Professional Documents
Culture Documents
RELEVANT CONDITIONS OF
CONTRACT
If, however, during the execution of the Works the Contractor encounters
physical obstructions or physical conditions, other than climatic conditions
on the Site, which obstructions or conditions were, in his opinion, not
foreseeable by an experienced contractor, the Contractor shall forthwith
give notice thereof to the Engineer, with a copy to the Employer. On receipt
of such notice, the Engineer shall, if in his opinion such obstructions or
conditions could not have been reasonably foreseen by an experienced
contractor, after due consultation with the Employer and the Contractor,
determine:
(a) any extension of time to which the Contractor is entitled under Clause
44, and
(b) the amount of any costs which may have been incurred by the
Contractor by reason of such obstructions or conditions having been
encountered, which shall be added to the Contract Price,
and shall notify the Contractor accordingly, with a copy to the Employer.
Such determination shall take account of any instruction which the Engineer
may issue to the Contractor in connection therewith, and any proper and
reasonable measures acceptable to the Engineer which the Contractor may
take in the absence of specific instructions from the Engineers.
27.1 Fossils
All fossils, coins, articles of value or antiquity and structures and other
remains or things of geological or archaeological interest discovered on
the Site shall, as between the Employer and the Contractor, be deemed
to be the absolute property of the Employer. The Contractor shall take
reasonable precautions to prevent his workmen or any other persons
from removing or damaging any such article or thing and shall,
immediately upon discovery thereof and before removal, acquaint the
Engineer of such discovery and carry out the Engineer's instructions for
dealing with the same. If, by reason of such instructions, the Contractor
suffers delay and/or incurs costs then the Engineer shall, after due
consultation with the Employer and the Contractor, determine:
(a) any extension of time to which the Contractor is entitled under Clause
44, and
(b) the amount of such costs, which shall be added to the Contract Price,
and shall notify the Contractor accordingly, with a copy to the Employer.
Where, pursuant to Sub-Clause 36.4, this SubClause applies the Engineer shall, after due
consultation with the Employer and the
Contractor, determine:
(a) any extension of time to which the Contractor
is entitled under Clause 44, and
(b) the amount of such costs, which shall be
added to the Contract Price,
and shall notify the Contractor accordingly, with
a copy to the Employer.
Without prejudice to the Contractor's entitlement to interest under SubClause 60.10 and to terminate under Sub-Clause 69.1, the Contractor
may, if the Employer fails to pay the Contractor the amount due under
any certificate of the Engineer within 28 days after the expiry of the time
stated in Sub-Clause 60.10 within which payment is to be made, subject
to any deduction that the Employer is entitled to make under the
Contract, after giving 28 days' prior notice to the Employer, with a copy to
the Engineer, suspend work or reduce the rate of work.
If the Contractor suspends work or reduces the rate of work in accordance
with the provisions of this Sub-Clause and thereby suffers delay or incurs
cost the Engineer shall, after due consultation with the Employer and the
Contractor, determine
(a) any extension of time to which the Contractor is entitled under Clause
44, and
(b) the amount of such costs, which shall be added to the Contract Price,
and shall notify the Contractor accordingly, with a copy to the Employer.
20.4
Employer's Risks