REACTIVE POWER

COMPENSATION
Presented by :
Ari Nugraheni
Chairy Wahyu Winanti

OUTLINE
1

Background

Problem

Data

Data Analysis

Conclusion and
Suggestion

BACKGROUND
Human Electric
Need
Raising

Fossil Energy
Availability
Decreasing

Optimizing Diesel Engine


Generator Efficiency

Reactive
Power
Compensation

PROBLEM
Base 1
Substation

Base 2
Substation

With PF
about 0.9

With PF
about 0.9

Bugis 1
Substation
With PF
minimum
0.7557

Total E&P
Indonesie
Exclude
Sepinggan
Substation

Bugis 2
Substation
With PF
minimum
0.7307

nb : standard minimal PF PLN is 0.85 to avoid kVARh penalty

MEASUREMENT

Fluke 43B
Single Phase Power Quality
Analyzer

DATA
Gunung Bugis Housing Active Power on Off Day in
Bugis 1 SS
308.76 kW
09:59:14

68.82 kW
01:52:50

ave = 173.77 kW

Data Taken On July, 9 10


2010
6

DATA
Gunung Bugis Housing Reactive Power on Off Day
in Bugis 1 SS
208.32 kVAR
13:06:58

ave = 125.07
kVAR

Data Taken On July, 9 -10


2010
7-

DATA
Studio Active Power on Off Day in Bugis 1
Substation

39.098 kW
05:45:04

Data Taken On July, 10 11


2010
8

DATA
Studio Reactive Power on Off Day in Bugis 1
Substation

Data Taken On July, 10 11


2010
9

DATA
GUNUNG BUGIS HOUSING, BUGIS 1
SUBSTATION
Day Status
Max Active Power (kW)
Min Active Power (kW)
Max Reactive Power (kVAR)
Min Reactive Power (kVAR)

Off Day
308.76
68.82
208.32
65.2

Working Day
282.72
85.56
193.44
70.68

STUDIO, R-PHASE, BUGIS 1 SUBSTATION


Day Status

10

Off Day

Working Day

Max Active Power (kW)

74.79

75.16

Min Active Power (kW)

39.098

40.82

Max Reactive Power (kVAR)

28.996

28.34

Min Reactive Power (kVAR)

14.33

13.76

DATA
Gunung Karang Housing Active Power on Working Day
in Bugis 2 SS

Data Taken On July, 19 20 2010

11

DATA

Gunung Karang Housing Reactive Power on Working Day i


Bugis 2 SS

Data Taken On July, 19 20 2010

12

DATA ANALYZE
For each minimum Power Factor
Location

Active Power (kW)

Reactive Power (kVAR)

Apparent Power (kVA)

Bugis 1
Substation

153.73

133.20

203.40

Bugis 2
Substation

152.67

142.61

208.92

Where, P
Q
S
PF
13

=
=
=
=

Active Power (W)


Reactive Power (VAR)
Apparent Power (VA)
Power Factor

DATA ANALYZE
Power Factor in Bugis 1 Substation

14

DATA ANALYZE
Power Factor in Bugis 2 Substation

0.9051
20:43:36

15

DATA ANALYZE
Reactive Power Compensation Bugis 1 Substation
PF = 0.7557
S = 203.40 kVA
P = 153.72 kW
Q = 133.20 kVAR
Its power factor is wanted to be improved becoming 0.95 so :
PF = 0.95
P = S x PF = 203.40 x 0.95 = 193.23 kW
Q1 =

Compensation Q = Q Q1
= 133.20 63.51 =

16

69.69 kVAR

DATA ANALYZE
Reactive Power Compensation Bugis 2 Substation
PF = 0.7307
S = 208.92 kVA
P = 152.67 kW
Q = 142.61 kVAR
Its power factor is wanted to be improved becoming 0.95 so :
PF = 0.95
P = S x PF = 0.95 x 208.92 = 198.47 kW
Q2 =

Compensation Q = Q Q 2
=142.61 65.24 =

17

77.37 kVAR

BENEFIT

18

BENEFIT

19

Spare Power Capacity

20

BENEFIT

21

CONCLUSION

22

SUGGESTION
By installing 69.69 kVAR in Bugis 1 Substation
and 77.37 kVAR Bugis 2 Substation, we will have 1199.9
kWh spare power capacities and some technical
benefits. But, it is not profitable enough economically.
Therefore, needs further study to make sure how
profitable it is.

23 - Reference, date, place

Cost per kWh for Sepinggan


Power House

Component

Percentage
(%)

(USD)

Variable Operational and Maintenance

80.124,83

15,58

Fixed Operational and Maintenance

28.408,71

5,52

Fuel Consumption

405.861,92

Total

514.395,46

78,90
100

1 USD = Rp 9.045,00 (per July, 23th 2010)

PLN Base Rate for R3 Class (3500 kVA - 5500 kVA) Household Customer per
July, 1 2010 per kWh
Cost / kWh for Sepinggan Power House

25

Rupiahs

Rp

Rp

891,00

2.440,77

USD

Comparison

0,0985

0,2698

2,74

Power Utility

27

28 - Reference, date, place