VIRAJ SAP PS User Guide

TABLE OF CONTENTS

Project Process Name Page No.


Create a Project Manual Project Cost Planning Project Budgeting Release Quarterly Based amount Budgeted value Release the Budgeted WBS Element for Execution Create Project Management Work Center Creation and Change of Network Header and Activities Project Date Planning and Scheduling Assignment of Project Team on WBS Element Level Resource Planning in Internal Activities Material and Service procurement for project Project Execution Project Versions (To set Baseline) and Simulation Versions (To see Future Implications) Project Material Consumption and Stock transfer from One Project to other Project or Storage Location Budget supplement to a WBS element Budget return Budget Transfer Project Closure

Create a Project

Procedural steps: Access Project Builder through: Via ECC Menu Via Transaction Code Logistics or Accounting > Project System > Project > Project Builder CJ20N

Work List and templates Structure Tree

Structure Tree

Work Area

The structure tree displays the project object (project definition, WBS element, Network, activity) Worklist You can store user-specifically frequently used project data (project definitions, networks, and WBS elements) in the worklist, so that you can access them quickly later. Furthermore, a list of the last five projects that you have worked on is always displayed in the worklist. Work Area In the work area, you see the details view of the object selected in the structure tree. You can also directly access overviews of subordinate objects. Here you can execute all the business transactions for project coordination and execution. You can always move between the detailed view of the selected object and the overviews of the subordinate objects.
3

There are two ways to create Project in Project Builder as 1).

2).

Select appropriate Investment Profile for document posting.

From this open button we can see created Project list.

Project Objects can be viewed as:

Network overview Activity overview Milestone overview PS Text overview Document overview

Manual Project Cost Planning

Cost planning for the Project can be done by various methods. We are using Manual Cost Planning (Hierarchical Planning) Access transaction by:
Via Menus Via Transaction Code Logistics Project System Financials Planning Cost in WBS Overall Values Change CJ40

Select the Project by taking drop down here or clicking F4


Select the version, 0 or 1 or 2 as only three versions are available in
9

10

11

12

If no error while check cost values then system will allow to save cost planning for version 0

13

Project Budgeting:-

The Project Budgeting will be copying from the Project cost planned with suitable approved version, before scheduling the original project for actual executions. Default cost planning for budgeting is 0.

Access transaction by:


Menu path Transaction code Logistics Project System Financials Budgeting Original Budget Change CJ30

14

15

16

17

18

19

20

Release Quarterly Based amount Budgeted value:Logistics -> Project system -> Financials -> Budgeting -> Release -> CJ32 Change CJ32

Access the transaction by: Via Menus Via Transaction Code

Once you click CJ32, the selection screen shall appear as follows

21

22

The Current Budget and Planned Totals at the right may be used as a reference to decide upon the budgets released amount. You can select the WBS Elements which have budgeted and have the system calculate the budget amounts as a fixed percentage of the Current Budget. In our case, we select all the WBS elements listed above. Then, using the menu path Edit Copy View (Shift + F1), choose 5th option Current Budget and giving the percentage as 25.

23

24

25

26

After released the Budget, Rlease Budgeted WBS element, so background system will be created AUC ( Asset Under Construction) or CWIP Asset with WBS data for monthly settlment form WBS to AUC and at the time of Capatilzation settlment from AUC to Fix Asset settlement

27

Release the Budgeted WBS Element for Execution:-

28

Create Project Management Work Center:Logistics Project Systems Basic Data Master Data Work Centers master Record Create CNR1

Menu Path

Transaction Code

Note: After entering in all required data fields, press the tab page Capacities, following screen will appear

29

Enter Capacity category 002 (person) and formula for calculating the capacity requirement Press Enter, following screen will appear. Enter factory calendar VL, capacity planner group-A, base unit of measure DAY, working times and no. of individual capacities in the work centre. After this press enter system calculates the available capacity and operating time based on the input data. Enter percentage overload, and check the indicators shown in the screen above. This is to ensure that the availability check of this work centre will happen during scheduling.

30

Note: After entering in all required data fields, press the green arrow press the Scheduling tab page, following screen will appear

to go back to Capacity overview page, than

Enter capacity category Note: After entering in all required data fields, press the tab page Costing, following screen will appear

31

Enter respective cost center, activity type and formula again. Now you can link your Project Organization structure (Project Department Hierarchy Defined in HR) can link to this work center for Resource Planning.

32

33

You have now created a New Work Center. Note: You must now save your work by clicking on the Save, which will then give you the message, Work Center xxxxx in Plant xxxx was created. You have now finished the task.

Creation and Change of Network Header and Activities:-

Access the transaction using:

Via Menus

Logistics Project System Project Special Maintenance Functions Networks Create

34

Via Transaction Code

CJ20N/ CN21

A network consists of the following: Activities Activity elements Relationships

In the network header you can enter the following data, which are used as default values for the entire network: Assignments to other object like WBS element Basic start (in case of Forward scheduling) or finish date (in case of backward scheduling) as well as indicator for Auto scheduling Release and scheduled dates Assignments of organizational data, such as profit center

The process of creating Network manually is explained here.

35

36

37

8
8.1

Project Date Planning and Scheduling:Project Planning Board / Date Planning

1. Durations are maintained in each activity. 2. Relationships are maintained among activities

8.1.1

Overview of Project Planning Board

Access the transaction using: Menu path Transaction code OR 2. From Project Builder by clicking Project planning board button as shown below, on the application bar. Logistics Project System Project Project Planning Board Change CJ2B

On the following Change Project Planning Board screen enter the necessary data: Before entering the project planning board, expand the project structure so that the activities are visible. These are then shown in the Project planning board as well. Users can go to planning board

38

Goto Settings Options. The following selection options will appear for scheduling

8.1.2

Other functions of Project planning board

All activities in the network are scheduled. Dates are copied to WBS. Critical activities are shown in red colour. The chain of critical activities is called as critical path. There are various activities can be perform through planning board. Icons on the planning board are as follows:

a. b. c. d. e. f.

g.

h.

i.

j. k.

l. m. n. o. p. q. r. s. t. u. v. w. x. y. z.

a. b. c.

Select all Deselect all Move up

39

d. e. f. g. h. i. j. k. l. m. n. o. p. q. r. s. t. u. v. w. x. y. z.

Move down Create Copy Cut Paste Undo Connect activities selected Relationships list Delete Details Confirm activity Schedule Calculate planned costs System/user status Network header Component overview Capacity overview Maintenance orders Costs overview Milestone trend analysis Successor/predecessor Show hide

40

41

1. 2.
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20.

3. 4.

5.

6. 7. 8. 9.

10. 11.12.13.14.15.16.17.18. 19. 20.

Open / close left window Open / close bottom window Filters Group Sort Highlighting Position Connect Scheduling comparison Zoom Adjust diagram area Adjust time axis Planning board assistant Time axis assistant Set of dates Options Field selection Legend Logs User settings.

8.1.3

WBS Scheduling

4. On the following Project change screen click on the select all icon. 5. Edit Function Schedule. Or click on the Schedule icon . System uses the networks start and finish date (in turn project start and finish dates since dates are copied from Project Definition) as the basis for calculating and displaying the earliest and latest dates for the activities.

42

6. Choose Edit Select WBS Elements.

8.1.4

Copying Schedule dates and extrapolating to WBS elements

7. Choose Edit Reconcile dates Copy scheduled dates. The system copies the maximum dates (earliest start and latest finish) determined in scheduling for each activity and displays them as date bars in the WBS elements.

8. To copy dates from lower WBS Elements to superior WBS Elements, Edit Deselect All Edit Reconcile Dates Extrapolate Dates.

Save your settings.

43

Assignment of Project Team on WBS Element Level

Select WBS Element, Edit->WBS Element-> Project team for WBS Element

Select WBS and Create assignment (F7)

44

45

46

10 Resource Planning in Internal Activities:Transaction:-Cj20n As shown in below screen shot the required amount of work system will calculate automatically from duration Activity type is maintained under cost center which contains the per unit rate of the work. In below example work planned is 10 Days for activity Excavation for 5400 plant. Activity type will be taken from cost center.

47

Here we can distribute 10 Days work in different resources.

11

Material and Service procurement for project

Once the structure exists for the project, you can start to plan/add components to activities. Cost planning and scheduling takes place simultaneously.

48

To add component for an activity: Select an activity There are different views under the activity:

Adding material for an activity There are two ways to add components to activities: 1) By dragging and dropping from the template area

Drag and drop the Material component object from template area to an activity. The screen will look as illustrated in the picture above. Give material definition, item category L (stock ), and qty. 2) By selecting the Component overview button, you can start to add components.

49

After the selection the screen looks as follows:

In this table you can add components to activities. Required fields are Material, Requirement qty and Item category. 1) Adding items which is manufactured by same BU: Always select L Stock item in the item category field.

50

The alternatives when the item category marked as L - Stock item for material

[Reserve for network: Use this indicator to specify that a reservation is created for materials kept in stock (stock items).] [Reserve. WBS element: You use this indicator to create a reservation for the non-stock item for the network and post the material in the project stock after goods receipt.] Preq+Res WBS elem.: Use this indicator to specify that the purchase requisition for the non-stock item and stock items, will be converted into a standard purchase order for the project. [Prelim. Preq-WBS el: Specifies that a purchase requisition is created for the material and this purchase requisition is then converted into a preliminary order for the WBS element. No MRP-relevant reservation is created. After goods receipt for the purchase order, a receipt is posted to the project stock.] [3rd party req. WBS el: Specifies that a purchase requisition should be created for the material and then converted to a third-party order for the WBS element. When the delivery address is separate from the plant address]

Procurement Parameter Tab:-

51

The data in Procurement parameter tab defaulted from material masters setting based on item category selected while creating component. From release means that the activity is released when the WBS element above is released Immediately means that the activity is immediately when the component is attached to activity

Long Text Tab

12 Project Execution:12.1 Activity Confirmation

5.1.1 Manual Confirmation of activity


Via Menus Via Transaction Code

Logistics Project System Projects Project Builder CJ20N

Enter Actual date for milestone: Actual date can be entered, either Confirming the activities so that the milestone will pick the actual date from activities OR , enter actual date manually in milestone actual date field. Open the project through Project Builder transaction (CJ20N) > Select the network > click on activity overview > select the activities which are required to be confirmed > click on confirm icon.

52

2. clcik on activity overview

1. Select the Network

3. Select the activity

4. Confirm the activity

53

4. If processing % is less than 100% then dont select the final confirmation and completed check box. Only enter Processing %.

5. After save system will save PCNF: Partially confirmed this activity.

6. At the time of Full confirmation select final confirmation and completed check boxs. Enter actual date finish date and go back.

54

13 Project

Versions (To set Baseline) and Simulation Versions (To see Future Implications):-

13.1 Project Version Creation: Once our Project Date Planning will be frozen out and scheduled the Project then system calculates start and finish dates for all WBS and activities. If you want set this will baseline for my future reference then create Version through T code CN72 (Create Project Version).
Menu path Transaction Logistics -> Project System -> Project -> Project Version -> Create CN72

55

13.2 Project Creation In Simulation mode: We can Transfer our active Project into Simulation Project for Future date implications.
Menu path Transaction Logistics -> Project System -> Project -> Simulation -> Transfer Project CJV4

56

57

14 Project Material Consumption and Stock transfer from One Project to other Project or Storage Location:

14.1 Project Material Consumption:The Purchase Department will convert your Project Material Purchase requisition into Purchase Order. Then that material received in Project Stock for consumption.
Menu path Transaction Logistics Logistics Execution Outbound Process Goods Issue for Other Transactions Enter Goods Issue (Mvt type is 281) MB1A

Before Procurement, the stock of material is as

After Procurement, the stock of material is as 58

Consumption of Materail against Network Activity:-

59

After consumption Project stock is as

60

14.2 Project stock transfer from one project to other Project:As per project requirement we can transfer project material from one to another project. Here the receiver WBS and sender WBS must have same system status and sufficient budget must be available for stock transfer.
Menu path Transaction Logistics Logistics Execution Internal Whse Processes Posting Change Via Inventory Management Enter Posting Change (Movement type is 415) MB1B

61

62

63

14.3 Project stock transfer from Project stock to storage Location:At the time of Project closer all project stock should consumed or transferred to another project or we can transfer this project stock into storage location stock.
Menu path Transaction Logistics Logistics Execution Internal Whse Processes Posting Change Via Inventory Management Enter Posting Change (Movement Type :411) MB1B

64

65

15 Budget supplement to a WBS element


Menu path Transaction Logistics Project System Financials Budgeting Supplements Supplement to Project CJ36

You will get the following screen

Input the receiver year and the text describing the reason of supplement Press Enter You will get a screen like the one shown below

66

Enter the Receiver WBS Element and Amount being supplemented to the WBS element as shown above. Save the transaction by clicking on the Save Button. After that release the same amount in CJ32 (Release Budget), then only system will allow using it.

67

16 Budget return
Menu path Transaction Logistics Project System FinancialsBudgeting Return from Project CJ35

Following screen appears,

68

69

17 Budget Transfer
Menu path Transaction code Logistics --> Project system-->Financials --> Budgeting --> Transfer CJ34

Input sender/receiver years, the text and Press Enter

70

71

Enter the Sender WBS Element, Receiving WBS Element and Amount being transferred between the WBS elements as shown above. Save the transaction by clicking on the Save Button.

Budget Line Item Report


Menu path Transaction code The initial screen follows as below, Logistics --> Project system--> Information system --> Financials --> Line Items --> Budget CJI8

72

Budget Type KBUD Original Budget Budget Type KBNO Supplement Budget Type KBRO Return Budget Type KBUS Transfer You can view the changes made in the report S_Alr_87013560 Enter the Project Definition and execute

73