OBSERVED DATA

Drilling of test holes in Foundation treatment of K.R.Dam for Test holes at KMs 1.50, 1.70,
1.90, 2.10, 5.185, 6.085, 7.009m 7.254, 7.485, 7.683, 7.758, 8.078 and KMs 8.265 (13 Nos)
Observed data for drilling of test holes for K.R.Dam for foundation treatment with Joy-7
Diamond drill (Corrected). For Reaches from Km.0.560 to Km.8.000.

S.No Description of work Amount Out turn of life Cost/RMT Remarks


of materials
1 2 3 4 5 6
I Drilling of holes 75mm. Dia (NX size)
in all types of rocks including hire
charges of machinery etc., complete
to full Reservoir depth from bottom
level of cut-off (to reckoned from
ground level) including plain washing
the hole with air and water Jets drilling
by Rotary method with Diamond drill.

a) Hire charges of Joy-7 Data as per


Diamond drill sanctioned
Total Hours worked estimate for
32.00 Drainage
Total depth drilled in rock 22.86 gallery of
Average rate of drilling 22.86 Somasila
drill per 1 Hour (as per 32.00 Project.
sanctioned estimate for =0.71 CE/TGP/SKHT
Drainage gallery of No.62/02-03.
Somasila)
Hire charges of Joy-7 275.14 1 RMT 387.52
Diamond drill for 1 RMT 0.71

B) Cost of drill bits


Cost of NX resetting bits Data as per
used 5 Nos. each sanctioned
Cost of each bit 6167.50 estimate for
1233.05x5 1541.88 Drainage
Add 25% extra 7709.38 gallery of
Cost per RMT 7709.38 1RMT 337.24 Somasila
22.86= Project.
337.24 CE/TGP/ SKHT
No.62/02-03.
c) Cost of reaming shell
Total No.of reaming shell 1No
used
Cost of new reaming 2000
shell at Rs. Data as per
Add VAT @ 4%: 25% 500 sanctioned
extra 2500 estimate for
Cost of reaming shells 25.00 Drainage
used 80% gallery of
Total depth of Hole 2500x80 = Somasila
100 Project.
Rs.2000/- CE/TGP/SKHT
Cost of reaming shell Rs.2000/ 87.49 No.62/02-03.
2.86
TOTAL 812.25
2

S.No Description of work Amount Out turn of life Cost/RMT Remarks


of materials
1 2 3 4 5 6
d) Cost of Drill rods, core B.F 812.25
barrel, core lifter and
fishing tools.
Cost of Drill rods of 25 53000
Mts
Cost of Core lifter 200
Cost of fishing tools 1000
Data as per
Cost of core barrel 5’ 1800 sanctioned
56000 estimate for
Add 25% extra 14000 Drainage
70000 gallery of
Somasila
Assuming the life of the Project.
above materials as 2000 CE/TGP/SKHT
Hr. No.62/02-03.

Rate per Hour 35.00 1 RMT 49.30


=70000/2000=35.00 0.71
Rate per 1 RMT
e) Extra crew charges for
drilling the following crew
is required for carrying
out the drilling operations
such as extending rods Data as per
removing the core sanctioned
changing of bits etc., estimate for
Fitter Gr.II – 1 No.x 188/- Drainage
=188.00 gallery of
Helper Gr.II 2Nox188= Somasila
376.00 Project.
Total Rs. 564.00 CE/TGP/SKHT
Rate for 1 Hour= 564/8 No.62/02-03.
= 70.50
Rate per 1 Mt=
70.50/0.71= 99.29 99.29 1 RMT 99.29
f) Cost of water charges 0.04385 280 Lts/1RMT 12.29 Rate as per
sanctioned
estimate CE/
TGP/No1/02-03
g) 10 H.P Diesel pump to Rate as per
supply water to drilling sanctioned
Hire charges of 10 H>P estimate
diesel pump as approved 49.82/Hour 0.49/1 RMT 24.41 CE/TGP/No.
in sanctioned estimate 1/2002-03
CE/TGP No. 1/2002-03.
h) Shifting charges of L.S 3.00 Rate as per
drilling machine and sanctioned
other materials from estimate
Hole to Hole. CE/TGP/No.
1/2002-03
TOTAL 997.52
3
S.No Description of work Amount Out turn of life Cost/RMT Remarks
of materials
1 2 3 4 5 6
I) B.F.985.75
Cost toward flushing
rods L.S 10.00
j) Plain washing after Rate as per
drilling with Air and sanctioned
Water Jets. estimate
1 CE/TGP/No.
Hire charges of Air 687.96/ 0.15 /Hour 03.19 1/2002-03
Compressor Hour

k) Cost of Hose pipe 1 ¼”


Dia 100 Mts length Rate as per
sanctioned
Rate as approved in estimate
CE/TGP/1 /450/RMT CE/TGP/No.
1/2002-03
For 100 Mts – 100x450= 45000.00 0.49 22.05
Hour/1000M
Labour charges for fixing
pipes for washing

Fitter 1No x206= 206.00


Helper 2Nox188= 376.00
M.M 2Nosx146=292.00
874.00 874.00/ 0.06/Days 52.44
Day 1RMT

l) Water required for Rate as per


1RMT=550 Lts sanctioned
estimate
Rate as per Hire charges 0.04385 550Lts/1RMT 24.11 CE/TGP/No.
for ‘K’ item above 1/2002-03.
Hire charges of 10 H.P
Diesel pump as per 50.00/Hour 0.23 11.46
above item Hour/1RMT

GRAND 1220.77
TOTAL

Asst. Exe. Engineer, Dy. Executive Engineer, Executive Engineer,


SSLC&SB Sub Dvn.No.2, SSLC&SB Sub Dvn.No.2, SSLC&SB Division No.2,
K.R.Dam. K.R.Dam. Nellore.