Professional Documents
Culture Documents
Abstract—The paper considers a solution for integration of large fully proved while LCC HVdc technology has been operated
offshore doubly fed induction generator-based wind farms with a with high reliability for more than 30 years. However, the LCC
common collection bus controlled by a STATCOM into the main requires a commutation voltage supplied by a synchronous com-
onshore grid using line-commutated high-voltage dc connection. A
design procedure is described and the controlled system is validated pensator [3]. Alternatively, a STATCOM can be used [4], [6] that
using PSCAD/EMTDC simulations confirming high performance can typically provide much faster control than a synchronous
of the proposed control strategy in both normal operation condi- compensator and with lower losses.
tions and faults. Engineering issues related to STATCOM capacitor For reasons of energy capture and reduced drive train stresses,
sizing and reduction of STATCOM rating are considered and their variable speed turbines are becoming the norm for new wind
effectiveness is confirmed.
farm installations. The direct-drive synchronous generator (op-
Index Terms—Controller design, doubly fed induction generator tionally with permanent magnet excitation) and doubly fed in-
(DFIG), frequency, high-voltage dc (HVdc) transmission, stability, duction generator (DFIG) have become the two generator alter-
STATCOM, voltage, wind energy.
natives. The former has the disadvantages of cost and a power
converter rated for the full power. Although requiring a gearbox,
I. INTRODUCTION the DFIG requires a converter of only 25% of the generator rating
T IS PREDICTED [1] that by 2020, up to 12% of the world’s for an operating speed range of 0.75 to 1.25 per unit (p.u.) and is
I electricity will be supplied from wind power. The majority
of wind farms are planned to be offshore where wind conditions
considered a lower cost, proven technology solution. The ratings
of commercial DFIG-based wind turbines now reach 5 MW [7].
are generally better while planning restrictions are reduced. For The converter-controlled DFIG, STATCOM, and LCC HVdc
example, several wind farms with registered capacities around have all been well studied as separate components. In [4]
1000 MW are planned off the north-west coast of Great Britain and [6], the overall power system concept and possible control
with distances over 100 km to the nearest grid connection point. paradigms have been described, but these studies have not
To transmit such bulk power over such distances creates chal- included system analysis or a formal procedure of control
lenges for both system operators and wind farm developers. system design. A detailed mathematical study of the system
Currently, two alternative connection methods are available for that resulted in the plant model appropriate for a formal control
connection of remote wind farms to the grid: high-voltage dc design had been represented by the authors in [8]. The present
(HVdc) and high-voltage ac (HVac). It is proven [2]–[4] that the paper is a logical continuation of our previous study [8]: the
HVdc transmission offers many technical, economic, and envi- proposed control algorithm is applied to the more realistic
ronmental advantages for large wind farm with long distances power system configuration, the model for simulation studies
to the main grid. includes lumped DFIG model under converter control [9] to
The HVdc transmission can be based on two alternative tech- represent 1000 MW wind farm, the mechanical dynamics is
nologies: voltage source converter (VSC) using IGBTs and taken into account, the HVdc is modelled according to the First
line-commutated converter (LCC) using thyristors. The VSC Benchmark Model for HDdc studies [10], and includes detailed
technology has the advantage of forced commutation so that switching models for both rectifier and inverter together with
an external voltage source is not required, but it has higher their harmonic filters, and the impedances of all offshore cables
overall losses than thyristor-based LCC HVdc. Moreover, the and transformers are considered as well. The performance of
present power rating for a single VSC is limited at the 330 MW the power system during normal operation and faults is studied,
level [5], and the reliability of VSCs in service has yet to be and engineering issue of STATCOM rating is discussed.
Manuscript received January 21, 2007; revised March 30, 2007. Paper no.
TEC-00012-2007. II. POWER SYSTEM STUDIED
S. Bozhko, G. Asher, R. Li, and J. Clare are with the Department of Electrical
and Electronic Engineering, Nottingham University, Nottingham NG7 2RD, The power system studied is shown in Fig. 1. It comprises
U.K. (e-mail: serhiy.bozhko@inottingham.ac.uk; greg.asher@nottingham. an DFIG-based offshore wind farm, an island platform for
ac.uk; eexrl@gwmail.nottingham.ac.uk; jon.clare@nottingham.ac.uk). HVdc rectifier station and auxiliary equipment, ac filters, and a
L. Yao is with the AREVA T&D Technology Centre, Stafford ST17 4LX,
U.K. (e-mail: liangzhong.yao@areva-td.com). STATCOM unit. Whereas, capacitive ac filters can compensate
Digital Object Identifier 10.1109/TEC.2007.914155 for the HVdc converter reactive absorption in lumped amounts,
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.
120 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 23, NO. 1, MARCH 2008
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.
BOZHKO et al.: LARGE OFFSHORE DFIG-BASED WIND FARM WITH LINE-COMMUTATED HVDC CONNECTION TO THE MAIN GRID 121
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.
122 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 23, NO. 1, MARCH 2008
Fig. 5. System performance. (a) Under normal operation (left). (b) During a solid three-phase fault in the onshore grid (right).
A. Effect of Faults on STATCOM DC-Link Capacitor Sizing Consider three right-hand side terms in details. The wind farm
receives fault detection signal with a communication delay τd ,
The STATCOM active power flow is related to the problem
of overvoltage across its dc-link capacitor. Analysis of power and then, the output power reduces according to the dynamics
flow during fault allows one to derive criteria for the capacitor of DFIG current (or power) loop that can be approximated as
first-order lag τG . Therefore, the first term in (9) can be derived
sizing. The energy e, passed into this capacitor is
as follows:
t
t
e(t) = e0 + (PG − PC − Pl ) dt (1) −
t −τ d
t0 PG dt =PG 0 τd + PG 0 τG 1 − e τ G . (4)
0
where e0 is its prefault value, and PG , PC , and P1 are windfarm
power, HVdc power, and losses correspondingly. This energy Losses assumed are constant (P10 = const), therefore
defines the voltage across the STACOM capacitor CS : t
Pl dt = Pl0 t. (5)
CS ES2 dc (t) 0
e(t) = . (2)
2 The HVdc power starts to drop without communication delay,
Introducing overvoltage factor kv = ES dc m ax /ES dc0 , the fol- and the transient is assumed according the first-order lag with
lowing expression can be derived using (1) and (2): time constant τC :
t t t t
CS ES2 dc0 2 − t
kV − 1 = PG dt− PC dt− Pl dt. (3) PC dt = PC 0 τC 1 − e τ C . (6)
2 t0 t0 t0 0
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.
BOZHKO et al.: LARGE OFFSHORE DFIG-BASED WIND FARM WITH LINE-COMMUTATED HVDC CONNECTION TO THE MAIN GRID 123
Using this expression, one can derive plots for particular stud- power support during normal operation) means that STATCOM
ied cases. Thus, for the power system studied with kV = 1.3 had to compensate for full reactive power generated by these ac
(i.e., 30% acceptable overvoltage), τG = 3 ms, and τC = 2 ms, filters when IC drops to zero. It works against the reduction of
and for maximum fault duration equal to 0.16 s (8 cycles at the STATCOM reactive power demand. This can be relieved if
50 Hz), the curve (7) for CS m in selection has been calculated us- dc-link current demand at faults is not zeroed, but set to some
ing MATLAB and is shown in the Fig. 6. The curve is produced value I0fin in order for rectifier to absorb the reactive power
as an upper envelop for a family of different curves, correspond- generated by ac filters. In our study, this value has been set at a
ing to different values of fault duration up to 0.16 s (shown in value 0.25 p.u.
Fig. 6 by thin lines, in number of cycles n, n = 1, . . . , 8). In the mean time, fast reduction of HVdc-link current means
Therefore, the minimal value of the STATCOM dc-link capaci- fast decay of active power transferred to the HVdc. Since the
tor should be chosen above the given curve for particular value windfarm output power is controlled via relatively slow power
of communication delay. In this case, it is guaranteed that the control loops, it means that STATCOM has to absorb the fast
overvoltage at the end of the fault with specified duration would developing excess of active power in the offshore grid. There-
not exceed the value kV ES dc0 . fore, decrease of STATCOM reactive power demand as earlier is
The derived criterion (7) put additional constrains for ca- compromising on its active power demand and additional over-
pacitor selection by STATCOM manufacturers and should be voltage to the STATCOM dc-link capacitor. It leads to the need
considered together with conventional sizing criteria, such as for extra costs for either the overvoltage-withstanding capacitor
maximum voltage ripple during single- and three-phase local or larger capacitor. To some extent, this can be relieved if after
grid faults. In any case, additional criteria should always be fault detection, the wind farm output is controlled not via power
considered in the context of the designed purpose of the STAT- control loops but via fast DFIG current control loops, putting
COM, which is to provide voltage and reactive power regulation zero demand for generator q-axis current. But due to the dis-
for the adequate operation of the HVdc-link in steady state and tant location of wind turbines from the technological platform
during faults in the onshore grid. (see Fig. 1), there is a communication delay τd before DFIGs
receive a fault detection signal. During this delay, the wind farm
still delivers full output power to the offshore grid. Therefore,
B. Reduction of the STATCOM Rating for Handling Fault the STATCOM rating in order to handle the fault scenario in-
Conditions evitably depends on the value of τd . Consider this effect in
For the case studied, the peak reactive power demand nearly details.
reaches 1.3 p.u. (at HVdc base). This is due to the fact that
the HVdc rectifier ac current become mainly reactive when the
C. STATCOM Rating and Communication Delay
rectifier’s firing angle moves toward 90◦ in attempt to reduce dc-
link current. Therefore, the first natural step to reduce reactive Under normal operation, before the fault occurs, both ac-
power demand during faults is to reduce HVdc dc-link current tive and reactive current components of HVdc rectifier in the
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.
124 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 23, NO. 1, MARCH 2008
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.
BOZHKO et al.: LARGE OFFSHORE DFIG-BASED WIND FARM WITH LINE-COMMUTATED HVDC CONNECTION TO THE MAIN GRID 125
Fig. 8. Enhanced system performance during a solid three-phase fault in the onshore grid and fault recovery.
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.
126 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 23, NO. 1, MARCH 2008
VI. CONCLUSION [7] P. Cartwright and L. Xu, “The integration of large scale wind power
generation into transmission network using power electronics,” presented
This paper has considered a large offshore wind farm with at the CIGRE Gen. Session, Paris, France, 2004.
an LCC HVdc connection to the main onshore network. The [8] S. V. Bozhko, R. Blasco-Gimenez, R. Li, J. C. Clare, and G. M. Asher,
“Control of offshore DFIG-based windfarm grid with line-commutated
proposed control system provides high-performance control of HVDC connection,” IEEE Trans Energy Convers., vol. 22, no. 1, pp. 71–
the offshore ac grid and guarantees the transfer of generated 78, Mar. 2007.
wind power into the main onshore grid. Engineering issues of [9] R. Pena, J. C. Clare, and G. M. Asher, “Doubly fed induction generator
using back-to-back PWM converters and its application to variable speed
STATCOM sizing are considered and confirmed using simu- wind-energy generation,” Inst. Electr. Eng. Proc.-Electr. Power Appl.,
lations in PSCAD/EMTDC, and recommendations for control vol. 143, no. 3, pp. 231–241, May 1996.
system enhancement are given. The control system studied in [10] M. Szechtman, T. Wess, and C. V. Thio, “First benchmark model for
HVDC control studies,” Electra, vol. 135, pp. 55–73, 1991 (CIGRE
this paper can be a satisfactory solution for integrating large Committee 14).
offshore DFIG-based wind farms into existing ac networks. [11] S. Muller, M. Deicke, and R. W. De Doncker, “Doubly fed induction
generator systems for wind turbine,” IEEE Ind. Appl. Mag., vol. 8, no. 3,
pp. 26–33, May/Jun. 2002.
APPENDIX I [12] PSCAD v.4.1: The professional tool for power system simulation, Mani-
tobe HVDC Research Centre, Winnipeg, MB, Canada, 2004.
POWER SYSTEM PARAMETERS
STATCOM: CS = 20 000 µF; ESo = 35 kV.
STATCOM transformer: 200 MVA; 10/132 kV; 0,12 p.u.
Collector bus transformer: 1100 MVA; 33/132 kV; 0,15 p.u.
HVdc rectifier transformers:
TC 1 : 604 MVA; 33/213 kV; Y/∆; x = 0,18 p.u. Serhiy Bozhko (M’96) received the M.Sc. degree
TC 2 : 604 MVA; 33/213 kV; Y/Y; x = 0,18 p.u. in electrical engineering and the Ph.D. degree in
electrotechnology from the National Technical Uni-
HVdc Link: R0 = 5 Ω; L0 = 1.836 H; I0 = 2 kA. versity of Ukraine, Kiev, Ukraine, in 1987 and 1994,
AC Filters: 250 MVAr at third harmonic; 250 MVAr at 11th/13th respectively.
harmonics and 125 MVAr capacitance bank. Since 1995, he has been a Senior Lecturer in the
Department of Electrical Drives and Automation, Na-
tional Technical University of Ukraine, where since
APPENDIX II 1987, he was a Research Assistant and a Lecturer.
Since December 2000, he has been with the Univer-
CONTROL DESIGN PARAMETERS sity of Nottingham, Nottingham, U.K., where he is
currently a Research Fellow at the School of Electrical and Electronic Engi-
neering. His current research interests include stability of power systems with
DESIGNED CLOSED LOOP NATURAL FREQUENCIES AND PI CONTROLLER distributed generation, intelligent control systems, and variable speed drives.
PARAMETERS
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.
BOZHKO et al.: LARGE OFFSHORE DFIG-BASED WIND FARM WITH LINE-COMMUTATED HVDC CONNECTION TO THE MAIN GRID 127
Jon Clare (M’90–SM’04) was born in Bristol, U.K. Liangzhong Yao received the M.Sc. and Ph.D. de-
He received the B.Sc. and Ph.D. degrees in electrical grees from Tsinghua University, Beijing, China, in
engineering from the University of Bristol, Bristol, 1989 and 1993, respectively, all in electrical power
U.K., in 1979 and 1991, respectively. engineering.
From 1984 to 1990, he was a Research Assistant From 1995 to 1999, he was a Research Associate
and a Lecturer at the University of Bristol, where at Manchester Centre for Electricity Energy, Univer-
he was engaged in teaching and research in power sity of Manchester (formerly UMIST), Manchester,
electronic systems. Since 1990, he has been with U.K., and from 1999 to 2004, he was a Senior Power
the Power Electronics, Machines and Control Group, System Analyst in the Network Consulting Group,
University of Nottingham, Nottingham, U.K., where ABB Ltd., U.K. He is currently a Technology Con-
he is currently a Professor of power electronics and sultant and a Programme Manager at the AREVA
the Head of the Research Group. His current research interests include power T&D Technology Centre, Stafford, U.K., where he is engaged in wind farm grid
electronic converters and modulation strategies, aerospace electrical systems, connections, network engineering design, and consulting for transmission and
variable speed drive systems, and electromagnetic compatibility. distribution systems.
Prof. Clare is a member of the Institution of Electrical Engineers. Dr. Yao is a Chartered Engineer and a member of the Institute of Electrical
Engineers (IEE).
Authorized licensed use limited to: University of Reading. Downloaded on December 4, 2009 at 06:17 from IEEE Xplore. Restrictions apply.