Professional Documents
Culture Documents
International Seminar on HVDC Systems, CIGR SC B4 SC B2 Buenos Aires, Argentina June 5th & 6th, 2008
Overview
SING
Transelec Transmission System Chilean Energy Market Situation HidroAysn Generation Project Aysn-SIC HVDC Transmission Project Feasibility Studies
Planning studies Power system studies Engineering studies Technical solutions Economic evaluation
Transelec is the largest electricity transmission company in Chile, concentrated on the highest voltage levels: 500 kV, 220 kV and 154 kV Transelec owns 959 kilometers of transmission lines and 4 substations in the Northern Interconnected System (SING)
SIC
Transelec owns 7.244 kilometers of transmission lines and 44 substations in the Central Interconnected System (SIC)
SING
8.5%
SIC
SIC GENERATION INSTALLED CAPACITY
1996
4859 MW
19% 1% 4%
2006
8274 MW
6% 2%
US$/MWh
Diesel
70 45 30
1997
2004
2010
YEAR
COAL+HYDRO
COAL+HYDRO Incentive to develop: New Coal fired plants Hydro resources at SIC Hydro resources in Aysn
SIC
2010
2012
2014
2016
2018
2020
Central Interconnected System (SIC): Maximum demand 2007: 6.313 MW 2013: 8.700 MW (5.7 % growth per year) 2020: 13.000 MW Installed capacity 2007: 9.148 MW
TG Diesel Central Cogeneracin Central Carbn Central GNL/GN Central Hidroelctrica Central Elica
Santiago
Baker 1
4.420 GWh
Baker 2
2.530 GWh
Pascua 2.1
5.110 GWh
Pascua 1
3.020 GWh
Pascua 2.2
3.350 GWh
CHILE
Santiago
SIC
1000 km
Puerto Montt
1000 km
Cochrane
2015 Pascua 2.2 500 MW 2017 Pascua 2.1 770 MW 2019 Pascua 1 2020 Baker 2 TOTAL 460 MW 360 MW 2750 MW
9
www.hidroaysen.cl
CHILE
Transelec Transmission
Santiago
SIC
1000 km
Puerto Montt
1000 km
660 MW
2015 Pascua 2.2 500 MW 2017 Pascua 2.1 770 MW 2019 Pascua 1 2021 Baker 2 TOTAL 460 MW 360 MW 2750 MW
10
11
Project Challenges on the route from Puerto Montt to South (1000 km)
Environmental challenges
Minimize potential route through protected or sensitive areas Protect Patagonian trees Minimize landscape modification Identify and characterize local Flora & Fauna
Corcovado Park
1000 km
Queulat Park
Geographical challenges
Areas exposed to boulders and erosion
Climatic challenges
Heavy rainfall Low temperatures, strong winds, and heavy ice loads
12
Project Challenges on the route from Puerto Montt to South (1000 km)
Corcovado Park
Demographic challenges
Very low population density which will impact the region during the construction period
1000 km
Queulat Park
Infrastructure challenges
Austral Road is the only gravel road and mainly one way Bridges are very limited tonnage Only one airport (Balmaceda), the rest being small airfields Coyhaique (40,000 inhabitants) is the main supplying center
13
January 2006 2009 2010 - Conceptual engineering - Power system studies - Environmental studies - Basic engineering - Additional studies Start up studies - Specifications Commissioning of the transmission project Construction decision Start up construction 2013 2021 Commissioning of the hydro power plants
Studies stage
Construction 4 years
14
SIC
Transmission capacity 2750MW and distance 2000 km Transmission voltage 500 kV or 600 kV Two alternative solutions: two bipoles or one bipole Conductor size: 2x 42 mm or 4x42 mm respectively, under optimization Reliability concern for design: 2021 Transmission/Max Demand= 20% Transmission/Min Demand= 30%
15
16
Engineering Studies
Engineering and logistic studies to identify practical constrains
System studies were combined with logistic studies to identify main practical constrains How big and heavy can the single converter transformer unit be? Should them be single-phase-two-winding or single-phase-threewinding? Converter Transformers physical dimensions and transportation weight constrains determine the use of single-phase-two-winding over single-phase-three-winding transformers in alternatives where the weight is above 280 tons Thyristor current capability constrains the solutions to two valve groups or two bipoles if more than 4kA monopolar overload is required
17
I2R ~ 60MW/polo
1.35 kA
1350 MW
1230 MW
675 MW
1350 MW
1230 MW
675 MW -500 kV
19
Bipolar operation
1350 MW
2.7 kA
SIC
2370 MW
Aysn
2750 MW
SR: ~210MW
1350 MW
+500kV
20
Economic Evaluation
Aimed at finding the solution that minimizes the present value of the total systemic cost (TSC)
takes into account the investment cost associated to every solution,
Converter costs estimated from budgetary quotations and line cost estimated by line specialists
1.1
1.3
Main Challenges
Definition of the transmission solution under several parameters:
Reliability requirements Spinning reserve Load shedding schemes Investment costs
Construction difficulties:
Selection of the route of the transmission line
Topographic challenges Environmental impact authorization Getting the concession Negotiation of rights of way
23
Conclusions
The Chilean southern hydro generation plus HVDC transmission projects represents a solution that competes efficiently against coal fired power plants. The Aysn-SIC HVDC project will bring renewable energy (produced by HidroAysn) to the Central Interconnected System allowing most the Chilean territory to have access to hydro electricity and avoiding 16.000.000 tons of CO2 emissions per year. Challenges
Incorporating a new technology in the Chilean power system Undertaking complex technical studies that ensure selecting the optimal transmission solution Designing a very long line with respect to the environment Constructing a very long DC line which will cross untouched lands Operating and maintaining the DC line and converter stations
24
Acknowledgements
To HidroAysn for providing essential data regarding the generation project To the Aysn-SIC HVDC Project Management team for collaborating with relevant feedback to this presentation
25
SC B4 contact: Juan C. Araneda Power System Development Manager Apoquindo 3721, 6th Floor Santiago, Chile Tel. 56-2-4677166 jcaraneda@transelec.cl Gabriel Olgun Head of Engineering Studies, Aysn Project Apoquindo 3721, 11th Floor Santiago, Chile Tel. 56-2-4677183 golguin@transelec.cl
www.transelec.cl
26
Biographical notes: Juan C. Araneda is an Electrical Engineer graduated from Universidad Tcnica Federico Santa Mara, Chile (1983) and Master of Philosophy from University of Manchester, UMIST, UK (2002). He worked in the distribution company Chilquinta (1984 to 1989), the generation company Colbn (1989 to 1994) and the transmission company Transelec (1994 to date). Currently he holds the position of Power System Development Manager in Transelec. He has participated as invited lecturer in several universities in Chile. He is a member of CIGR and IEEE. Gabriel Olgun is an Electrical Engineer graduated from Universidad de Santiago de Chile (1993), Master of Science from Federal University of Santa Catarina, Brazil (1999) and Doctor of Philosophy from Chalmers University of Technology, Sweden (2005). In Chile, he was with the distribution company Emec where he undertook a number of studies in planning and engineering (1995 to 2001). After obtaining his PhD he joined ABB Corporate Research, Sweden where he specialized in reliability studies, generator protection and HVDC. He is now with Transelec heading the engineering studies of the Aysn-SIC HVDC Project. He has participated as invited lecturer in universities in Brazil and Sweden. He is a member of CIGR and IEEE.
27