Purpose
To provide an overview of library facilities designed and constructed utilizing 2003 bond funds To provide an update of the status of library facilities designed and constructed utilizing 2006 bond funds To recommend best use for bond savings
www.dallascityhall.com
Background
The 2003 and 2006 Bond Programs included $101.5M in funding for Library facilities Total value of 2003 Bond Proposition 3: $55.5M
Land Acquisitions=$0.6M New Libraries and Renovation= $54.9M
www.dallascityhall.com
www.dallascityhall.com
www.dallascityhall.com
Polk Wisdom Renovation (under construction) Fretz Park Renovation (under design)
www.dallascityhall.com
Location map
www.dallascityhall.com
Construction Documents phase completion June 2012 Funding for construction not originally included in the 2006 Bond Program
www.dallascityhall.com
11
Location map
Location map
www.dallascityhall.com
13
www.dallascityhall.com
14
Status
Design
Construction
Under Construction Closed for renovation Scheduled to close for renovation Late 2012 In Design In Design In Design In Design In Design
Highland Hills Forest Green North Oak Cliff Park Forest Preston Royal Vickery Meadows
* * * *
www.dallascityhall.com
15
www.dallascityhall.com
www.dallascityhall.com
17
www.dallascityhall.com
18
Recommendation
Utilize the $8.7m in 2006 bond savings to: Fund the construction of the Highland Hills branch library = $6M
The Library Master Plan originally called for the replacement of the Highland Hills Branch Library in 2002, and the remaining 4 branches in 2005 Highland Hills was the only library in the 2006 bond program that was originally funded for design
Remaining branches were designed utilizing bond savings
www.dallascityhall.com
19
Recommendation
Fund the renovation of the J. Erik Jonsson Central Librarys 7th Floor Texas/Dallas History and Archives = $3M
A public/private partnership between the Friends of the Dallas Public Library and the City of Dallas was formed in 1995 to fund the renovations of the Central Librarys public floors The City of Dallas committed to match private donations to fund the renovations:
1st Floor completed 1998 2nd Floor completed 2011 3rd Floor completed 2007 4th Floor completed 2003 5th Floor completed 2006 6th Floor TBD 7th Floor TBD 8th Floor completed 2002
The Friends of the Dallas Public Library have received $3M in private gifts to fund the renovation of the 7th floor
www.dallascityhall.com
20
Recommendation
Recommended Project Savings: Highland Hills Replacement Branch Renovation of Central Library 7th Floor* Total: Estimated Cost $8.7m $6.0m $3.0m ($0.3m)
Additional savings from ongoing and scheduled projects are expected to cover the $300k shortage.
www.dallascityhall.com
21
Questions
www.dallascityhall.com
22
APPENDIX
www.dallascityhall.com
23
www.dallascityhall.com
24
www.dallascityhall.com
25
Renner-Frankford
$87,500
Scheduled
www.dallascityhall.com
26
North Oak Cliff Park Forest Renner Frankford Walnut Hill Central Library Downtown Branch
www.dallascityhall.com
27