Professional Documents
Culture Documents
CLIENTS
NICON TOWN MANAGEMENT CO. PLC
Lekki Epe Express Lagos
BY
NOBLE BC LTD.
No 3 Asenuga Str.
Off Opebi Link road
Ikeja Lagos
REF: NBC-CNG367-R004REV0 08023356112, 07093189196
Route Assessment and design Osapa channel
Via Nicon town – Lagos - Nigeria
EXECUTIVE
SUMMANRY
EXECUTIVE SUMMARY This report considers the hydraulic and hydrological parameters for
the Osapa channel catchment and these were used to assess and
The objective of this report is to provide the details of the
design the downstream reach of the channel which is to discharge
assessment and design of the Osapa channel downstream reach. A
into the lagoon. The challenge is to study the flow behavior of the
brief was given by Nicon town management Company concerning
channel alignment, if straight and also if diverted via a Bypass
the Osapa channel and its discharge reach whose downstream
channel which will not pass throught the Nicon town premises.
alignment is designed by the Lagos state ministry of environment
(drainage department) to pass through the premises of Nicon town
Two downstream reach were considered for the Osapa channel.
Lekki.
• Straight reach through the premises of Nicon Town.
• Bypass reach circumventing the Nicon town premises on the
The Osapa channel is a about 2.3km in length from midstream at
east and northern boundary wall.
the Lekki Epe express way to Its discharge point inside the Lagos
Two hydraulic assessment procedures were employed
Lagoon behind Nicon town Lekki. As at the point of this report, the
• Gradually varied or unsteady flow simulation for 12hrs.
naturally formed earth channel is beign lined to chainage 0+850
• Quasi-unsteady flow for 3yrs for sediments transport
from the Express way. The Osapa channel is with top width of 12m
simulation
upstream before the Lekki-Epe express way and 15m top width just
after the bridge(in its midstream) on Lekki-Epe expressway to its
present point of construction. Average depth of the channel is 1.5m.
Our assessment results shows: section required for storm water discharge in the sediment
• unsteady flow simulation for 12hrs shows both bypass and prone area.
straight options having water profile elevation for upstream • In three years, with a sediment basin in place, about 0.5m
channels on or below 4m elevation which is fit for purpose sediment deposition height is achieved above ambient invert
• sediment transport simulations shows; about 0.35m elevation of the channel.
sediment deposition (in 3yrs) in the downstream reach if the • Water elevation profile is grossly decreased below flood
channel is made straight while sediment deposition reached limits.
about 1.2m depth (in 3yrs) of the total 1.5m depth of the • Section for bypass channel or straight channel 12m bottom
channel if bypass channel is considered. width trapezoidal channel wit1.5m average depth and 1:2
• Upstream regions becomes prone to flooding due to gross walls
increase in water profile elevation if downstream reach is • Discharge channel into the lagoon is 15m bottom width
made into a bypass channel. trapezoidal channel wit1.5m average depth and 1:2 walls
• The channel total length from the its junction with Igbokushu
Our design results shows channel to the Lekki lagoon is 1.54km for Bypass channel
• Introduction of a sediment basin just before the high • The channel total length from the its junction with Igbokushu
sediment deposition zone in the bypass channel will help channel to the Lekki lagoon is 1.087km for Straight channel
reduce drastically, the rate of depletion of available hydraulic
data was however updated by Noble B.C. Ltd to make it • The South by Atlantic Ocean,
fit for purpose.
2.4. RAINFALL
Figure 2: sample rainfall precipitation data for year 2007 Obtained from NIMET
3. OSAPA CHANNEL DOWN STREAM REACH ASSESSMENT Average land slopes along the terrain are used for the
AND DESIGN estimation process of runoff rates.
The design criteria are developed on the basis of Land 3.2.1. Rational Method
Eq. 3.1
Time of concentration, tc
Rainfall Intensity
Time of Concentration
There are a number of methods that can be used
to estimate time of concentration (tc), some of
Sheet flow is the shallow mass of runoff on a I = rainfall intensity, mm/hr (in/hr)
planar surface with a uniform depth across the S = surface slope, m/m (ft/ft)
distances, rarely more than about 130 m, and Since I depend on tc and tc is not initially known,
possibly less than 25 m. Sheet flow is estimated the computation of tc is an iterative process.
with a version of the kinematic wave equation, a An initial estimate of tc is assumed and used to
derivative of Manning's equation, as follows: obtain I from the IDF curve. The tc is then
computed from equation 4.2 and used to check
the initial value of
o tc. If they are not the same, the
process is repeated until two successive tc Shallow Concentrated Flow Velocity. After short
estimates are the same. distances of at most 130 m (400 ft), sheet flow
tends to concentrate in rills and then gullies of
increasing proportions. Such flow is usually
referred to as shallow concentrated flow. The
velocity of such flow can be estimated using a
relationship between
betwee velocity and slope as follows:
Eq. 3.3
where:
Ku = 1.0 (3.28 in English units)
V = velocity, m/s (ft/s)
Eqn3.4
where:
n = roughness coefficient (see table 4.4)
V = velocity, m/s (ft/s)
where:
Eq. 3.5 hL = head or energy loss between section 1 and
2, m (ft)
where:
Et = total energy, m (ft)
o Subcritical,
Subcritical supercritical or critical
4. DRAINAGE DESIGN
SN Element Area Weighted Average Equivalent Time Accumulated Total Peak Rainfall
ID Runoff Slope Width of Precipitation Runoff Runoff Intensity
Coefficient Concentration
4.2.3. Igbokushu channel with relevant nodes J-1, J- 4.2.4. ‘Primary A’ channel with relevant nodes J-23, J-
21, J-22. 24, J-25.
Osapa Upstream
Before the Lekki Epe express way
Trapezoidal channel (Bottom Width (BW) 6m Side Slope
1:2
Midstream
Rectangular channel (Bottom Width (BW) 3m, depth
1.5m
Downstream
Rectangular channel (Bottom Width (BW) 5m, depth
1.5m
Downstream
Rectangular channel (Bottom Width (BW) 8m, depth
1.5m
Figure 26: Quasi- Unsteady flow graph for Bypass channel Figure 28:Quasi-Unsteady flow graph for Igbokushu channel upstream
Figure 27: Quasi-Unsteady flow graph for Osapa channel upstream Figure 29: Quasi-Unsteady flow graph for Primary A channel upstream
4.4.3. SEDIMENT TRANSPORT ANALYSIS RESULTS WATER SURFACE, INVERT CHANGE PROFILES
Here also, two scenarios where considered at this point: This profile features the change in invert elevation of the
• Osapa with Bypass channel proposed channel reach over three years(2007-2010)
• Osapa with Straight channel of sediment deposit after the three seasons of rainfall
event.
channel when its alignment follows the Bypass route. OSAPA WITH STRAIGHT CHANNEL
Figure32 also shows these points in the site layout. Maximum water surface profile is seen below 4.5m which
is mean ground elevation. Sediments deposit is about
300mm in the third year of simulation.
Figure 33: Sediment profile for Osapa channel with straight alignment
Figure 32: layout showing areas of high sediment deposits (with Bypass channel)
BYPASS ROUTE ASSESSMENT is high. Depth of sediment basin is 0.6m, 10m width and
The hydraulic simulation shows that the bypass route will about 40m long within the bed of the channel.
cause accumulation of debris and sediments at the bends
shown in figure 32. This causes water surface elevation
to back up upstream and causing flooding. A straight
alignment shows debris accumulation to about 0.3m
height which is fair enough. However, the situation in the
bypass channel can be remedied. An option is the
introduction of sediment basins at major sediment deposit
areas. The next section shows the result of the
assessment of the bypass option but this time with a
sediment basin.
Figure 34: Sediment deposit for Osapa Bypass option with Sediment basin
Figure 37: cross section of high deposit area for bypass channel without sediment basin Figure 36: cross section at midpoint of straight reach passing through Nicon town
Figure 35: Cross section of High deposit area but with sediment basin
5. CONCLUSION AND RECOMMENDATION the channel and sediment deposition is also imminent but
Two major options were considered. The first is the mild and not concentrated. However, routine maintenance
option of a bypass channel to align with western and is also required to ensure good ambience and hygiene