Tutorial 13: Revision
Test 2 possible questions: 9,11,12,13,17,18,29
Objectives:
1. Revision on initiating, planning, executing, monitoring and controlling
processes
Test 2 possible questions: 9,11,12,13,17,18,29
Answer: C
Answer: B
10844574.doc Page: 1 of 5
AY0809 October Semester
Answer: A
Answer: B
Answer: B
Q7. If the actual cost for a WBS item is $1500 and its earned value was
$2000, what is its cost variance, and is it under or over budget?
A. the cost variance is -$500, which is over budget
B. the cost variance is -$500, which is under budget
C. the cost variance is $500, which is over budget
D. the cost variance is $500, which is under budget
Answer: D
10844574.doc Page: 2 of 5
AY0809 October Semester
Answer: C
Q11. A _____ maps the work of a project as described in the WBS to the
people responsible for performing the work.
A. project organisation chart
B. work definition and assignment process
C. resource histogram
D. responsibility assignment matrix
Answer: D
Q14. If you add 3 more people to a project team of 5, how many more
communication channels will you add?
A. 2
B. 12
C. 15
D. 18
Answer: D
Q15. A _____ report describes where the project stands at a specific point
in time
10844574.doc Page: 3 of 5
AY0809 October Semester
A. status
B. performance
C. forecast
D. earned value
Answer: A
Q19. Your boss believes that all of your project team members avoid
work as much as possible. He or she often uses threats and various
control schemes to make sure people are doing their jobs. Which
approach to managing people does your boss follow?
A. Maslow’s hierarchy of needs
B. Theory X
C. Theory Y
D. Herzberg’s motivation and hygiene factors
Answer: B
Q20. Which type of diagram shows planned and actual project schedule
information?
A. a network diagram
10844574.doc Page: 4 of 5
AY0809 October Semester
B. a Gantt chart
C. a Tracking Gantt chart
D. a milestone chart
Answer: C