Republic of the Philippines NORTHWEST SAMAR STATE UNIVERSITY Main Campus, Calbayog City

A Report on the Subject Engineering and Technology Management Engr. Ramil Catamora Instructor

PROJECT SELECTION AND MANAGEMENT


Reporter: HENDRIX R. ORTEGA, CE

Introduction
2

Project management has emerged because characteristics of our late twentieth-century society demanded the development of new methods and techniques of management, but its roots may be traced back to ancient times.

Project Selection and Management

Project selection
3

may simply be described as the process of evaluating projects, and then choosing to implement some of them to achieve the goals of the parent organization.

Project Selection and Management

Four objectives of project selection


4

choose only the viable projects reject the undesirable projects ensure that there is no damaging effect on flow of project proposals and ensure that there is no rejection of desirable projects

Project Selection and Management

Terms and Definitions


5

Project. This is a plan of work job assignment, or task. Project management. This is the art of directing and coordinating material and human resources throughout the project life span by utilizing various management methods and techniques to achieve effectively predetermined goals of scope, quality, time, cost, and participant satisfaction. Project manager. This is a person with an assigned direct responsibility for project execution. Project organization. This is an establishment of people, procedures, responsibilities, and authority. Project selection. This is the process of evaluating projects and then choosing to implement some of them to achieve the goals of the parent organization.

Project Selection and Management

Terms and Definitions


6

Project objectives. These are the goals, as measured by time parameters, constraints or targets, results, milestones, and control considerations, and usual project sequencing. Project team. This consists of all participants involved in the project (i.e., full or part time). Project parameters. These are the factors, specifications, or characteristics of the complete project or of its parts.

Project proposal. This is a summary of a proposed project concerning its managerial, schedule, and technical contents.
Project control report. This is a management report and an operations tool utilized to report manpower- or financial-related information in a summarized form both by program and organization

Project Selection and Management

Types of Information Required for Evaluating a Project


7

Main categories of information required for project evaluation. Project Selection and Management

Project Selection Models


8

Inadequate reliable estimates for cost, performance, utility, and time; Inadequate recognition of the interrelationships between projects; Dynamic nature of project selection and review; Poor handling of uncertainty and risk; Poor consideration given to the relationship between the effort applied to a project and the chance for success; Necessity for multiple criteria for evaluation.

Project Selection and Management

Types of Project Selection Models


9

Benefit-Cost Ratio Model Disman Model Pacifico Model Mottley and Newton Model Calculated-Risk Model Sobelman Model Manley Model Profitability Index Model Relative Worth Index Model Dean-Sengupta Model Net Income Present Value Model
Project Selection and Management

Types of Project Selection Models


10

Benefit-Cost Ratio Model

This simple model is concerned with performing analysis to determine if benefits from a given project outweigh its cost. More specifically, it is only worthwhile to consider a project for development if its benefits are far greater than the investments. Nonetheless, the benefit/cost ratio is defined by:

BCR = UB/TIC where


BCR TIC UB

is the benefit/cost ratio. is the total investment cost including the operating cost. is the user benefits.

For a project to be beneficial, the value of BCR must be greater than unity.

Project Selection and Management

Example
11

Assume that a machines acquisition cost is P100,000 and its expected useful life is 15 years. The annual maintenance plus operation cost of the machine is estimated to be P4,000. The lifetime benefits of the machine are estimated to be P200,000. Calculate the value of the benefit/cost ratio. The total investment cost of the machine is: TIC = P100,000 + (P4,000) (15) = P160,000

Substituting the above and specified values

BCR = P200,000/P160,000 = 1.25

The value of the benefit/cost ratio is 1.25.

Project Selection and Management

Project Organization may be divided into the following phases


12

Investigation phase Start-up phase Growth phase Maturity phase Decline phase Phase-out phase

Project Selection and Management

13

Project management performs many functions , and they may be categorized into seven major areas.

The characteristics of a project management procedure include limited life project, dynamic changes in responsibilities and organization, project- oriented organization, frequent progress evaluation, poor project management control over participants from other firms, and clearly defined goal, task, and subtask responsibilities

Project Selection and Management

Three basic responsibilities of a project manager


14

To ensure that the product under consideration is produced within the allocated budget; To ensure that the product under consideration is delivered to the customer within the limits of a defined time schedule; To ensure that the product under consideration satisfies fully all of the specified performance requirements.

Project Selection and Management

A successful project manager possesses qualifications


15

Appropriate previous experience; Thorough understanding of profitability concepts; Effective knowledge of management problems A burning desire to train and develop supervisory personnel; Sufficient working knowledge in various areas of science.
Project Selection and Management

Project Management Methods


16

Critical Path Method (CPM)


is

used in situations where the duration times of activities are quite certain.

Program Evaluation and Review Technique (PERT)


is

used in situations where the duration times of activities are quite uncertain

Project Selection and Management

For both of these methods to be most applicable


17

a project must possess the following four characteristics


Independent jobs or tasks. Full job completion. Ordered jobs. The defined jobs completion leads to actual project completion.

Project Selection and Management

PERT Steps
18

1. Break down a given project into various jobs or tasks and identify each of these jobs or tasks. 2. Determine the sequence of these jobs or tasks and develop a network. 3. Estimate the duration time of each activity. 4. Obtain each activitys expected duration time. 5. Determine the time variance of each activity. 6. Determine the networks critical path. 7. Calculate the probability of project completion on a given time or date.

Project Selection and Management

General steps of PERT and CPM.


19

Project Selection and Management

CPM Steps
20

1. Break down the project into various jobs or activities and identify them. 2. Determine the sequence of jobs or activities and develop the network. 3. Estimate duration time of each activity. 4. Determine the networks critical path.

Project Selection and Management

CPM/PERT Symbols
21

Circle. Continuous arrow. Dotted arrow. Circle with divisions.

CPM/PERT symbols: (a) circle; (b) continuous arrow; (c) dotted arrow; and (d) circle with divisions.
Project Selection and Management

Assume that the network diagram of a research and development project


22

A network with given activity duration times along with determined earliest and latest event times. Project Selection and Management

CPM Advantages and Disadvantages


23

Some of the advantages of the CPM are as follows :


It is useful to show interrelationship in work flow. It is useful in cost control and cost saving. It is useful to determine project duration systematically. It is useful to monitor project progress effectively. It is useful to avoid duplications and omissions.

It is useful to improve communication and understanding.


It is useful to determine the need for labor and resources in advance. It is useful to identify critical work activities for completing the project on time.

By contrast, some of the disadvantages of the CPM are high cost, time consumption, poor time-estimate provision, and a bias to use pessimistic time estimates.

Project Selection and Management

Project Management Benefits


24

It identifies a methodology for tradeoff analysis and time limits for scheduling. It minimizes the need for continuous reporting and improves the estimating capability for potential planning. It identifies functional responsibilities for ensuring that all activities are accounted for, irrespective of manpower turnover. It identifies problems early so that corrective measures may follow. It can measure accomplishments against plans.

Project Selection and Management

Obstacles to Achieve Benefits


25

The project management benefits can only be achieved by overcoming obstacles such as project complexity and risks, changes in technology, for- ward planning and pricing, special needs of customers, and organizational restructuring

Project Selection and Management

Project Management Failure Factors


26

Failure to inform employees about the workings of project management; Failure to explain the effect of the project management organiza- tional structure on the wage/salary administration program; Failure to convince employees that executives completely support the change; Failure of executives to choose appropriate projects and project managers for the first few times and projects; The project management was not needed.

Project Selection and Management

References
27

[1] [2] [3] [4] [5] [6]

Cleland, D. I., Project Management, New York: McGraw-Hill, 1994. Gaddis, P. O., The Project Manager, Harvard Business Review, MayJune 1959, pp. 5560. Meredith, J. R., and S. J. Mantel, Project Management, New York: John Wiley and Sons, 1995. Wearne, S. H., Control of Engineering Projects, London: Edward Arnold Publishers, 1974. Banki, I. S., Dictionary of Administration and Management, Los Angeles, CA: Systems Research Institute, 1981. Thamhain, H. J., Engineering Management, New York: John Wiley and Sons, 1992.

[7] Brochure No. 7, Project Management Institute, Drexel Hill, PA. [8] Liberatore, M. I., and G. I. Titus, The Practice of Management Science in R and D Project Management, Management Science, August 1983, pp. 7074. [9] Gee, R. E., A Survey of Current Project Selection Practices, Research Management, Vol. 14, No. 5, 1971, pp. 3845. [10] Thomas, H., Some Evidence on the Accuracy of Forecasts in R and D Projects, R and D Management, Vol. 1, No. 2, 1971, pp. 5569. [11] Shannon, R. E., Engineering Management, New York: John Wiley and Sons, 1980. [12] Souder, W. E., Utility and Perceived Acceptability of R and D Project Selection Mod- els, Management Science, August 1973, pp. 8994. [13] Dhillon, B. S., Engineering Management, Lancaster, PA: Technomic Publishing Com- pany, 1987. [14] Cetron, M. J., and J. Martino, The Selection of R and D Program Content: Survey of Quantitative Methods, IEEE Trans. on Engineering Management, Vol. 14, 1967, pp. 413. [15] Clarke, T. E., Decision-Making in Technologically Based Organizations: A Literature Survey of Present Practice, IEEE Trans. on Engineering Management, Vol. 21, 1974, pp. 923. [16] Baker, N. R., and W. J. Pound, R and D Project Selection: Where We Stand, IEEE Trans. on Engineering Management, Vol. 11, 1964, pp. 124134. [17] Kasner, E., Essentials of Engineering Economics, New York: McGraw-Hill, 1979. [18] Baker, N. R., R and D Project Selection Models: An Assessment, IEEE Trans. On Engineering Management, November 1974, pp. 6165. [19] Souder, W. E., Comparative Analysis of R and D Investment Models, AIIE Transac- tions, April 1972, pp. 2026. [20] Disman, S., Selecting R and D Projects for Profit, Chemical Engineering, December 1962, pp. 8790. [21] Mottley, C. M., and R. D. Newton, The Selection of Projects for Industrial Research, Operations Research, 1959, pp. 740751. [22] Murdick, R. G., and E. W. Karger, The Shoestring Approach to Rating New Prod- ucts, Machine Design, January 1973, pp. 8689. [23] Seiler, R. E., Improving the Effectiveness of Research and Development, New York: McGraw-Hill, 1975. [24] Sobelman, S. A., Modern Dynamic Approach to Product Development, Dover, NJ: Pica- tinny Arsena, 1958. [25] Martin, C. C., Project Management: How to Make It Work, New York: AMACOM, 1976. [26] Kerzner, H., Project Management: A Systems Approach to Planning, Scheduling, and Con- trolling, New York: Van Nostrand Reinhold, 1992. [27] Riggs, J. L., and M. S. Inoue, Introduction to Operations Research and Management Sci- ence: A General Systems Approach, New York: McGraw-Hill, 1975. [28] Chase, R. B., and N. J. Aquilano, Production and Operations Management: A Life Cycle Approach, Chicago, IL: Irwin, 1981. [29] Clark, C. E., The PERT Model for the Distribution of an Activity Time, Operations Research, Vol. 10, 1962, pp. 405406. [30] Lomax, P. A., Network Analysis: Application to the Building Industry, London: The Eng- lish Universities Press Limited, 1969.

Project Selection and Management

28

THANK YOU!!!