LINEA DE CONDUCCION
PROYECTO : "AGUA POTABLE EL NOGAL"
PROP. MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA
01.04.00 ACCESORIOS
01.04.01 ACCESORIOS COSTO GLOBAL
CODO PVC SAP 1 1/2" 45º 6.00 und.
CODO PVC SAP 1 1/2" 90º 6.00 und.
CANASTILLA DE SUCCIÓN BRONCE 1 1/2" 1.00 und.
MUROS
0.15
0.15
0.55 interior ACERO VERTICAL
3/8" 0.20 2.65 1.00 83.00 4.32 358.56 0.58 207.96
exterior
1.97 L= 4.32
0.15 Exterior 3/8" 0.20 2.60 1.00 6.00 16.34 98.04 0.58 56.86
0.80
LOSA DE TECHO
variable 3/8" 3.60 1.00 2 5.74 11.48 0.58 6.66
0.15 4.36 m a menos 0.15 3.50 1.00 4 5.64 22.56 0.58 13.08
3.50 1.00 4 5.64 22.56 0.58 13.08
3.40 1.00 4 5.54 22.16 0.58 12.85
0.12 0.8 0.8 0.12 3.25 1.00 4 5.39 21.56 0.58 12.50
3.00 1.00 4 5.14 20.56 0.58 11.92
L= 2.14 2.70 1.00 4 4.84 19.36 0.58 11.23
2.30 1.00 4 4.44 17.76 0.58 10.30
1.75 1.00 4 3.89 15.56 0.58 9.02
0.85 1.00 4 2.99 11.96 0.58 6.94
CASETA DEVALVULAS
3/8" 0.20 3.34 1.00 5.00 3.34 16.70 0.58 9.69
1.20 1.20 L= 1.05 3/8" 0.20 1.05 1.00 16.00 1.05 16.80 0.58 9.74
0.94 0.95
L= 3.34 3/8" 0.20 1.30 1.00 5.00 1.30 6.50 0.58 3.77
0.10
3/8" 0.20 1.15 1.00 6.00 1.15 6.90 0.58 4.00
977.96
01 TRABAJOS PRELIMINARES
01.01 LIMPIEZA DEL TERRENO 13.82 m2
Reservorio 2.00 12.57
Caja de Válvulas 1.25 1.00 1.25
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION MANUAL 20.10 m3
Reservorio 2.00 1.50 18.85
07 HIPOCLORADOR
07.01 Suministro y colocación de Hipoclorador 1.00 und.
09 VALVULAS Y ACCESORIOS
10 CERCO PERIMETRICO
10.01 DADO DE CONCRT. SIMPLE 0.40*0.40*0.60M+COLU MADERA 4"X 8' , C/3M 7.00 8.00 30.00 30.00 ml.
03.00 TUBERIAS
03.01 TUBERIA Ø=1 1/2" PVC SAP CL-7,5 360 M
03.02 TUBERIA Ø=1" PVC SAP CL-10 348 M
03.03 TUBERIA Ø=3/4" PVC SAP CL-10 280 M
03.04 PRUEBA HIDRAULICA Y DESINFECCION EN REDES DE AGUA 988 M
04.00 ACCESORIOS
04.01 ACCESORIOS COSTO GLOBAL
TEE PVC SAP 1 1/2" 1.00 und.
TEE PVC SAP 1" 2.00 und.
CODO PVC SAP 1" X 45º 2.00 und.
CODO PVC SAP 1" X 90º 2.00 und.
REDUCCION PVC SAP 1 1/2" X 1" 2.00 und.
REDUCCION PVC SAP 1" X 3/4" 3.00 und.
988 OK
HOJA DE METRADOS
PROYECTO : AGUA POTABLE EL NOGAL
01 TRABAJOS PRELIMINARES
Trazo y replanteo 1 1.30 1.30 1.69 1.69 8.45 m2
02 MOVIMIENTO DE TIERRAS
Excavación manual 2 0.50 0.50 1.00 0.50 0.50 2.50 m3
04 TUBERIA,VALV. Y ACCESORIOS
Tubería Fo Go 1 1/2" 6.00 30.00 m
Unión Fo Go 1 1/2" 2.00 10.00 Un.
Adaptador Pvc Sap 1 1/2" 2.00 10.00 Un.
HOJA DE METRADOS
CAMARA ROMPE PRESION TIPO -6
PROYECTO : AGUA POTABLE EL NOGAL
PROP. : MUNICIPALIDAD PROVINMCIAL DE UTCUBAMBA
MUROS: LONGITUDINALES
0.20
MUROS: TRANSVERSALES
0.84
0.2 3/8" 0.25 1.00 6.00 3.56 21.36 0.58 12.39
0.84 0.84
0.84
MUROS: LONGITUDINALES
0.2 1.1 0.2 3/8" 0.20 1.00 6.00 1.50 9.00 0.58 5.22
MUROS: TRANSVERSALES
0.2 0.7 0.2 3/8" 0.20 3.00 6.00 1.10 19.80 0.58 11.48
LOSA DE TECHO
0.1 0.60 0.1 3/8" 0.20 1.00 4.00 0.80 3.20 0.58 1.86
0.1 0.40 0.1 3/8" 0.20 1.00 5.00 0.60 3.00 0.58 1.74
01 TRABAJOS PRELIMINARES
Limpieza de terreno 1 0.80 0.80 0.64 0.64 1.28 m2
Trazo y replanteo 1 0.80 0.80 0.64 0.64 1.28 m2
02 MOVIMIENTO DE TIERRAS
Excavación manual 1 0.80 0.80 0.80 0.51 0.51 1.02 m3
04 VALV. Y ACCESORIOS
Válv. Comp. Bronce Ø 1" 1.00 2.00 Un.
Tapa de Inspección metálica 1.00 2.00 Un.
HOJA DE METRADOS
PROYECTO : AGUA POTABLE EL NOGAL
01 TRABAJOS PRELIMINARES
Limpieza de terreno 1 1.30 1.30 1.69 1.69 1.69 m2
Trazo y replanteo 1 1.30 1.30 1.69 1.69 1.69 m2
02 MOVIMIENTO DE TIERRAS
Excavación manual 1 1.30 1.30 1.25 2.11 2.11 2.11 m3
04 VALV. Y ACCESORIOS
01 TRABAJOS PRELIMINARES
Limpieza de terreno 1 1.60 1.60 2.56 2.56 2.56 m2
Trazo y replanteo 1 1.60 1.60 2.56 2.56 2.56 m2
02 MOVIMIENTO DE TIERRAS
Excavación manual 1 1.60 1.60 1.30 3.33 3.33 3.33 m3
04 VALV. Y ACCESORIOS