HAZIRA 1 & 2, Pipe Limits

Item 1 HP STEAM DRUM 2 BOILER HEADERS 3 BOILER TUBES 4 INTERCONNECTING PIPING 5 DRAINS 6 VENTS 7 HP MAIN STEAM UP TO STOP VALVE 8 HP MAIN STEAM DOWNSTREAM STOP VALVE 9 FEEDWATER LINE FROM NON RETURN VALVE UP TO ECO INLET HEADER ASME Boiler Proper ASME B&PV Code Sect. I Boiler Proper ASME B&PV Code Sect. I Boiler Proper ASME B&PV Code Sect. I Boiler Proper ASME B&PV Code Sect. I Boiler External Piping ASME B31.1 (up to the second valve) Boiler External Piping ASME B31.1 (up to the first valve) Boiler External Piping ASME B31.1 Non Boiler Piping ASME B31.1 Boiler External Piping ASME B31.1 Non Boiler Piping ASME B31.1 Non Boiler Piping ASME B31.1 Non Boiler Piping ASME B31.1 Boiler External Piping ASME B31.1 (up to the first valve) Non Boiler Piping ASME B31.1 Boiler External Piping ASME B31.1 Integral piping External piping External piping Boiler Boiler Boiler Integral piping IBR HAZIRA Applicable Code IBR IBR IBR IBR From ECO inlet header up to SH outlet heder (first circumferential weld after PSV included) Up to the second valve Up to the second valve From ECO inlet header up to SH outlet heder (first circumferential weld after PSV included) Note

Integral piping IBR (up to the second valve) (up to the second valve) Integral piping IBR (up to the second valve) (up to the second valve) Integral piping External piping Integral piping External piping IBR and ASME B31.1 IBR and ASME B31.1 IBR and ASME B31.1 IBR and ASME B31.1 IBR and ASME B31.1 IBR and ASME B31.1 IBR IBR and ASME B31.1 IBR and ASME B31.1

10 FEEDWATER LINE UP TO NON RETURN VALVE 11 HOT REHEATER LINE 12 COLD REHEATER LINE 13 14 LINE STARTING FROM NOZZLES ON BOILER OR INTEGRAL PIPING (AS PER IBR) LINE FROM TERMINAL POINT UPSTREAM THE FIRST VALVE OF BOILER

Integral piping only up to the first valve, if present; otherwise, external piping Integral piping only up to the first valve, if present; otherwise, external piping Refer also to sketch sent by SAT Refer also to sketch sent by SAT Provisional end cap is to welded on the spray nozzle for IBR Hydrotest of Boiler and Integral Piping

15 DESUPERHEATING LINE TO SPRAY NOZZLE

Boiler and Integral piping - To be approved as IBR Boiler and Integral piping and to be designed in acc. with IBR sections for Boiler and Integral piping Integral piping - To be approved as IBR Integral piping, but to be designed as External piping in acc. with IBR sect. IIIV and ASME B.31.1 External piping - To be approved as IBR External piping and to be designed in acc. with IBR sect. IIIV and ASME B.31.1