You are on page 1of 34

Managing Delay and Project

Learning to Improve Project


Quality
----Critical Points for Success in Construction

From Quality Management to Project Learning

----Critical Points for Success in Construction

Delay Issues in the International Construction Industry


A great deal of information concerned with project delay and
overruns may be found in the literature as shown in Table 1. It
is important to predict and identify the problems in the early
stages of construction and diagnose the cause to find and
implement the most appropriate and economical solutions
(Abdul-Rahman & Berawi, 2002b).

Source: Abdul-Rahman (2008), Project International 2008, Kuala Lumpur.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry


Delay Issues in the International Construction Industry
Table 1 Information Concerned with Project Delay
Country

Researcher

Year

Nigeria

a)Aibinu & Jagboro

2002

facing a major criticism due to the growing rate of


delays in project delivery
projects are accelerated or duration extended beyond
the scheduled completion date

a)Odeyinka & Yusif

1997

seven out of ten projects surveyed suffered delays in


their execution

a)Ajanlekoko

1987

performance of the construction industry in terms of


time was poor

a) Al-Khalil & Al-Ghafly

1999

government authorities face a serious problem of


lengthy delays in public projects

b) Al-Ghafly

1995

according to the contractors, 37% of all projects in


Saudi Arabia were subject to delay
an average time overrun of 39% of the original project
duration

c) Assaf & Al-Hejji

2006

only 30% of construction projects were completed within


the scheduled completion dates
average time overrun was between 10% and 30%

d) Al-Sultan

1989

surveyed time performance of different type of public


projects
70% of public projects experienced time overrun

e) Zain Al-Abedien

1983

70% of the projects undertaken by the Ministry of


Housing and Public Works in Jeddah were subject to
delay

Saudi Arabia

Evidence of Delays

Continued on next page

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry


Delay Issues in the International Construction Industry
Table 1 Information Concerned with Project Delay
continued
Country

Researcher

Year

Australia

a) Bromilow

1974

only one-eighth of building contracts were


completed within the scheduled completion dates
average times overrun exceeded 40%

Ghana

a) Frimpong et al.

2003

study on groundwater projects indicated that 33


out of a total of 47 projects completed between
1970 and 1999 were delayed while 38 projects
were overruns
75% of the projects exceeded the original
project schedule and cost whereas only 25%
were completed within the budget and on time

Thailand

a) Ogunlana & Promkuntong

1996

the boom in construction was unanticipated


many projects experienced delays and thereby
exceeded initial time and cost estimates

Singapore

a) Clough & Sears

1994

variations in drawings and contract documents


usually lead to a change in contract price or
contract schedule
construction projects may face variations that
could cause delay in the project completion time

Continued on next page

Evidence of Delays

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry


Delay Issues in the International Construction Industry
Table 1 Information Concerned with Project Delay
continued
Country

Researcher

Year

Evidence of Delays

Jordan

a) Al-Moumani

2000

delays occurred in 106 out of 130 projects


surveyed
the time required to complete construction of
public projects is frequently greater than the time
specified in the contract

b) Battaineh

1999

evaluated the progress reports of 164 building


and 28 highway projects constructed during the
period 1996-1999
result indicate that delays are extensive: the
average ratio of actual completion time to the
planned contract duration is 160.5% for road
projects and 120.3% for building projects

c) Odeh & Battaineh

2002

this problem is more evident in the traditional or


adversarial type of contracts in which the
contract is awarded to the lowest bidder

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry

4. Some Lessons Learned - Case Studies


4.1 Engineering Faculty Building
4.1.1 Project Description
The project comprises the construction and completion of a Tower and
a Laboratory Blocks. The type of contract used was design & build,
negotiated and lump sum contract.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry


4. Some Lessons Learned - Case Studies

4.1 Engineering Faculty Building


4.1.2 Summary of Findings
The project comprises the construction and completion of a Tower and
a Laboratory Blocks. The type of contract used was design & build,
negotiated and lump sum contract. The commissioning of the project
comprised of two phases; the main block was handed over first. When
the constructed building was fully handed over, the client has not got
the building plan approved, let alone the certificate of fitness due to
the contractors failure to meet the requirements of the local authority
(Abdul-Rahman, Berawi, et al., 2006).

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry

4. Some Lessons Learned - Case Studies

4.2 The Law Faculty Building


4.2.1 Project Description
The project comprises the construction and completion of Law Faculty
Building and a Library Block. Type of contract is lump sum contract
and open tender. In this project the contractor failed to finish within
the contract time. The contractor completed the sub-structure
without any delay but soon after his financial problems appeared
(Abdul-Rahman, Berawi, et al., 2006)

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry


4. Some Lessons Learned - Case Studies
4.2 The Law Faculty Building
4.2.2 Summary of Findings
The problems started when the end user began to change the scope of
project twice during construction of the project. The main contractors
top management did not contribute much in site meetings and were
not involved with the projects problem solving. The architect for the
project was of the opinion the main cause for delay was due to the
main contractors financial problem, poor management and
performance, and shortage of skilled workers. The client later realized
that the contractor was handling more than five projects at the same
time. Subsequently, the extra works requested have affected the
overall program and schedule probably due to cashflow problems
(Abdul-Rahman, Berawi, et al., 2006).

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry

4. Some Lessons Learned - Case Studies


4.3 Chemistry and Biochemistry Building, Faculty of Science
4.3.1 Project Description
The project consists of the construction of a four and a half-storey
reinforced concrete building for two departments. The site used for
the building was formerly a chemistry laboratory. The new building
consists mainly of laboratory rooms and lecturer rooms with the
office and main seminar rooms located at the ground floor.
Selective tendering was used and the consultants were
recommended by the Ministry of Finance.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of Delay Issues In The Malaysian Construction Industry

4. Some Lessons Learned - Case Studies


4.3 Chemistry and Biochemistry Building, Faculty of Science
4.3.2 Summary of Findings
The contractor encountered problem with the quality of civil and structural (C&S)
design. The effects of poor quality design are cracks on main beams - the
cracks on the first floor beams were detected during the completion of the
upper floors (roof beams, water tank levels and parapet walls). The cracking
on main beams was the major problems the contractor dealt with. Besides
that, there was delay due to minor problem in the initial construction stage
because the supplier of micro piles was too specific. Apart from this, services
bay for laboratory benches were not provided in the floor for ease of
maintenance. The head room (floor to ceiling height) was low compared to the
clients requirement due to poor coordination between the C&S and M&E
engineers. Furthermore, columns appear in the middle of some of the lecturers
rooms. The rectification works increased the time and cost of the project by 6
months and RM3million, respectively.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of a Successful Project by a Malaysia Contractor

4. An Example of a Successful Project by a Malaysian Contractor


-- Some Lessons Learned - Case Studies
4.4 The Bahrain International Circuit (BIC)
4.4.1 Project Description
The track was built on a 400 acre sandy plot of land in Sakhir, 19 miles
southwest of the island's capital, Manama. The site is between AlAreen Wild Life Park and the University of Bahrain. It is just 30
minutes from the Bahrain International Airport. The Bahrain
International Racing Circuit was built on 1.7 square kilometers area
of land.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of a Successful Project by a Malaysia Contractor


4. Some Lessons Learned - Case Studies
4.4 The Bahrain International Circuit (BIC)
4.4.2 Summary of Findings
WCT and its joint venture partner, Cebarco Bahrain (Cebarco), a local Bahrain
construction company in completed a prominent and demanding international
project the BIC project. To the surprise of many, the BIC project was completed
earlier than the original required completion date. The achievement of the joint
venture contractor to complete the project on time and according to the rigid
requirements of the F1 organizer has promoted the identity, image and reputation
of WCT and Cebarco not only in Bahrain but also in the surrounding region.
Through the joint venture company, WCT and Cebarco shared specific business
objectives for the BIC project by:
a) Maximizing the effectiveness of co-operation and mutual trust;
b) Developing a win-win culture;
c) Reducing the overall project cost, reducing the project time and ensuring the
utmost quality and safety;
d) Reducing the administrative cost;
e) Eliminating contractual conflict through less adversarial relationships; and
f) Reducing errors

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of a Successful Project by a Malaysia Contractor

4. Some Lessons Learned - Case Studies


4.4 The Bahrain International Circuit (BIC)
4.4.3 Design
Designed by German track specialist, Herman Tilke, the 70,000spectator track has made Bahrain the first country in the Middle
East to host a Formula One race. The architecture is based on
Arabian themes. The desert circuit is unique in the world of Formula
One and combines leading edge technology with fine examples of
Arabic architecture and iconic buildings such as the Sakhir Tower.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of a Successful Project by a Malaysia Contractor

4. Some Lessons Learned - Case Studies


4.4 The Bahrain International Circuit (BIC)
4.4.4 Factors for Successful Construction Project Performance
By instilling an efficient control mechanism in monitoring the project,
WCT was be able to monitor the progress of project according to the
predetermined plan and adapt suitably to the situation. However,
interrelated factors need to be present in order for a project
accomplishment.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of a Successful Project by a Malaysia Contractor


4. Some Lessons Learned - Case Studies
4.4 The Bahrain International Circuit (BIC)
4.4.4 Factors for Successful Construction Project Performance
continue
From the start of the BIC project, the Contractor has identified 9 factors
for successful construction performance:
a) Excellent teamwork between all parties
b) Experience of the project team and consultants
c) Good financial condition
d) Planning and control system
e) Realistic and definite set of goals
f) Communication throughout the project
g) Sufficient completion time
h) Clients characteristic
i) Project characteristic/nature

From Quality Management to Project Learning

----Critical Points for Success in Construction

Examples Of a Successful Project by a Malaysia Contractor

4. Some Lessons Learned - Case Studies


4.4 The Bahrain International Circuit (BIC)
4.4.5 Critical Factors for the Bahrain F1 Circuit
Whether it is a tangible or intangible return that the company or ventures
are looking for, all factors are often interrelated and their combination
leads to the success or failure of a joint venture.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay

Delay prevention and delay mitigation contribute the similar aims in


the construction, those are to minimize the loss, damages and
others negative impacts cause by delay events. To improve the
schedule performance in the future, the construction practitioners
need to understand, adapt and evolve in the knowledge-economy
age. By achieving it, a few aspects that need to take a deep
consideration by the industry, namely:
a) clients needs in future;
b) the risks and opportunities for the future; and
c) future directions to prevent and mitigate construction projects
delay.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay


Future Directions: Are We Measured Up To The New Challenges?
Principal Points in Developing Delay Mitigation Model
Figure 1 displays the principal points of developing delay mitigation model.
The principal points composed of management aspects, changes needs,
the overriding human factor and the Plan-Do-Check-Action (PDCA) cycle.
Based on these principals points a basic integrated delay mitigation model.
Cultural
change

Delay
management

PROJECT PROCESSES

Knowledge
management
Policy
change

Learning
management
Technical
change

Figure 1 Principles of a Delay Mitigation Model

From Quality Management to Project Learning

----Critical Points for Success in Construction

Development of a Basic Integrated Delay Mitigation Model


PRECONSTRUCTION
STAGE

START

CONSTRUCTION
STAGE

COMPLETION

Practise project management


Practise
project
management
techniques
and
tools
Integrate learning, knowledge
techniques
and
For example: tools
Integrate
learning,
knowledge
and delay
management
For
example:
ASAP approach;
and delay management
ASAP
approach;
Critical
path
method;
Implementing the
Critical
path
method;
Pareto analysis;
Implementing
the throughout
integrated management
approach
Pareto
analysis;
Work breakdown system;
integrated management
approach
throughout
the project period,
Work breakdown
system;
Project management
software
system
the project period,
Project management software system
Filtering the lesson learned
Filtering the lesson learned

TECHNIQUE
=
FORM & USE
COMPOSITE
KNOWLEDGE

Document filing system


Document filing system
Disseminate to project-related parties
Disseminate to project-related parties

Top of role played by organizations, projects and individual


ORGANISATION

INDIVIDUAL
COMMUNICATION

COMMUNICATION

PROJECT TEAM

Change the culture of late payment


Implement organizational change
Build up a cross-discipline cooperation
Cultivate knowledge sharing culture of bad and good practices at the project level
Eliminate them and us attitude
Establish a systematic individual time management
Commit to learn

Figure 2 Basic Integrated Delay Mitigation Models

From Quality Management to Project Learning

----Critical Points for Success in Construction

Development of a Basic Integrated Delay Mitigation Model

The integrated delay mitigation model shown in the previous


Figure (Figure 2) is generated based on the four (4) principal
points of developing a delay mitigation model as discussed in the
previous section.
At the bottom of the Figure 2, top of role and action to be played
by the organizations, project team and individual are specified to
mitigate the delay events.
In the model, the composite knowledge is the different bodies of
knowledge being combined to achieve the best outcome at any
given time a decision or action is done. A diagrammatic
representation of composite knowledge is shown next.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Development of a Basic Integrated Delay Mitigation Model


Project
management
principles

Professional
ethnics

Project
management
techniques

Etc.

Financial
and risk
management

Decision
making
models

Analytical
thinking

Time
management
techniques

COMPOSITE
KNOWLEDGE

Communication skill

Human
resource

Technical
know how

Negotiation
skills

Team
building and
teamwork

Technical
know who

Establish
core values
in projects

Figure 3 Composite Knowledge

Creativity

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay


Conceptual Framework of the Delay Mitigation Model Using a
Project Learning Approach
Drawing on the results and analysis of the four-stages data collection
discussed on the above sections, a conceptual based delay mitigation
model as shown in Figure 3. The delay mitigation model is designed
specifically for the use in construction projects and with an intention to
deal with major delay factors caused by lack of knowledge and poor
management of lessons learned.

Peter. M. Senge
The founder of organizational learning theory

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay


Phase 1:
Knowledge identification

Phase 2:
Knowledge sharing, creation,
and integration

Phase 3:
Knowledge exploitation

Phase 4:
Knowledge storage

Implement action and


informal project learning
Quantify project
activities into several
milestones

Formal project learning


process

Identify time goal for


each milestones
Identify critical or high
potential types of delay
for each activity
Explore activity
knowledge

No

Comprehensive
consideration?
Yes
Documentation and
making decision

Any potential
or delay
Yes
events?
No
Continue implement
action and informal
project learning
Lesson learned feedback
loop
No

Filter knowledge and


lesson learned
Compile knowledge and
lesson learned
Store knowledge and
lesson learned

End of the
project?
Yes
Go to Phase 4

Project stages Preconstruction and construction stage


Enablers

Continuous individual commitment, continuous top


management commitment, continuous inductive
environment, continuous human network, continuous
open communication, teamwork, equity

Barriers

Poor commitment, adversarial relationship,


individualism, discrimination

Construction stage

Near the project completion stage

Continuous individual
commitment, continuous top
management commitment,
continuous inductive environment,
continuous human network,
continuous open communication,
Poor commitment, poor teamwork
active and opportune feedback
and lack of observance

Continuous individual
commitment, continuous top
management commitment,
openness
Discontinuous commitment,
conceal

Figure 3 Delay Mitigation Model Using Project Learning Approach

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay

Processes of Delay Mitigation Model


The proposed model consists of four (4) main phases. Each phase
contains enablers and barriers of project learning which have been
accumulated and gathered from the data collection. The four phases
are:
Phase 1: Knowledge identification
Phase 2: Knowledge sharing, creation and integration
Phase 3: Knowledge exploitation
Phase 4: Knowledge storage

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay


What Next?
1. Model development

1.1 Comparison to Some Existing Developed Models


Table 2 shows the focus areas of knowledge management between the proposed model and existing
developed models.
Knowledge management
Authors
Table 2 Comparison of the Proposed Model to Others Existing Developed Models
areas
Fong
Kamara
Robinson
Tserng and Lin (2004);
(2003)
et al. (2003)
et al. (2004)
Lin et al. (2005)

The present
proposed
model

Knowledge gap

Knowledge goal

Know. identification

Knowledge creation

Knowledge sharing

Knowledge linkage

Knowledge filtering

Knowledge storage

Knowledge retrieve

Knowledge dissemination

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay


What Next?
1. Model development

1.2 Theoretical Perspectives of the Developed Model


The theoretical perspectives of the developed model are based on the
integration of team learning theory (including individual learning reviews,
functional learning reviews, whole team learning review and
communication of learning) from Barker and Neailey (1999) and learning
process theory (including focus, environment and techniques) from
Buckler (1996). Based on these theories, seven (7) aspects were taken
into account in the development of the proposed model as follow:
(i) learning goal setting;
(ii) storytelling;
(iii) brainstorming;
(iv) reflection;
(v) feedback;
(vi) knowledge exchange protocol; and
(vii) web-based tools.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay


What Next?
2. A Proposed Continuous Project Learning Model
Figure 4 represents the eight (8) phases of the proposed continuous project
learning model during pre-construction stage.

1. Identify a subject
matter
2. Identify learning
goals

8. Lesson learned
linkage

7. Knowledge
dissemination, retrieve
and update

3. Identify knowledge
source

6. Knowledge filter and


storage

4. Knowledge sharing

process
5. Knowledge
application

Figure 4 Continuous Project Learning Model

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay

A Discussion on the Proposed Project Learning Model


Results from a survey illustrate that the proposed model tends to be more
capable to enhance learning, knowledge sharing and individual
knowledge seeking in the construction industry. Thus, it is expected that
the application of the proposed model during the pre-construction stage
is capable to enhance the value of construction projects in terms of time,
cost or quality.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Future Prospect for Mitigation of Delay

Discussion of the Proposed Project Learning Model


The strength of the proposed model is that it focuses on project
knowledge and continuous collective learning in which both elements
are critical in enhancing the value of the construction projects. While,
the potential shortcomings of this model are that it is built on an
unproved premise, the model seems to be suitable for moderate large
and complex construction projects in enhancing the value of
construction.

From Quality Management to Project Learning

----Critical Points for Success in Construction

A summary of Critical Points for Success in Construction


After having presented a variety of sub-themes in this lecture, let me try to
summarise the main themes for the benefit of fellow audience. The main
issues that need to be addressed by policy makers and practitioners to
succeed in construction include:
1. The need to re-look at the incapacities of existing quality
management approaches and probably the need for a radical
change in how quality is managed in its totality in construction.
2. Understanding the implications of poor quality in terms of quality
cost and the need for more proactive prevention efforts.
3. The different needs in managing quality at the different stage of
construction, with a focus on the pre-design and the
commissioning stages.
4. Appreciating the impact of quality failures on the society and the
construction industry.
5. Understanding the benefits of and applying basic knowledge
management in construction.
6. Appreciating the importance of institutionalised project learning.
7. Going back to basics by observing strictly the Good Project
Management Practices and the need to develop high calibre
construction work force.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Conclusions

The title of this lecture is from quality management to project learning


critical points for success in construction. The first part of the lecture
advocates the use of quality management throughout construction.
The concept of quality cost and the importance of tracking quality cost
of failure are then highlighted. Results of studies on quality
management in design and build projects and during the
commissioning stage of projects presented show the importance of
quality management and the negative impacts of failure in quality.
Case studies that looked into the factors project failures and success
were presented to provide an insight into the critical issues that need
to be recognized, learned and put to practice.

From Quality Management to Project Learning

----Critical Points for Success in Construction

Conclusions

Certain futuristic demands that can influence the success of construction


firms were also presented. One of the most important criteria for
success is the ability of construction firms to meet stricter requirements
from the clients and end-users. Beginning with studies into how
knowledge management can improve project performance, the author
eventually recommends the extensive use of knowledge management in
construction projects through a project learning model. Although the
model is more appropriate for large construction outfits, smaller
companies can easily apply the concepts to improve their performance
in construction. Project learning remains to be a mere knowledge
management tool and cannot increase productivity and improve quality
unless the knowledge is actually put to practice with sincerity and
commitment just like if quality management is to be successful.

Thank You

You might also like