SITE CLEARANCE, EARTHWORK & TURFING

Bill No. 4.1

ITEM

DESCRIPTION

UNIT QUANTITY

RATE (RM)

AMOUNT (RM)

Specification and General Labour Clauses:Note:- The whole of the works are to be carried out in a manner approved by the S.O. SITE CLEARANCE Before commencing site clearance, the contractor shall as certain the existence and position of water and other services from the relevant authorities and arrange for the diversion or termination of the services. The Contractor shall allow for paving all costs and charges in connection there with. A Allow for taking over the site and clear the area and including encroachment area of all rubbish, debris, top soil, lalang, undergrowth,creepers, shrubs , bushes and cut down and remove existing trees and stumps including grubbing uproots and cart away to an approved dumping ground to be found by the Contractor and was permitted by the local authority. (8.10 Acre) EARTHWORK (ALL PROVISIONAL) Note : The rates for excavation to formation level shall include for excavating below water table level, excavating in whatever soil except rock. The rates shall also include all multiple handling on the site. The measurement of all excavations and subsequent disposals shall be those before excavations. All excavations are measured nett. The increase in bulk after excavation shall be allowed for in the Contractor's rates. The Contractor shall allow for consolidation by roller as directed by the S.O. B Bulk excavation to required formation level and fill in the excavated material to area of filling and compacted to 95% of the maximum dry density as determined using BS1377 Test No.13 and required formation level as described all as shown in the drawings and including the formation of slopes. The rate shall include carring out field density tests as described in the specification or directed by the S.O.

Item

M3

12140

B4.1/1

TO COLLECTION

SHM/07/001

Bill No. 4.1 Site Clearance, Earthwork & Turfing ITEM DESCRIPTION UNIT QUANTITY RATE (RM) AMOUNT (RM)

EARTHWORK (Cont'd) A Excavate for unsuitable material to the S.O. approval and remove the excavated unsuitable material from site inclusive of payment of all permits, fees, deposits, etc to the local authority SILT TRAP B Excavate for temporary silt trap bed area size 43.0m x 10.0m x 1.50m deep complete with emergency spillway, sand bag, 450mm diameter perforated pipe riser with coarse gravel filter , 150mm perforated outlet pipe with gravel surrounded , lean concrete and temporary bund and all necessary works all as per Engineer's Drawing TEMPORARY EARTH DRAIN C Excavate for earth trench overall size 0.60m wide x 0.90m high to the S.O. approval and the remove surplus excavated material from site and including the formation slopes WASH TROUGH D Allow for construction wash trough overall size 6.00m x 5.96m complete with 300mm thick concrete base Grade 20, 2 layer BRC A10 , 300m thick crusher run and compacted sub grade including 75mm diameter PVC pipe as per Engineer's Drawing No TURFING E Trim, level and grade to falls slope surfaces of filled or excavated formation to receive and including 50mm thick top soil/vegetable soil to form seed bed conditions for turfing (measured separately) Trim, level and grade to falls flat surfaces of filled or excavated formation to receive and including 50mm thick top soil/vegetable soil to form seed bed conditions for turfing (measured separately) Close turfing to slope surfaces with approved, good grade cow grass, watering, rolling, weeding, tending and maintenance as specified Spot turfing to flat surfaces with approved, good grade cow grass, watering, rolling, weeding, tending and maintenance as specified (END OF ALL PROVISIONAL) B4.1/2 TO COLLECTION 1

M3

12720

No

990

M2

4,000

M2

10,000

M2

4,000

M2

10,000

SHM/07/001

Bill No. 4.1 Site Clearance, Earthwork & Turfing ITEM DESCRIPTION UNIT QUANTITY RATE (RM) AMOUNT (RM)

COLLECTION PAGE B4.1/1 PAGE B4.1/2 . . . . . .

BILL NO. 4.1 - SITE CLEARANCE, EARTHWORK AND TURFING TOTAL CARRIED TO BILL SUMMARY B4.1/S SHM/07/001

ROAD WORKS

ITEM

DESCRIPTION

UNIT QUANTITY

RATE (RM)

Specification and General Labour Clauses:For description of Materials, Workmanship and General Labour applicable to this Bill see "specification". (ALL PROVISIONAL) ROAD WORKS A Excavation surface to reduce level 375mm deep (average) commencing from platform level, including Grading to fall and chamber to obtained road formation level as specified. Excavation surface to reduce level 200.25mm deep (average) commencing from platform level, including Grading to fall and chamber to obtained pavement formation level as specified. Remove excavated material, deposit, spread, level and compact as specification within site as directed by the SO or to Contractor's own dumping site. Allow for keeping the surface of the site and excavation free of surface water. 50mm Thk compacted sand as sub-base, spread and levelled to chambers, gradient and cross fall to receive crusher run. 225mm Thk compacted crusher run as road base spread and levelled to chamber, gradient and cross fall, rolled with roller to receive binder course. 50mm Thk binder course of compacted asphaltic concrete spread, and levelled rolled and compacted as described. 50mm Thk wearing course of compacted asphaltic concrete spread, and levelled rolled and compacted as described.

M3

2,031

M3

270

M3 ITEM

2,301

M2

5,415

M2

5,415

M2

5,415

M2

5,415

TO COLLECTION

SHM/07/001

ITEM

DESCRIPTION

UNIT QUANTITY

RATE (RM)

Road Marking Supply, apply two coats approved 'Thermoplastic' Reflective road line paint as specified or approved equivalent on premix road surface to:A B C 200mm wide x 1000mm long continuity line at 1000mm a part 100mm wide x 1000mm long centre line at 1700mm a part 300mm wide for stop line Pavement direction arrows making to shapes as shown in the drawing D E Straight sign Turn left or right sign arrow NO NO 5 5 M M M 80 644 11

Road Accessories Supply, deliver and complete installation of standard approved traffic sign constructed of 75mm diameter x 3.5mm galvanised iron post with one end fixed to aluminium alloy board including all necessary welding, fixing, bolting, cutting, lettering, painting, excavation, concrete works and formwork all to authority's approval. F G Sign board name for road Stop sign Bollard 75mm diameter Class B galvanised iron pipe fill with concrete to be painted with gloss enamel paint black & white at 600mm centre to centre NO NO 7 5

NO

75

TO COLLECTION

SHM/07/001

ITEM

DESCRIPTION

UNIT QUANTITY

RATE (RM)

Kerb 550mm width x 225 mm thick precast concrete road kerb splayed on top, finished fair on exposed surfaces, bedded, jointed and poited in cement mortar (1:3), including precast concrete channel, outlet, concrete Grade 20 bed, haunch and all necessary formwork, reinforcement and excavation complete all as Ditto, curve on plan Extra Over for forming holes at 600mm centre to centre Prepare and paint two coats of white cement base paint in exposed surfaces of kerb in alternate black and white bays Footpath

M M NO

1,263 126 2,315

B C D

1,389

914mm width including 200.25mm Thk concrete Grade 20 RC slab with one layer of BRC A7 with stamp concrete surface finished including expansion joint at 30m centre to centre and 0.25mm pvc sheet M Testing Allow for all necessary inspections and testing (including coring and compaction tests) including submission of reportsand also pay all necessary fees and deposits including liaison for the inspection and approval (END OF ALL PROVISIONAL)

1,388

ITEM

TO COLLECTION

SHM/07/001

AMOUNT (RM)

SHM/07/001

Road Works

AMOUNT (RM)

Road Works

SHM/07/001

AMOUNT (RM)

SHM/07/001

Bill No.4

ITEM

DESCRIPTION

UNIT QUANTITY RATE (RM)

AMOUNT (RM)

BILL SUMMARY PAGE A B C D E F G H J K SITE CLEARENCE AND EARTHWORKS ROAD WORKS SURFACE WATER DRAINAGE SEWERAGE DRAINAGE WATER RETICULATION FENCING AND GATES RETAINING WALL ANCILLARY BUILDING WORKS OUTSIDE BOUNDARY 1 WORKS OUTSIDE BOUNDARY 2 B4.1/S #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

BILL NO. 4 - EXTERNAL WORK TOTAL CARRIED TO FINAL SUMMARY B4.S/1

SHM/07/001

area depth amount 5414.13 0.375 2030.299

739.635 0.914 0.2 135.2053 2 270.4106