You are on page 1of 5

2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004)April 2004 Hong Kong

Intelligent Method for Protection Coordination


C.W. So, Member, IEEE, K.K. Li, Senior Member, IEEE

Abstract: This paper presents the application of manage the relay settings. In distribution network, the
Artificial Intelligence in protection coordination. It can major backup protections are Inverse Definite Minimum
substantially improve the coordination of protection Time Lag (LDMTL) overcurrent and earth fault relays.
relay operations. The relay settings and coordination Their operations depend on the fault current magnitude.
requirements are formulated into a set of constraint Thus, the relay operation is affected by the change of fault
equations and an objective function is developed to current magnitude [7]. In fact, any unclear fault will be
manage the relay settings by the Time Coordination cleared by the backup relay operations. Any circuit
Method (TCM). Modified Evolutionary Programming breaker operation will result in changes in fault current
(MEP) is employed to search for the optimum relay distribution and magnitude experienced by backup relays.
settings with maximum satisfaction of coordination In order to boost the performance, the TCM must be able
constraints. The results show that the intelligent to handle a reasonable number of fault current changes.
method for protection coordination can optimize the This paper shows how the TCM can significantly improve
protection relay settings, reduce relay mis-coordinated the supply reliability and reduce relay mal-operations.
operations, and increase supply reliability. The
efficiency of TCM taking the fault current changes
into consideration is also discussed in this paper. 11. PRINCIPLES OF TIMECOORDINATION METHOD
(TCM)
Index Terms -
Protection Relay Coordination, Time
Coordination Method, Power System Reliability. Initialize relay settings
I. INTRODUCTION

A modem protection system consists of various types Generate new relay settings
of protective relays, which functions to detect and isolate I
system abnormalities swiftly. For various voltage level,
the various combinations of main and backup relays are
installed to provide complete protection to various power
apparatus. The main protection relay works in unit
protection principle and removes in-zone fault instantly.
The backup protection relay is designed to backup the
I Objective value calculation I
main protection relay in case it fails. The overcurrent relay
No
is a major type of backup protection relay. As it is non- E
unit protection, it is discriminated by their operating time,
which forms a sequence of backup relay operations for the
unclear system fault. Any incorrect operation of the
backup relays will result in a large area of supply Fig. 1
interruption [ 11 as well as decreasing the supply reliability. Time Coordination Method
The backup protection relay coordination is thus necessary.
The process flow chart of the TCM is shown in Fig 1.
It ensures that the fault clearance actions are in correct
sequence and minimizes the supply interruption. As the It formulates the power network and protection system
into an objective function and a set of constraint equations.
power system is changing from time to time, the
The objective function in the TCM is shown in equation
coordination work should be carried out upon any
significant change in power system configurations [2]. (1).
Based on the communication ability equipped in modem
digital relay, the coordinated relay settings can be
downloaded through the communication network. The
Time Coordination Method (TCM), which formulates the where
coordination of relay settings into a set of constraint Ri is each relay operation time and regulated by a
equations and an objective function, is proposed in [3] to scale factor a.
The authors would like to thank The Hong Kong Polytechnic
C y is the operation time difference for each pair of
University for supporting the research and publishing this work. relays and regulated by a scale factor p.
C.W. So (e-mail: paulsot~~comnuter.or~) is currently working in CV, is the number of coordination constraint
a PhD project with the Hong Kong Polytechnic University. Dr. K.K. Li
(e-mail: cckkli@polwi.cdu,hk) is with the Dcpartment of Electrical
x
violations and regulated by scale factor and 6.
Engineering, Hong Kong Polytechnic University, Hong Kong. Note: Variable i, j and k are iterated for all possible
system configurations.

0-7803-8237-4/04/$17.0002004IEEE
378
2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong

order to minimize the initialization time. The performance


The initialization is to generate several sets of relay of EA is determined by population size, number of
settings randomly. Each set of relay settings will be generations and mutation rate [SI and will be discussed in
checked against all system constraints and configurations. the result section.
The effectiveness of the relay settings is calculated by (1).
Any violation of system constraints will be penalized and IV. FORMULATION
this will be reflected in the increased objective value.
+us BO
The optimization is used the Modified Evolutionary
Programming (MEP) [ 3 ] to search for the optimum relay Bus B1
settings. The relay settings improvement process to
produce the next generation is carried out by a sub-process
of MEP called ‘mutation’. It is based on Gaussian normal
distribution noise as shown in Eqn (2).

x, = x, + or N I(0,l) (2)

0, =Jm
where
xi is the i element of relay settings.
pi is the scale factor for EA mutation.
yi is the offset for EA mutation.
@(x’) is the objective value of the relay settings.
N , ( 0 , ~ ) is the Gaussian normal distribution noise. Line L5
The scale factor pi and the offset yi are to control the Bus B7
performance of EA and typically set to 1 and 0
respectively.
Circulating current protection relay
These newly generated relay settings should be Overcurrent protection relay
passed to constraints checking and objective value Fig. 2
calculation for the next EA generation. Sample distribution system

The process will stop after a fixed number of The sample system as shown in Fig. 2 is considered
generations. The number of generations required to carry in this study. Each circuit is protected by circulating
out the optimum relay setting depends on the pattern and current (CC) protection, Inverse Definite Minimum Time
the number of initial relay settings. Lag (LDMTL) Overcurrent (OC) and Earth Fault (EF)
protection. . The CC protection is a unit protection with a
fixed setting and do not need to be changed adaptively.
The IDMTL OC & EF protection is a non-unit protection.
III. MODIFIED
EVOLUTIONARY
PROGRAMMING It operates on excessive current flowing through the
circuit in which the TCM is applied to coordinate the
The relay setting coordination is modeled according settings.
to its constraint optimization [ 3 ] . As the relay setting is
discrete and constrained by the adjacent relay, it is The TCM is required to calculate the relay setting for
difficult for the conventional gradient search method [5] all possible system configurations. The relay with
to find the solution. The MEP is a stochastic parallel optimized settings should be capable to handle the change
search method for multi-variables. It can increase the of fault current due to the tripping of adjacent circuits [7].
chances to search for the optimum relay settings in a fixed In fact, most of the faults can be cleared by two to three
number of generations with maximum satisfaction of protection relay operations. For instance, for a busbar fault
coordination constraints. Initialization process is used to occurred on Bus B5, if the relay located at Line L25
generate several sets of protection relay settings in random operates first, the relays located in other lines will
basis to set up the initial population pool. A larger initial experience a fault current change. If the relay located in
population pool will broaden the solution search area [ 6 ] . Line L36 operates next, the relays located in Line L14,
Each initialized protection relay setting is passed to the L46, L67, L57 will experience the second change of fault
Protection Performance Evaluation module for currents. Finally the relay located in Line L57 operates
coordination constraints checking [3]. Unfortunately, the and the fault is completely cleared. The relay operation in
pure random generated initial protection relay settings Line L36 is definitely a mal-operation. In this case, the
may not pass the coordination constraints checking. The TCM should at least handle all the relay operations up to
setting pusher technique [7] is thus developed to improve two step changes of fault current. It should also be able to
the success rate of coordination constraint checking in handle other kind of mis-coordinated relay operations

379
2004 E E E International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004)April 2004 Hong Kong

which will caused fault current changes. In the result


section, the efficiency of the TCM with different number
of fault current changes will be examined. The more
number of fault current changes to be handled, the larger
number of system configurations should be considered. Where
The possible system configurations are considered as Afis the failure rate of busbar.
follows: rf is the repair time of busbar.
&(b) is the supply b failure rate due to busbar fault.
For a fault in a particular busbar, the number of Ub(b) is the supply b repair time.
system configurations C to be studied due to the number
of lines N in the system is: The third class of reliability calculation is the
C=2N protection fault and is shown in equations (8) and (9).
The number of system configurations C' if r out of N U , (b) = Pf ',r, (8)
circuits will trip to isolate the fault is shown in equation
(4). (9)

(3)
i=O
Where
In the sample system as shown in Fig 2, although the A, is the failure rate of the cable.
number of configurations is C=2' =256, but some rare r, is the switching time of the cable.
system configurations may be ignored. If the maximum Pfis the probability of protection failure.
allowable circuit outages = 3, the number of system AJb) is the supply b failure rate due to protection
configurations to process C' = C: + C: + C: + C: = 93 . fault.
U,(b) is the supply b restoring time.
The processing time reduction due to the minimized
system configurations is equal to 6- 93 -36,3% . The The resultant reliability of the supply b due to
C 256
protection operation is shown in equations (lo), (1 1) and
effect of the reduced number of system configuration in
constraint checking will be discussed in the result section. (12).
A (b) = As@) + + &,(b) (10)
During the constraint checking, the constraint
violations are checked against whether the operation time
U@)= Us@) + Ub(b>4-Up@)
r(b) = U(b)/A (b) [E]
Where
difference between the upstream and downstream relays is A (b) is the failure rate of supply b.
smaller than the coordination margin [3,4]. The objective U(b) is the repair time of supply b.
value is also calculated during constraint checking. One of r(b) is the mean duration of supply b interruption.
the major objective of the TCM is the minimization of the
number of constraint violations. The supply reliability for every supply busbar may be
evaluated by simulating the busbar fault, stuck breaker
V. RELIABILITY
EVALUATION and protection failure in each busbar. For instance, a
single-phase-to-earth fault occurs at busbar bi, the
The benefits of the TCM may be measured by the protection relay operates according to the fault current
supply reliability indices. The basic principle of the supply distribution and resulting in busbar bj loss of supply
reliability is presented by Billinton and Allan [9,10]. The (bifbj). The supply reliability of busbar bj should be
effectiveness of protection relay operations contributed to updated according to equations (6) and (7).The protection
the supply reliability [I 11 may be computed by the three failure and stuck breaker cases are also simulated by
classic calculations. The first class of reliability applying busbar fault on the circuit connected to the
calculation is the stuck breaker and is shown in equations busbar and update the reliability indices by equations (4),
(4) and (5). (9,(8) and (91). The resultant reliability indices will be
the sum of all individual simulated reliability indices
us ( b ) = 'brb (4) according to equations (lo), (1 1) and (12).
1 ' (b) = ' b (5)
Where VI. SIMULATION RESULT
AND DISCUSSION
A,, is the failure rate of stuck breaker.
rb is the switching time to restore system due to stuck The relay information and system parameters of the
breaker. sample distribution system are shown in Table 1 and 2
&(b) is the supply b failure rate due to stuck breaker. respectively.
Uv(b)is the supply b restoring time.
The second class of reliability calculation is the
busbar fault and is shown in equations (6) and (7).

380
2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong

The contribution of constraint violations in objective


value is proportional to the number of system
configurations. Moreover, from the results, the number of
constraint violations depends on the number of fault
current changes, the comparison of the objective value is
only valid for those cases with the same number of fault
current changes, i.e. case 1 to 3 , 4 to 6, 7 to 9, 10 to 12, 13
to 15 and 16 to 18. For cases 1 to 3, they have been
checked based on no fault current change. The TCM then
only checks the relay operations with single and three
phase busbar faults at E31 to B7, i.e. 12 fault cases are
being studied. In cases 16 to 18, the number of system
configurations based on equation (2) for a fault in either
busbar is c = 2 cp
r=O
= 219 . As there are six
busbars in the system and two types of fault are simulated,
a total of 219 x 6 x 2 = 2628 fault cases are to be studied.
Thus, the number of constraint violations for cases 16 to
18 are considerable larger than cases 1 to 13.
When a busbar fault occurred, two or more tripping
should be carried out by OC relay to isolate the fault
completely. For cases 1 to 6, since the number of fault
current changes is less than 2, they are impractical to
implement. The number of constraint violations and the
processing time per generation of cases 7 to 9 are less than
cases 10 to 18. Case 8 has the smallest number of
constraint violations. Case 14 has better reliability indices
Note: All per-unit (pu) values are based on 100MVA. with 0.6160 f/yr and 1.2016 hr/yr. It implies that case 13
to 15 has less chance in loss of supply due to relay mis-
Table 3: Si1 coordination. As the roll of distribution is to provide a
reliable power network to customers, relay settings of case
14 should be the best for retaining the supply reliability.
The performance of MEP depends on the population
size, the number of generations and the number of fault
current changes. For cases 13 to 15, a better objective
value occurs in case 14 for population size of 50 rather
than case 13 or 15, similar behaviors occur in every three
consecutive cases. It implies that population size of 100
may be over-crowed, in which better protection settings
are not easily to be selected to survive during the selection
process in MEP.
VII. CONCLUSION

The TCM can make relays more intelligent and adapt


to the system configuration. The supply reliability can be
improved by reducing the number of mis-coordinated
relay operations. The setting of the TCM with different
number of fault current changes is examined. The result
shows that better improvement of supply reliability do not
occur in larger number of fault current changes. It implies
that the unrealistic number of fault current changes will
cause the TCM to over-test the system and the TCM force
the protection relays to handle those unrealistic system
configurations.

The TCM can be set of different population size, VIII. REFERENCE


number of generations and number of fault current
changes. The results shown in Table 3 are used to [l] R.P. Graziano, V.J. Kruse, G.L. Rankin,
determine the case for the best TCM performance. "Systems Analysis of Protection System Coordination: A
Strategic Problem for Transmission and Distribution

38 1
2004 IEEE Intemational Conference o n Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong K o n g

Reliability”, IEEE Transactions on Power Delivery, Vol. C11lJ.J. Meeuwsen, W.L Kling, S.P.J. Rombouts
7, NO. 2, pp 720-724, April 1992. “The influence of protective relay schemes on the
[2] William J. Ackerman, “Substation Automation reliability indices of load points in meshed operated mv
and the EMS”, I999 IEEE Transmission and Distribution networks”, I 4rH International Conference and Exhibition
Conference, April 1999, Los Angeles, USA, Vol. 1, pp. on Electricity Distribution, Part 1: Contributions, Congres
274-279. International des RCseaux Electriques de Distribution
[3] C.W. So, K.K. Li, “Time Coordination Method (CIRED), June 1997, IEE Publication No. 438, Vol;. 4, pp.
for Power System Protection by Evolutionary Algorithm”, 14/1-14/5.
IEEE Transactions in Industry Application, Vol. 36, No. 5,
Sqt/Oct 2000, pp. 1235-1240.
[4] C.W. So, K.K. Li, K.T. Lai, K.Y. Fung,
“Application of Genetic Algorithm for Overcurrent Relay IX. BIOGRAPHIES
Coordination”, IEE 6Ih International Conference on
Developments in Power System Protection, Nottingham, C.W. So rcceived the BEng and PhD degree from
UK, March 1997, pp. 66-69. the Hong Kong Polytechnic University in 1996
[5] R. Salomon, “Evolutionary Algorithms and and 2001 respectively. He is working as an
Engineer in CLP Power Ltd. in Hong Kong,
Gradient Search : Similarities and Differences”, IEEE responsible for Protection and Substation
Transactions on Evolutionary Computation, Volume 2, pp Automation. His rescarch interest is power
45-55, July 1998. system protection, the applicahon of artificial
[6] C.W. So, K.K. Li, K.T. Lai, K.Y. Fung, intelligent, substation automation and power
system computer programming
“Overcurrent Relay Grading Coordination Using Genetic
Algorithm”, IEE APSCOM-9 7 International Conference,
Hong Kong, Vol. 1, pp. 283-287, November 11-14, 1997.
[7] C W So, K K Li, “Overcurrent Relay K. K. Li received the M.Sc. and the Ph.D degree
Coordination by Evolutionary Programming”, Journal of from the University of Manchester Institute of
Electric Power System Research, Volume 53, pp 83-90, Science and Technology, Manchester, U.K., and
2000. City University, London, U.K. He is currently an
Associate Professor in the Department of
[8] A. E. Eiben, R. Hinterding, and Z. michalewicz, Electrical Engineering, Hong Kong Polytechnic
“Parameter Control in Evolutionary Algorithms”, IEEE University, Hong Kong. His research interests
Transactions on Evolutionary Computation, Volume 3, pp are power systcm protection and A I applications
124-141, July 1999. in power systems.
[9] R. Billinton, and R.N. Allan, “Reliability
Evaluation of Engineering Systems: Concepts and
Techniques”, Plenum Press, New York, USA, 2”dEdition,
1992.
[ 101R. Billinton, and R.N. Allan, “Reliability
Evaluation of Power Systems”, Plenum Press, New York,
USA, 2”dEdition, 1996.

382

You might also like