You are on page 1of 25

WELCOME

FIELD TRAINING REPORT

Presented by,
Mr. Nirag B. Parmar.
B.E.Civil,
Roll No. 142
2

INTRODUCTION
The name of the firm in which I completed my field training
is SHP Properties Pvt Ltd, Meerabhakti Residential.
I visited the office at Mirabhakti, 1319/1, A Ward, Meera
bag Rankala, Tal: Karveer, Dist: Kolhapur. Developer gave
me permission to get basic knowledge of building
construction.
I selected a site SHP Properties Pvt Ltd, Meerabhakti
Residential. Main purpose to select this site is that the site
is started earlier, and work of foundation is started.
So, due to the training I could get the basic knowledge of
construction work.

SITE DETAILS:

Name of Project:
Meerabhakti Residential.

Name of Owner:
Mr.Shankar Patil.

Address:
Mirabhakti, 1319/1, A Ward, Meera bag Rankala..

Project Manager:
Mr.Sanjay More.

Name of Architect:
Mr. Rahul Durgule.

Electrical consultant:
Mr.UpendraDeuskar.

Structural Designer:
Mr. Pranav Kulkarni.

Name of Contractor:
Mr.AvinashAnekar.

Name of site Engineer:


Mr. Vijay Patil.

Total plot area:


42000sq.ft
A project of total 207 Flats and containing 2 wings A Wing & B Wing.
A Wing - 110 Flats
B Wing - 97Flats

PROJECT DETAILS

PLOT AREA42000 Sq. Ft.


TYPE OF BUILDINGR.C.C. Framed
Structure
DEPTH OF FOUNDATION6 m below Ground Level
TYPE OF FOUNDATIONSpread, Footing
FLOOR INCLUDEDBasement Parking
Eleven floor apartment

SPECIFICTION OF MATERIALS AND


EQUIPMENTS
CEMENTOrdinary Portland Cement (Grade 43, Ultra Tech)
STEEL-

Tor Steel ; Fe 500 (8mm, 10mm, 12mm, 16mm,

20mm)
CONCRETE

MIX-

SANDAGGREGATEMATERIAL

M20 Grade
Natural Sand, Artificial Sand.
Crushed Agg, Medium Agg.

USED FOR FORMWORK-

Timber Formwork and

Steel
Spans
EQUIPMENT USED- Diesel Vibretor, Backhoe, Tractor, Cutter
etc.

NOTES
RELATED
TO DESIGN OF
Data
for mix
for slab & beam:
CONCRETE
MIX:mix concrete
A.
Type of mix- Design
B.
Grade designation- M20
C.
Type of cement- 43 Grade ordinary Portland Cement
D. Maximum size of aggregate- 20mm(694 kg) &
10mm(440 kg)
E.
Course sand 458kg
F.
River sand - 458kg
G. Admixture- 3.06kg
H.
Water 160 kg
I.
Min.cement content as per IS 456-2000 for M20320kg/m^3
J.
Maximum temp. of the concrete at time of placing- 30
degc-32 degc
K.
Degree of quality control- Concrete with weigh batching
& good supervision
7

DATA FOR MIX FOR COLUMN:

Type of mix- Design mix concrete

Grade designation- M15

Type of cement- 43 Grade ordinary Portland Cement

Crushed aggregate 4 bucket

Medium aggregate 4 bucket

Course sand 2 bucket

River sand 2 bucket

CONSTRUCTION PROCESS ON SITE

1. Site cleaning
2. Excavation of foundation
3. Locating column centre on ground by
TTS
4. P.C.C. on ground
5. Locating column centre on P.C.C. by
TTS
6. Fixing steel on P.C.C.
7. Shuttering of footing
8. Casting of footing
9

TOTAL CONSTRUCTION PROGRESS-

Construction of foundation- Pile Foundation

Pile Excavated
of pile

Pile Excavated

Excavation

Excavation of pile

10

DETAILS OF PILE

Type of soil- Black cotton soil


Type of Pile foundation- Friction Pile
Diameter of Pile- 530mm
Depth of Pile- 4m to 4.5m
Friction piles are those they do not reach the hard stratum.
These piles transfer the load through skin friction between the
embedded surface of the pile and the surrounding soil. Friction
piles are used when a hard stratum does not exist at a
reasonable depth.

11

Pouring of concrete in pile

Reinforcement of pile
12

PILE CAP- THEY USING THE TWO TYPES OF PILE CAP


1. RECTANGLE
2. TRAPEZOIDAL

Rectangle type
Trapezoidal
type

13

DETAILS OF CAP

Size of cap 2.5*2.0*0.9


10mm ,16mm & 20mm steel are used for pile
cap.
Column size 300*600mm.
In rectangle type total two piles are
driven. Two piles are driven in two corners as
shown above fig & In trapezoidal type total
three piles are driven. Two piles are driven in
two corners & one is driven in middle one as
shown above fig.
14

Actual site

15

Reinforcement of slab

Consult wiring
16

Pouring of Concrete with RMC


(Total Quantity of slab is 225 meter cube)

Using of Vibrator for proper


compaction

17

Starter of Column(depth 100mm) Starter may be defined as base


structure
before casting of column to keep column in fixed position & to
erect formwork.
.
18

Extending the steel in column with help of lapping of steel bar for making column.
Lapping is done about 1 m long with help of cutting at every 75mm distance.

19

Shuttering Of column

Pouring of concrete in column

20

Drum mixing for making

concrete with volume batching

Start up of beam bottom for making the


next
slab formwork
21

Reinforcement of
lift(2.5*2.0m)

Reinforcement of staircase
22

HONEY COMBING

After concreting is done honey combing occurred because of there is no


using of vibrator& tamping is not done properly As you seen in below
fig.
This type of concreting is not good for structure because it cant take
the proper load & therefore this particular item is demolished. After
demolishing the new concreting is done with the help of RMC & proper
vibrating & tamping is also done.

23

CONCLUSION
It was the great experience about actual site work taken during
this session of vacation. The training period that I spent to
see the construction work will definitely give me invaluable
experience and knowledge for shaping my future carrier. This
training period gave me an actual idea about site work.

The important that we learned in this field training:


Project execution
Time management
Material management
Decision making
Communication
Daily muster reports & its importance
Safety management & precautions
Financial aspects
Actual site works

24

THANK YOU

25