Alcatel-Lucent GSM

Move BTS/Abis, Different BSC, Different OMC-R MPI14 / MDR2 - CCL

BTS Document Reconfiguration Method

3BK 17430 0142 QZZZA Ed.06

BLANK PAGE BREAK

Status Short title

RELEASED MPI14 / MDR2


All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from Alcatel-Lucent.

2 / 12

3BK 17430 0142 QZZZA Ed.06

Move BTS/Abis, Different BSC, Different OMC-R MPI14 / MDR2 - CCL

Identification
Customer

Country

OMC-R Site

Name: Name:

Address: Address:

Alcatel-Lucent Representative (s) Customer Representative (s)

Customer Contractor Representative (s)

Date, Time and Duration of Work

Start

End

Duration

General Remarks from Customer

General Remarks from Alcatel-Lucent

3BK 17430 0142 QZZZA Ed.06

3 / 12

Applicable Documents
Fill in the edition of the applicable documents Document Title Move BTS/Abis, Different BSC, Different OMC-R BSS Methods Handbook BSS Configuration Handbook BSS Surveillance Handbook Network Reconfiguration Recommendations BSC Terminal User Guide BTS NEM User Guide Document Reference 3BK 17430 0142 RJZZA 3BK 21268 AAAA PCZZA 3BK 21201 AAAA PCZZA 3BK 21206 AAAA PCZZA 3BK 21269 AAAA PCZZA 3BK 21220 AAAA PCZZA 3BK 21228 AAAA PCZZA Edition

Applicable ITL

Information
Fill in the site data. OMC-R Hostname User Name Password

4 / 12

3BK 17430 0142 QZZZA Ed.06

Cases and Options


Enter a cross for the applicable case or option. C1 C1.1 C1.2 C1.3 C2 C2.1 Move BTS(s) New target Abis link must be created There are downstream BTS(s) on the source Abis link There will be downstream BTS(s) on the target Abis link (after move). Move a complete Abis link Source and Target BSC are colocalized, so Abis link recabling is performed on the BSC site Source and Target BSC are not colocalized, so Abis link recabling is performed on the first BTS site (chain) or on the first and last BTS sites (ring). Moved BTS supports at least one share cell Each synchronized BTS supports at least one Main Sector and the procedure applies to the first BTS to be moved Each synchronized BTS supports at least one Main Sector and the procedure applies to the second BTS to be moved One of synchronized BTS supports secondary sectors only. The source and target Abis links do not have the same connection type. BTS to be moved is synchronized with other BTS (no cell sharing) The procedure involves one BTS only or the first one of them. Both BTS have to be moved and the first one is already on the target OMC-R Transfer via an external support such as a diskette or a tape Transfer by ftp Delete Abis (if moved BTS was the last one on source BSC) Modify NExtra AbisTS (if HSDS is supported) Modify LAC of the moved cells Manual Transmission Programming Automatic Transmission Programming

C2.2 C3 C3.1

C3.2 C3.3 C4 C5 C5.1 C5.2 O1 O2 O3 O4 O5 O6 O7

3BK 17430 0142 QZZZA Ed.06

5 / 12

Software & Documentation Versions


Fill in the appropriate INITIAL and FINAL software versions. For BSS reshuffling methods, the INITIAL and FINAL versions are equal. For installation methods, the INITIAL version is "-". Initial Version OMC-R NPA RNO LASER BSS MFS Documentation Version Final Version

6 / 12

3BK 17430 0142 QZZZA Ed.06

Results Table
Fill in the Results Table according to the following rules: YES: Put a cross here if the task was performed NO: Put a cross here if the task was not performed N.A: Put a cross here if the task is not applicable S.A: Enter the number of solved anomalies N.S.A: Enter the number of non-solved anomalies

Scenario Description
Initial Checks
YES Initial Checks Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

Preparation
YES Prepare Backup for Reverse Procedure C3.1, C5.1: BTS Reconfiguration Create BTS / Abis on Target BSC Preparing Inputs on Source and Target OMC-R Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

3BK 17430 0142 QZZZA Ed.06

7 / 12

Switch BTS
YES Shut Down Cells on Source Impacted BTSs Shut Down Cells on Target Impacted BTSs Recable Impacted BTS Unlock Cells on Downstream BTSs (on Source and Target OMC-R) Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

Set into Service Cells Belonging to Moved BTS


YES Inform MSC that Cells Are Moved Unlock Cells on Moved BTS C3.2, C5.2: BTS Reconfiguration Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

Final Checks
YES Final Checks Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

8 / 12

3BK 17430 0142 QZZZA Ed.06

Reverse Procedure
Shutdown Cell on Impacted BTSs
YES Shutdown Cell on Impacted BTSs Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

Perform a Rollback Reconfiguration and Activate Backup PRCs


YES Perform a Rollback Reconfiguration and Activate Backup PRCs Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

Reinsert Impacted BTS in Source BSC


YES Reinsert Impacted BTS in Source BSC Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

Unlock Cells on Impacted BTSs


YES Unlock Cells on Impacted BTSs Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

3BK 17430 0142 QZZZA Ed.06

9 / 12

Delete BTS on Target BSC


YES Delete BTS on Target BSC Performed by Site Date Start Time End Time Duration NO N.A S.A N.S.A

10 / 12

3BK 17430 0142 QZZZA Ed.06

Unavailability Duration Sheet


Fill in the unavailability duration sheet according to the following rule: Section Title Title of the paragraph where the unavailability occured Unavailability type T for traffic interruption, R for traffic reduction, S for loss of supervision (T,R and S could be held simultaneously) Equipment Equipment with its number (eg BTS-1) Date Date expressed as: yy/mm/dd Start time Start time expressed as: hh/mm/ss End time End time expressed as: hh/mm/ss

Unavailability Type Section Title

Equipment

Date

Start Time

End Time

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

3BK 17430 0142 QZZZA Ed.06

11 / 12

Anomaly Sheet
Fill in the unavailability duration sheet according to the following rule: Section Title Title of the paragraph where the anomaly occured Brief description of the anomaly Summarize the anomaly (details must be in anomaly report) Anomaly report Anomaly report was sent or no Solved by Name of the technician who solved the anomaly Date of anomaly solving

Description Section Title: Brief description of the anomaly: Date: Anomaly report: Y/N Section Title: Brief description of the anomaly: Date: Anomaly report: Y/N Section Title: Brief description of the anomaly: Date: Anomaly report: Y/N Section Title: Brief description of the anomaly: Date: Anomaly report: Y/N Section Title: Brief description of the anomaly: Date: Anomaly report: Y/N Section Title: Brief description of the anomaly: Date: Anomaly report: Y/N Name: Name: Name: Name: Name: Name:

Solved by

12 / 12