the supposed errors
of fact or of law are so patent and gross and prejudicial as to
amount to a grave abuse of discretion or an exces de pouvoir on the
part of the arbitrator." 21

The SC after closely studying the list of errors finds that petitioners
have amply made out a case where the voluntary arbitrator failed to
apply the terms and provisions of the Construction Agreement
which forms part of the law applicable as between the parties, thus
committing a grave abuse of discretion in granting unjustified extra
compensation to respondent for several items, he exceeded his
powers — all of which would have constituted ground for vacating
Page 2 of 14
Arbitration 2011
—Bill of Lading #1 covered 10,000 metric tons for Manila; Bill of
Lading #2 covered 4,000 metric tons for Iloilo; and Bill of Lading #3
covered 1,500 metric tons for Manila.

Except for those under Bill of Lading #2, the shipments covered by
the other Bills of Lading (bound for Manila) were discharged in bad
order and condition, to which damages were valued at P683,056.29.
Because of this, Puromines filed a complaint with the RTC of Manila
for breach of contract of carriage against Maritime Factors Inc as
ship agent in the Philippines for the owners of the vessel. Philipp
Brothers Oceanic was impleaded as charterer of the vessel and
proper party for complete relief.

Maritime Factors filed an answer while Philipp Brothers Oceanic filed


a Motion to Dismiss on the ground that the complaint was
prematurely filed because of non-compliance with the arbitration
clause provided in the sales contract. Puromines opposed this
motion contending that the arbitration clause is inapplicable since
the cause of action arose for the claims of cargo damages (no
arbitration agreement) and not from the sales contract (with
arbitration clause). RTC denied the motion; CA reversed.

ISSUE
Whether the phrase “any dispute arising under this contract”
stipulated in the arbitration clause of the sales contract covers a
cargo claim against the vessel (owners and charters) for breach of
contract of carriage—YES.

2. PUROMINES v COURT OF APPEALS and PHILIPP BROTHERS


OCEANIC INC. RULING
G.R. No. 91228, March 22, 1993 The Supreme Court agreed with the Court of Appeals that the sales
contract is comprehensive enough to include claims for damages
FACTS arising from carriage and delivery of the goods. Generally, the seller
Puromines Inc and Makati Agro Trading (not a party to this case) has the obligation to transmit the goods to the buyer, and thus, the
entered into a contract with Philipp Brothers Oceanic Inc for the sale contracting of a carrier to deliver the goods.
of prilled Urea (organic compound used as animal feeder additive
and fertilizer) in bulk. The sales contract provided for an arbitration As correctly argued by Philipp Brothers Oceanic, Puromines derived
clause, which states that any dispute arising under the contract its right to the cargo from the bill of lading, which is the contract of
should be settled by arbitration in London in accordance with its affreightment, together with the sales contract. Thus, it is bound by
arbitration law. the provisions of both the bill of lading and the sales contract.

In 1988, vessel M/V Liliana Dimitrova loaded a shipment of 15,500 The Court also ruled that the parties are nevertheless obligated to
metric tons of prilled Urea in bulk from Yuzhny, USSR to be respect the arbitration clause on the sales contract and/or bill of
transported to Iloilo and Manila. Three (3) bills of lading were issued
Page 3 of 14
Arbitration 2011
lading. Puromines, being a signatory and party to the sales contract,
cannot escape from his obligation under the arbitration clause. 3. BF Corp v CA, Shangri-La Properties Inc (SPI)| Romero
G.R. No. 120105, March 27, 1998 | 288 SCRA 267
Neither can petitioner contend that the arbitration clause in the bills
of lading should not have been discussed as an issue because it was FACTS
not raised as a special or affirmative defense. However, the bills of • BF Corp and SPI entered into an agreement to where BF was to
lading were attached as annexes to the complaint and may be construct the main structure of EDSA Plaza Project (Shangri-La Mall).
considered as evidence although not introduced as such. Hence, it This was contained in the ARTICLES OF AGREEMENT.
was proper for the CA to discuss the contents of the bills of lading, • BF incurred delay in the completion of the project, which SPI considered
having been made part of the record. to be serious and substantial while BF holds that it was in faithful
compliance with their FIRST AGREEMENT. Later, Phase I of the project
Arbitration has been held valid and constitutional that even before was gutted by fire (in Nov 1990) which further exacerbated their
the enactment of RA 876, the Court has allowed the settlement of situation. SPI proposed a re-negotiation.
disputes through arbitration. The rule now is that unless the • May 30 1991: BF and SPI entered into an Agreement (Agreement for the
agreement is such as absolutely to close the doors of the courts Execution of Builder’s Work for Edsa Plaza Project). This agreement
covers the construction until it’s eventual completion, set on October
against the parties, which agreement would be void, the courts will
31, 1991.
look with favor upon such amicable arrangements and will only
• SPI said there was failure to complete the project, which sparked
interfere with great reluctance to anticipate or nullify the action of
disagreement between the parties
the arbitrator.
• November 1991: BF billed SPI and demanded payment. Instead of
paying, SPI counterclaimed P220M for the delay in the construction
(pursuant to penalty clause of the agreement: Php80K for every day of
delay from Nov. 1 1991 up to 5% of the contract price)
• July 12, 1993: SPI initiated a conference but they failed to agree.
• July 14, 1993: BF filed a complaint to collection of the balance due (110,
883, 101.52).
• August 3, 1993: SPI filed motion to suspend proceedings (instead of
filing an answer) claiming that their agreement contained an arbitration
clause—(that there should be prior resort to arbitration before resorting
to judicial proceedings). BF opposed this motion claiming:
o there was no formal contract to arbitrate because the
CONDITIONS OF THE CONTRACT which contained the
arbitration clause did not comply with the formal requisites of
an arbitration contract pursuant to Sec 4 of RA876 (this
instrument did not bear the signature of representative of SPI
and Bayani Fernando, Pres. of BF Corp only initialed it), hence
there is no arbitration clause to speak of.
• TC: denied the motion to suspend proceedings. It also said that
assuming there was an arbitration clause, demand to arbitrate was not
reasonably made because SPI failed to file a written demand to
arbitrate for 1 year and 8 mos already (counted from the time BF billed
them to pay until the filing of collection complaint)
• SPI filed a petition for certiorari under R65 to the CA.
• CA: granted the petition and set aside the orders of the TC, hence this
Petition for Review on Certiorari

Page 4 of 14
Arbitration 2011
• Court also ruled that reasonable time is relative. In this case,
ISSUES & ARGUMENTS the 1-mo period from the time they held a conference (July 12,
• Whether the ARBITRATION CLAUSE EXISTS? 1993) that SPI invoked the arbitration clause is within a
• Does the CA have the jurisdiction to determine this issue reasonable time.
even if on it’s face , the existence of an arbitration clause • Court highlighted: that arbitration is “the wave of the future”
is a factual matter? and that this is recognized worldwide. To brush aside the
HOLDING & RATIO DECIDENDI contractual agreement between the parties calling for arbitration
ARBITRATION CLAUSE EXISTS. The CA have jurisdiction. in case of disagreement between the parties would therefore be
Although on its face, the existence of an arbitration clause a step backward.
is a factual matter, in this case, the existence of the • (REMEDIAL PART) Where a rigid application of the rule that
arbitration clause depends upon the interpretation of Sec 4 certiorari cannot be a substitute for appeal will result in a
of RA 876 (Formal Requisite of an Arbitration Clause) which manifest failure or miscarriage of justice, the provisions of the
is a question of law. It became the proper subject of a Rules of Court which are technical rules may be relaxed. As we
petition for certiorari because the CA had to determine (by shall show hereunder, had the CA dismissed the petition for
settling the question of law) whether the TC prematurely certiorari, the issue of whether or not an arbitration clause exists
assumed jurisdiction over the case. in the contract would not have been resolved in accordance with
• (ARBITRATION PART) The Court finds that, upon a scrutiny of evidence extant in the record of the case. Consequently, this
the records of this case, these requisites were complied with in would have resulted in a judicial rejection of a contractual
the contract in question. The Articles of Agreement, which provision agreed by the parties to the contract. In the same
incorporates all the other contracts and agreements between vein, this Court holds that the question of the existence of the
the parties, was signed by representatives of both parties and arbitration clause in the contract between petitioner and private
duly notarized. The failure of the private respondent's respondents is a legal issue that must be determined in this
representative to initial the "Conditions of Contract" would petition for review on certiorari.
therefore not affect compliance with the formal requirements for
arbitration agreements because that particular portion of the WHEREFORE, premises considered, the instant petition is
covenants between the parties was included by reference in the DENIED. The Decisions of the CA is AFFIRMED.
Articles of Agreement. 4. FIESTA WORLD MALL CORPORATION vs. LINBERG
• Petitioner's contention that there was no arbitration clause PHILIPPINES, INC.
because the contract incorporating said provision is part of a G.R. NO. 152471 August 18, 2006
"hodge-podge" document, is therefore untenable. A contract
need not be contained in a single writing. It may be FACTS:
collected from several different writings which do not conflict Fiesta World Mall Corporation, petitioner, owns and operates
with each other and which, when connected, show the parties, Fiesta World Mall located at Barangay Maraouy, Lipa City; while
subject matter, terms and consideration, as in contracts entered Linberg Philippines, Inc., respondent, is a corporation that builds and
into by correspondence. A contract may be encompassed in operates power plants.
several instruments even though every instrument is not signed
by the parties, since it is sufficient if the unsigned On January 19, 2000, respondent filed with the Regional Trial
instruments are clearly identified or referred to and Court (RTC), Pasig City, a Complaint for Sum of Money against
made part of the signed instrument or instruments. petitioner. The complaint alleges that on November 12, 1997,
Similarly, a written agreement of which there are two copies, petitioner and respondent executed a build-own-operate
one signed by each of the parties, is binding on both to the same agreement, entitled "Contract Agreement for Power Supply
extent as though there had been only one copy of the Services, 3.8 MW Base Load Power Plant" (the Contract). Under this
agreement and both had signed it. Contract, respondent will construct, at its own cost, and operate as
Page 5 of 14
Arbitration 2011
owner a power plant, and to supply petitioner power/electricity at its If FIESTA WORLD disputes the amount specified by any
shopping mall in Lipa City. Petitioner, on the other hand, will pay invoice, it shall pay the undisputed amount on or before such
respondent "energy fees" to be computed in accordance with the date(s), and the disputed amount shall be resolved by arbitration of
Seventh Schedule of the Contract. three (3) persons, one (1) by mutual choice, while the other two (2)
to be each chosen by the parties themselves, within fourteen (14)
The complaint further alleges that respondent constructed days after the due date for such invoice and all or any part of the
the power plant in Lipa City at a cost of about P130,000,000.00. In disputed amount paid to LINBERG shall be paid together with
November 1997, the power plant became operational and started interest pursuant to Article XXV from the due date of the invoice. It
supplying power/electricity to petitioner’s shopping mall in Lipa City. is agreed, however, that both parties must resolve the disputes
In December 1997, respondent started billing petitioner. As of May within thirty (30) days, otherwise any delay in payment resulting to
21, 1999, petitioner’s unpaid obligation amounted to loss to LINBERG when converted to $US as a result of depreciation
P15,241,747.58, exclusive of interest. However, petitioner of the Pesos shall be for the account of FIESTA WORLD. Corollarily,
questioned the said amount and refused to pay despite in case of erroneous billings, however, LINBERG shall be liable to
respondent’s repeated demands. pay FIESTA WORLD for the cost of such deterioration, plus interest
computed pursuant to Art. XXV from the date FIESTA WORLD paid
In its Answer with Compulsory Counterclaim, petitioner for the erroneous billing.
specifically denied the allegations in the complaint, claiming that
respondent failed to fulfill its obligations under the Contract by Thereafter, petitioner filed a Motion to Set Case for
failing to supply all its power/fuel needs. From November 10, 1998 Preliminary Hearing on the ground that respondent violated the
until May 21, 1999, petitioner personally shouldered the cost of fuel arbitration clause provided in the Contract, thereby rendering its
(Lindberg should supply the fuel under the contract). Petitioner also cause of action premature.
disputed the amount of energy fees specified in the billings made by
respondent because the latter failed to monitor, measure, and This was opposed by respondent, claiming that paragraph
record the quantities of electricity delivered by taking photographs 7.4 of the Contract on arbitration is not the provision applicable to
of the electricity meter reading prior to the issuance of its invoices this case; and that since the parties failed to settle their dispute,
and billings, also in violation of the Contract. Moreover, in the then respondent may resort to court action pursuant to paragraph
computation of the electrical billings, the minimum off-take of 17.2 of the same Contract which provides:
energy (E2) was based solely on the projected consumption as
computed by respondent. However, based on petitioner’s actual 17.2 Amicable Settlement
experience, it could not consume the energy pursuant to the The parties hereto agree that in the event there is any
minimum off-take even if it kept open all its lights and operated all dispute or difference between them arising out of this Agreement or
its machinery and equipment for twenty-four hours a day for a in the interpretation of any of the provisions hereto, they shall
month. This fact was admitted by respondent. While both parties endeavor to meet together in an effort to resolve such dispute by
had discussions on the questioned billings, however, "there discussion between them but failing such resolution the Chief
were no earnest efforts to resolve the differences in Executives of LINBERG and FIESTA WORLD shall meet to resolve
accordance with the arbitration clause provided for in the such dispute or difference and the joint decision of such shall be
Contract." binding upon the parties hereto, and in the event that a settlement
of any such dispute or difference is not reached, then the provisions
Finally, as a special affirmative defense in its answer, of Article XXI shall apply.
petitioner alleged that respondent’s filing of the complaint Article XXI, referred to in paragraph 17.2 above, reads:
is premature and should be dismissed on the ground of non- ARTICLE XXI (JURISDICTION)
compliance with paragraph 7.4 of the Contract which
provides: The parties hereto submit to the exclusive jurisdiction of the
7.4 Disputes proper courts of Pasig City, Republic of the Philippines for the
Page 6 of 14
Arbitration 2011
hearing and determination of any action or proceeding arising out of them may compel the other to arbitrate. Thus, it is well within
or in connection with this Agreement. petitioner’s right to demand recourse to arbitration.

In its Order dated October 3, 2000, the trial court denied We cannot agree with respondent that it can directly seek
petitioner’s motion for lack of merit. judicial recourse by filing an action against petitioner simply
because both failed to settle their differences amicably. Suffice it to
Petitioner then filed a Motion for Reconsideration but it was state that there is nothing in the Contract providing that the parties
denied in an Order dated January 11, 2001. may dispense with the arbitration clause. Article XXI on jurisdiction
cited by respondent, i.e., that "the parties hereto submit to the
Dissatisfied, petitioner elevated the matter to the Court of exclusive jurisdiction of the proper courts of Pasig City" merely
Appeals via a Petition for Certiorari. On December 12, 2001, the provides for the venue of any action arising out of or in connection
appellate court rendered its Decision dismissing the petition and with the stipulations of the parties in the Contract.
affirming the challenged Orders of the trial court.
Petitioner’s Motion for Reconsideration of the above Decision In this connection, since respondent has already filed a
was likewise denied by the appellate court in its Resolution dated complaint with the trial court without prior recourse to arbitration,
February 28, 2002. the proper procedure to enable an arbitration panel to resolve the
parties’ dispute pursuant to their Contract is for the trial court to
Hence, the instant Petition for Review on Certiorari. stay the proceedings. After the arbitration proceeding has been
pursued and completed, then, the trial court may confirm the award
ISSUE: made by the arbitration panel.
The sole issue for our resolution is whether the filing with the
trial court of respondent’s complaint is premature.

HELD:
Paragraph 7.4 of the Contract, quoted earlier, mandates that
should petitioner dispute any amount of energy fees in the invoice
and billings made by respondent, the same "shall be resolved by
arbitration of three (3) persons, one (1) by mutual choice, while the
other two (2) to be each chosen by the parties themselves." The
parties, in incorporating such agreement in their Contract, expressly
intended that the said matter in dispute must first be resolved by an
arbitration panel before it reaches the court. They made such
arbitration mandatory.

It is clear from the records that petitioner disputed the


amount of energy fees demanded by respondent. However,
respondent, without prior recourse to arbitration as required in the
Contract, filed directly with the trial court its complaint, thus
violating the arbitration clause in the Contract.

It bears stressing that such arbitration agreement is the law


between the parties. Since that agreement is binding between
them, they are expected to abide by it in good faith. And because it
covers the dispute between them in the present case, either of
Page 7 of 14
Arbitration 2011
under a Financial and Technical Assistance Agreement (FTAA).
Arimco Mining obtained the FTAA and carried out work such.

Climax Mining executed the Operating and Financial


Accommodation Contract (between Climax-Arimco Mining
Corporation and Climax Mining Ltd., and Australasian Philippines
Mining Inc. (APMI)) and Assignment, Accession Agreement (between
Climax-Arimco Mining and APMI). Climax and APMI entered into a
Memorandum of Agreement whereby the former transferred its
FTAA to the latter.

Gonzales filed before the Panel of Arbitrators a Complaint seeking


the nullity or termination of the Addendum Contract, the FTAA, the
Operating and Financial Accommodation Contract, the Assignment,
Accession Agreement, and the Memorandum of Agreement on the
grounds of fraud, oppression and violation of the constitution.

The Panel of Arbitrators dismissed the Complaint for lack of


jurisdiction. MR was filed which was granted. It held that there was a
mining dispute between the parties.

5. Gonzales v. Climax Mining Ltd. (2005) On appeal, the CA held that the Panel of Arbitrators does not have
jurisdiction.
FACTS: Jorge Gonzales is the claimowner of mineral deposits
located in the provinces of Quirino and Nueva Vizcaya. He entered ISSUE: Whether the complaint filed by Gonzales raises a mining
into a co-production, joint venture and /or production sharing letter- dispute over which the Panel of Arbitrators has jurisdiction? or a
agreement (May 14, 1987 Letter of Intent) with Geophilippines Ltd. judicial question which should be brought before the regular courts?
and Inmex Ltd. The agreement granted to Geophilippines and Inmex
collectively, the exclusive right to explore and survey the mining HELD/ RATIO: SC held that the complaint raises a judicial question
claims for a period of 3 years within which it could decide to take an which should be brought before the regular courts.
operation agreement on the mining claims and/or develop, operate,
mine and exploit the mining claims and market minerals that may A judicial question is a question that is proper for determination by
be derived therefrom. The parties renegotiated the May 14, 1987 the courts. A judicial question is raised when the determination of
Letter of Intent into the Feb. 28, 1989 Agreement wherein they the question involves the determination of what the law is and what
extended the agreement to another 3 years. the legal rights of the parties are with respect to the matter in
controversy. This is a question which involves the exercise of a
Thereafter, Gonzales, Arimco Mining Corporation, Geophilippines judicial function.
Inc., Inmex Ltd., and Aumex Philippines, Inc. signed a document
designated as the Addendum to the May 14, 1987 Letter of Intent A mining dispute is a dispute involving a) rights to mining area, b)
and February 28, 1989 Agreement with Express Adhesion Thereto mineral agreements, FTAAs, or permits and c) surface owners,
(hereafter, Addendum Contract). Under the Addendum Contract, occupants and claimholders/ concessionaires. Under the Philippine
Arimco Mining would apply to the Government of the Philippines for Mining Act of 1995 (RA No. 7942), the Panel of Arbitrators has
permission to mine the claims as the Government’s contractor exclusive and original jurisdiction to hear and decide these mining
disputes.
Page 8 of 14
Arbitration 2011
Also, the fact that the dispute involves FTAAs does not mean that it
In this case, the complaint charged Climax Mining with disregarding is exclusively within the jurisdiction of the Panel of Arbitrators. The
and ignoring provisions of the Addendum Contract, violating the Complaint raised the issue of the constitutionality of the FTAA,
purpose and spirit of the May 14, 1987 Letter of Intent and Feb. 28. which is definitely a judicial question. The Panel of Arbitrators does
1989 Agreement, and acting in fraudulent and oppressive manner not have jurisdiction over such an issue since it does not involve the
against Gonzales. It was alleged that Climax-Arimco had committed application of technical knowledge and expertise relating to mining.
to complete the Bankable Feasibility Study by 28 February 1992, Furthermore, arbitration before the Panel of Arbitrators is proper
but the same was not accomplished. Instead, Climax-Arimco, only when there is a disagreement between the parties as to some
through false and insidious representations and machinations by provisions of the contract between them, which needs the
alleging technical and financial capacity, induced Gonzales to enter interpretation and the application of that particular knowledge and
into the Addendum Contract and the FTAA in order to repeatedly expertise possessed by members of that Panel. It is not proper when
extend the option period within which to conduct the feasibility one of the parties repudiates the existence or validity of such
study. contract or agreement on the ground of fraud or oppression as in
this case. The validity of the contract cannot be subject of
It is apparent that the Panel of Arbitrators is bereft of jurisdiction arbitration proceedings. Allegations of fraud and duress in the
over the Complaint filed by Gonzales. The basic issue in the execution of a contract are matters within the jurisdiction of the
Complaint is the presence of fraud or misrepresentation allegedly ordinary courts of law. These questions are legal in nature and
attendant to the execution of the Addendum Contract and the other require the application and interpretation of laws and jurisprudence
contracts emanating from it, such that the contracts are rendered which is necessarily a judicial function.
invalid and not binding upon the parties. This constitutes fraud
which vitiated Gonzales’ consent, and under Article 1390 of the Civil Therefore, the case should not be brought under the ambit of the
Code, is one of the grounds for the annulment of a voidable Arbitration Law. The complaint should have been filed before the
contract. Gonzales insists that the Complaint is actually one for the regular courts as it involved issues which are judicial in nature.
declaration of nullity of void contracts. However, whether the case
involves void or voidable contracts is still a judicial question. It may, 6. Gonzales vs. Climax Mining (2007)
in some instances, involve questions of fact especially with regard
to the determination of the circumstances of the execution of the This is a consolidation of 2 previous cases in the same disputed
contracts. But the resolution of the validity or voidness of the Addendum Contract entered into by the parties. The first case stems
contracts remains a legal or judicial question as it requires the from the petition to compel arbitration filed by Climax-Arimco before
exercise of judicial function. It requires the ascertainment of what the RTC of Makati while the complaint for the nullification of the
laws are applicable to the dispute, the interpretation and application Addendum Contract was pending before the DENR Panel of
of those laws, and the rendering of a judgment based thereon. Arbitrators. Climax had sent Gonzales a demand for arbitration
Clearly, the dispute is not a mining conflict. It is essentially judicial. pursuant to the arbitration clause of the Addendum Contract.
The complaint was not merely for the determination of rights under Gonzales filed a motion to dismiss alleging that the Addendum
the mining contracts since the very validity of those contracts is put Contract containing the arbitration clause is void in view of the acts
in issue. The Complaint is not about a dispute involving rights to of fraud, oppression and violation of the Constitution and other acts
mining areas, nor is it a dispute involving claimholders or committed by Climax. The RTC granted Gonzales motion and set the
concessionaires. The main question raised was the validity of the case for pre-trial. Another motion for reconsideration filed by Climax
Addendum Contract, the FTAA and the subsequent contracts. The claiming that RA 876 does not authorize a pre-trial but directs the
question as to the rights of the parties to the mining area pursuant court to hear the motion summarily and resolve the same within 10
to these contracts is merely corollary to the main issue, and may days. Judge Pimentel granted the motion and directed the parties to
not be resolved without first determining the main issue. arbitration. Gonzales is now assailing the order of Judge Pimentel

Page 9 of 14
Arbitration 2011
Issue: Won it was proper for the RTC, in the proceeding to
compel arbitration to order the parties to arbitrate even
though the defendant therein has raised the twin issues of
validity and nullity of the Addendum Contract

Held: Yes, should go to arbitration

Disputes do not go to arbitration unless and until the parties


have agreed to abide by the arbitrator’s decision. Necessarily , a
contract is required for arbitration to take place and to be binding.
Two or more persons may submit to the arbitration of one or more
arbitrators any controversy existing between them at the time of
the submission which may be the subject of an action, or the parties
may in such contract agree to settle by arbitration a controversy
thereafter arising between them. Such submission shall be valid,
enforceable and irrevocable, except on grounds recognized by law
for the revocation of any contract.
The reparability of the arbitration agreement is especially
significant for the determination of whether the invalidity of the
main contract also nullifies the arbitration clause. Irrespective of the
fact that the main contract is invalid, the arbitration clause or
agreement still remains valid and enforceable. 7. Agan v. PIATCO
G.R. No. 155001
The U.S. courts held that courts should not order the parties 5 May 2003
to arbitrate if the making of the arbitration agreement is in issue.
The parties should be ordered to arbitration if they have contracted Facts
to submit to arbitration. The courts have held that the validity of the Petitioners and petitioners-in-intervention filed petitions for
contract containing the agreement to submit to arbitration does not prohibition under Rule 65 to prevent MIAA and DOTC from
affect the applicability of the arbitration clause itself. A contrary implementing agreements executed by the government through
ruling would suggest that a party’s mere repudiation of the main DOTC and MIAA and PIATCO.
contract is sufficient to avoid arbitration. That is exactly the
situation that the separability doctrine seeks to avoid. On August 1989, DOTC engaged the services of Aeroport de Paris
(ADP) to conduct a study on NAIA to determine whether the airport
can cope with traffic development until the year 2010. ADP was to
determine:

1. traffic forecasts and capacity of existing facilities and NAIA


future development plans
2. presentation of preliminary design of passenger terminal
building.

ADP submitted a draft to DOTC on December of the same year.

Page 10 of 14
Arbitration 2011
On 1993, 6 business leaders consisting of Gokongwei , Sy, Tan, and 1. lack of corporate approval and financial capability of
Yuchengco went to FVR to explore the possibility of investing in PAIRCARGO and PAGS
construction and operation of the new airport terminal. To show 2. prohibition by general banking act on amount of Security
their commitment to pursue the project they formed Asia’s Bank that it could legally invest
Emerging Dragon Corp. (AEDC) duly registered with SEC. 3. inclusion of Seimens as contractor of PAIRCARGO
4. appointment of Lufthansa as facility operator of a public
The next year they submitted an unsolicited business proposal to utility
the government through DOTC/MIAA for the development of NAIA 3
under BOT arrangement pursuant to the BOT law (RA 6957 as AEDC offered the government 135million pesos as guaranteed
amended RA 7718). payment for 27 years
PAIRCARGO consortium offered 17.75 billion pesos.
DOTC issued a department order constituting the PBAC PBAC formally informed AEDC that it had accepted PAIRCARGO’s
(Prequalification Bids and Awards Committee) for the price proposal.
implementation of the NAIA 3. This was forwarded to AEDC and to AEDC failed to match the bid within 30days.
NEDA. NEDA passed a resolution approving the project. Thus PAIRCARGO incorporated into PIATCO (Phil. Int’l Airport
Terminals Co. Inc.)
1996 DOTC/MIAA caused publication for competitive proposals on
AEDC’s unsolicited proposal. The bidders were required to submit in AEDC filed with the RTC a petitioner for declaration of nullity of the
3 sealed envelopes: proceedings, mandamus and injunction against DOTC secretary et
al.
1. Prequalification Documents
2. Technical Proposal On July 12, 1997 DOTC and PIATCO signed a concession agreement
3. Financial Proposal to franchise, operate, and maintain NAIA 3. But on November 28,
1998, the government and PIATCO signed an amended and restated
In PBAC Bulletin No. 1, DOTC postponed the availment of bid concession agreement (ARCA) which had the ff changes:
documents to June 28, 1996 upon submission of a written 1. definition of cert of completion
application and a nonrefundable fee of P50, 000. 2. special obligation of RP
3. exclusivity franchise given to concessionaire
Proponent must have : 4. proceeds of concessionaire’s insurance
1. adequate financial capability to sustain detailed engineering, 5. temporary takeover of the government
design, construction and maintenance of the phases of the 6. taxes and duties that may be levied on the Concessionaire
project 7. periodic assessment of public utility fees
2. minimum amount of equity for the project (30% of the proj 8. provisions on termination of contract
cost) 9. venue of arbit proceedings in case of dispute
3. capacity to secure external financing
Subsequently government and PIATCO signed 3 supplemental
On September, the PAIRCARGO consortium consisting of the ff, agreements.
submitted their bid.
PAIRCARGO (People’s Air Cargo and Warehousing Corp) On Sept 17, 2002 workers of international airline and service
Security Bank providers claiming that they stand to lose their employment upon
PAGS (Phil. Air & Grounds Services Inc.) implementation of the agreements filed a petition for prohibition to
enjoin enforcement of said agreements.
AEDC questioned the qualification of PAIRCARGO because of:

Page 11 of 14
Arbitration 2011
On October 15, 2002 the service providers joining the cause of In Del Monte v CA, even after finding that the arbit clause is valid
workers filed a motion for intervention. and binding and the dispute arbitrable, the court affirmed the
jurisidiction of the courts to hear the dispute. In so ruling, the court
On October 24, 2002 several congressmen filed a similar petition. held that the contracts produce legal effect between the parties,
assigns, and heir and only the parties to the agreement are bound
On Novermber 6, 2002, other employees filed a petitioner assailing by its terms including the arbit clause. The arbit clause could be
the legality of the various agreements. called for but ONLY with respect to parties in the contract in
question.
On December 11, 2002, another group of congressmen moved to
intervene DEFENDING the validity of the assailed agreements In Salas Jr. v Laperal Realty, the court held that to tolerate the
splitting of proceedings by allowing arbit as to some of the parties
OSG and OGCC filed their respective comments. on the one hand and trial for the others on the other would in effect
result in multiplicity of suits, duplicitous procedure and unnecessary
Then Former president GMA, in a speech before Shell Export Awards delay. The interest of justice would be best served if the trail court
declared that she will not honor PIATCO contracts. hears and adjudicates the case in a single and complete
proceedings.
The court heard the case on oral arguments and required the
parties to submit their memoranda and within 30days required the
parties to explore the possibility of arbit and mediation as provided
in the contracts.

On March 6, 2003, respondent PIATCO informed the court that on


March 4 in commenced arbit proceedings before the ICC (Int’l
Chamber of Commerce), ICA (Int’l Court of Arbit) by filing a request
with the secretariat of ICC against the government through
DOTC/MIAA.

Issue
PIATCO assails the jurisdiction of the court over the
proceedings in lieu of their agreement to first submit any
dispute to arbitration proceedings.

Held
The arbit step taken by PIATCO did not oust the court of its
jurisdiction.
It is established that petitioners in the present cases who have
presented legitimate interests in the resolution of the controversy
are not parties to the PIATCO contracts. They cannot be bound by
the arbit clause and cannot be compelled to submit to the
proceedings. A speedy and decisive resolution of all the critical
issues in the present controversy cannot be made before an arbitral
tribunal.

Doctrine
Page 12 of 14
Arbitration 2011
Oribanex, through the spouses Abujos, the bananas rejected by
DOLE, stating that Oribanex is an exporter of bananas.
SEARBEMCO responded with a motion to dismiss, stating that it
was the DARAB that had proper jurisdiction, that they sold to
third party buyers and not exporters, and for the prematurity of
the complaint for not being arbitrated.

The RTC and CA both ruled against SEARBEMCO, stating that the
matter was not an agrarian contract and that For DARAB to have
jurisdiction over a case, there must exist a tenancy relationship
between the parties. Further, as there were necessary parties
impleaded that weren’t in the initial deal between SEARBEMCO
8. Stanfilco v. Dole GR 154048 and Dole, the arbitration clause would be invalid. SEARBEMCO
now raises these issues to the SC.
Facts:
On January 29, 1998, SEARBEMCO, as seller, and respondent Issues not related to subject: W/N DARB had jurisdiction
DOLE Philippines, as buyer, entered into a Banana Production and w/n there was a valid cause of action.
and Purchase Agreement4 (BPPA). The BPPA provided that
SEARBEMCO shall sell exclusively to DOLE, and the latter shall Held:
buy from the former, all Cavendish bananas of required The SC held that the parties in the present case have no
specifications to be planted on the land owned by SEARBEMCO. tenurial, leasehold, or any other agrarian relationship that could
bring their controversy within the ambit of agrarian reform laws
Part of the agreement states that SEARBEMCO shall exclusively and within the jurisdiction of the DARAB. Tenancy relations
sell to the BUYER all bananas produced from the subject cannot be presumed. The elements of tenancy must first be
plantation, except those rejected by the BUYER for failure to proved by substantial evidence which can be shown through
meet the specifications and conditions. In the case of any such records, documents, and written agreements between the
rejected bananas, the SELLER shall have the right to sell such parties. The Court declared that when the question involves the
rejected bananas to third parties, for domestic non-export rights and obligations of persons engaged in the management,
consumption. cultivation, and use of an agricultural land covered by CARP, the
case falls squarely within the jurisdictional ambit of the DAR.
Their contract also had an arbitration clause, stating that all
disputes arising in connection with their agreement shall be The action of [DOLE] involves and calls for the application of the
finally settled under the Rules of Conciliation and Arbitration of New Civil Code, in tandem with the terms and conditions of the
the International Chamber of Commerce by three (3) Arbitrators [BPPA] of [SEARBEMCO] and [DOLE].
appointed in accordance with said Rules.
Hence, the RTC’s jurisdiction was proper.
On December 11, 2000, DOLE filed a complaint with RTC against
SEARBEMCO, the spouses Elly and Myrna Abujos (spouses The SC also stated that there was a valid cause of action, as
Abujos), and Oribanex Services, Inc. (Oribanex) for specific hypothetically admitting the allegations in DOLE’s complaint that
performance and damages, with a prayer for the issuance of a SEARBEMCO sold the rejected bananas to Oribanex, a
writ of preliminary injunction and of a temporary restraining competitor of DOLE and also an exporter of bananas, through
order. DOLE alleged that SEARBEMCO sold and delivered to the spouses Abujos, a valid judgment may be rendered by the
RTC holding SEARBEMCO liable for breach of contract.

Page 13 of 14
Arbitration 2011
Main issue for arbit: W/N the parties should resort to
arbitration first

The SC agrees with the CA ruling that the BPPA arbitration


clause does not apply to the present case since third parties are
involved. Any judgment or ruling to be rendered by the panel of
arbitrators will be useless if third parties are included in the
case, since the arbitral ruling will not bind them; they are not
parties to the arbitration agreement. In the present case, DOLE
included as parties the spouses Abujos and Oribanex since they
are necessary parties,i.e., they were directly involved in the
BPPA violation DOLE alleged, and their participation are
indispensable for a complete resolution of the dispute. To
require the spouses Abujos and Oribanex to submit themselves
to arbitration and to abide by whatever judgment or ruling the
panel of arbitrators shall make is legally untenable; no law and
no agreement made with their participation can compel them to
submit to arbitration.

The object of arbitration is to allow the expeditious


determination of a dispute. Clearly, the issue could not be
speedily and efficiently resolved in its entirety if there was
simultaneous arbitration proceedings and trial, or suspension of
trial pending arbitration. Accordingly, the interest of justice
would only be served if the trial court hears and adjudicates the
case in a single and complete proceeding.

Super short summary: SEARBEMCO is trying to dismiss Dole’s


action against them for supposed breach of contract as they
have not initiated arbitration proceedings as stated in their
contract. The SC held that a direct trial was proper since third
parties were involved.

Page 14 of 14

You might also like