You are on page 1of 81

SAFE RIGGING PRACTICE

KJP ON TANGGUH-LNG

JAN. 2006
OVERVIEW
DEFINE OF RIGGING
RESPONSIBILITIES
DOCUMENTATION
TYPE OF RIGGING
RIGGING EQUIPMENT
PREPARATION ON SITE
INSPECTION REQUIREMENT
LIMITATION & ENVIRONMENT
DEFINE OF RIGGING
RIGGING IS A WAY OF MOVING
OF HEAVY AND BIG SIZE
MATERIALS AND FACILITIES TO
APPOINTED PLACE SAFELY
RESPONSIBILITIES
Manager and Area Manager
- Responsible for the implementation of procedure
- Responsible to have KJP and subcontractors
hoisting and maintained in accordance with
procedure.
- Function as the coordinator of rigging work
necessary to perform hoisting and ensure inspection
and test of hardware process has been completed
prior to use of hardware.
- Designed for implementing the requirements and
adherence to this procedure.
RESPONSIBILITIES
Superintendent/Subcontractor

- Will select a qualified competent person to perform


inspections.
- Ensure all rigging hardware in the area is properly
tagged and inspected prior to use.
- Retain and filing of rigging hardware inspection
reports.
- Will determine whether additional testing is required
prior to rigging operations or not.
- Assign qualified rigging engineer.
RESPONSIBILITIES
Person In Charge (PIC)
- Shallbe a qualified competent person who rigger
and be familiar to the lifting and rigging for
responsible.
- Inspection and testing of lifting and rigging
hardware.
- Delivery and report of inspection records to
Superintendent for filing.
- When leasing or purchasing the rigging hardware,
ensure to request that certificate of Compliance and
document of proof test.
- Ensure that a postponed periodic inspection is
documented.
RESPONSIBILITIES
Subcontractor Requirement
- Ifsubcontractors choose to use their own inspection
program, it shall be submitted to KJP Hoisting and
Rigging Manager for review and approval.
- Subcontractor shall use KJPs Hoisting and Rigging
Hardware Inspection and Testing procedure, in absence
of their own procedure.
- Any non-off the shelf, below the hook lifting device
(spreader beam, load equalizer beam, etc.) rigging
apparatus or component shall be reviewed and
approved by KJP prior to use. Component shall have
certificate of compliance and proof tests, prior to using.
- Subcontractors are subject to visual on-site hoisting
and rigging hardware/device inspections by KJP
organization.
Rigging and Lifting Procedure
Before a CRITICAL or PRE-ENGINEERED LIFT
is made the Critical Lift Evaluation Form
must be prepared.
A procedure must be developed that includes
the activities bellow ;
- Calculation and analysis data,
- Elevation view drawings,
- Plan view drawings
- Checklist for lift planning.
- Access road for load and cranes.
Rigging and Lifting Procedure
CRETICAL LIFT;
Critical Lift shall be prepared and approved
by KJP as specified S-900-1242-55, HSE
standard, Craneage, Rigging and Lifting

- All lift of 50 tons or more,


- Any lift made over critical equipment,
regardless of the weight,
- For multi-crane lifts.
Rigging and Lifting Procedure
CRETICAL LIFT ;
(Normal determining factor)
- The load being lifted has a seated single
surface area greater than 40 M 2.
- Handle and lift of radioactive/hazardous
materials.
- Load is grater than 85% of mobile crane rated
capacity.
- Load is grater than 90% of rated capacity
of fixed crane.
Rigging and Lifting Procedure

PRE-ENGINEERED LIFT;
A repetitive or production-type lifting
operation using specialized lifting fixtures
and tooling, supported by analysis,
sketches, and approved by KJP
Rigging and Lifting Procedure

PRE-ENGINEERED LIFT;
A repetitive or production-type lifting
operation using specialized lifting fixtures
and tooling, supported by analysis,
sketches, and approved by KJP
Rigging and Lifting Procedure
CRITICAL LIFT EVALUATION FORM(CLEF)
REQUESTED COMPANY NAME: _
PERSON REQUESTING THE LIFT
Dept./Div. Print Name Date _
PERSON IN CHARGE (PIC) Print Name : _
DETERMINING FACTOR FOR CRITICAL LIFT
____ Load is greater than 85% of mobile crane rated capacity,
Load is greater than 90% of rated fixed crane capacity,
Load is greater than 50 tons and more.
____ Two or more cranes/booms are required or special hoisting/rigging equipment will be used.
____ Handling and Lifting of radioactive/hazardous materials,
____ Seated surface area grater than 40 M2
OPERATING EQUIPMENT
Type of Crane Manufacturer _
Model No. Serial No. _
Manufacturer Restriction for WIND SPEED m/hr
(No lifts at wind speeds of 9 m/sec or greater)
Crane Equipped with Anemometer
Copies of Latest Annual Inspection shall be included bellow;
- Latest Calibration Date of Instruments
- Operator Licensed for Equipment
- Expiration Date
Rigging and Lifting Procedure
DESCRIPTION OF ITEMS TO BE LIFTED _
HOW WEIGHT OF OBJECT OBTAINED
A. Certified Weight Scale _________________ Ticket # _____________________
B. Calculated Independently by More than One Source
1. Source _____________________ Weight________________________
2. Source _____________________ Weight _______________________
C. If lift is an existing item (being removed or demolished), the weight must be recalculated, taking into account all
modifications, including internal, as well as an Allowance for Scale, Sediment, Sludge, and Insulation.
Calculation Work Sheets shall be included in the LIFT PLAN and have a PE stamp or be signed off by a
QUALIFIED PERSON. (When weights are calculated, a 10% tolerance margin shall be added. This value
may be increased at the discretion of the Lifting Safety Committee).
D. Shipping Manifests Weight ____ _____ Manufacturer Data Weight ____ ______
CENTER OF GRAVITY (CG)
CG will be marked onto load, and a drawing included showing how it was determined.
DESCRIPTION & WEIGHT OF ALL RIGGING EQUIPMENT & CRANE ATTACHMENTS
Type of slings Rated Capacity Weight
Shackles Rated Capacity Weight _
Load Block/Jib Rated Capacity Weight
Hoist Wire Rated Capacity Weight _
Spreader Beams/Equalizer Beams on Below the Hook Lifting Devices
Rated Capacity Weight _
WEIGHT OF OBJECT, RIGGING EQUIPMENT, & CRANE ATTACHMENTS

Source _ ___________________Total Weight _________________________


Rigging and Lifting Procedure
EQUIPMENT AND LIFT RELATIONSHIP
A. Maximum Operating Radius: ________________________________________ ____
B. Planned Operating Radius: ______________________________________ ______
C. Allowable load at maximum lift radius anticipated (from Load Chart): _____
D. Ratio of Lift to Allowable Load: ____________________________________ _______
E. Clearance between Boom & Lift:__________________________________ ________
F. Clearance to Surrounding ___________________________________ ___________
Facilities/Utilities: _______________________________ ____________
G. Clear Path for Load Movement:________________________________ ___________
STABILITY OF GROUND AREA
A. Soil Bearing Capacity: Source:_________________ ___
B. Mats Required: Size & Number: __________
C. Underground Utilities Location: _____________________________ ______________
D. Ratio of Soil Bearing Capacity to Actual: _________________________ __________
LIFTING OPERATION
A detailed drawing, to scale, MUST be included showing the Set-up Area, Lifting Area, Load Placement
Area, and Sling Attachment Points w/sling angle reduction factor.
INSPECTION OF CONTRACTORS EQUIPMENT
All contractors' Lifting and Rigging Equipment must be inspected before being brought onto the KJP Site by
KJP HSES Department : Contact: _
LIFT APPROVAL SIGNATURES
Professional Engineer/ Qualified Person: _
Person in Charge (PIC) (Critical Lift): _
Responsible Manager or Designee: _
Lifting Safety Committee Recommendation: Approve: Disapprove: _
DETERMINING OF THE WEIGHT

Shipping Document
Catalogue & Manufacturers Data
Label on Object
Design Drawing
Calculation
Weighing and Others
MEASURING OBJECTS
CONVENTIONAL METHOD
USE WHAT YOU HAVE?
- Span of hand extended
- Span of open arms
- Height
- Pace of step
- Bill
- Cigarette case etc.
TYPE OF MEASUREMENT
WEIGHING of LOAD
Weight of Materials (Specific Gravity)
- Water : 1,000 Kg/Cubic Meter
- Ice : 920 Kg/Cubic Meter
- Steel (Rolled) : 7,850 Kg/CBM
- Reinforced Concrete : 2,400 Kg/CBM
- Sand (dried) : 1,600 Kg/CBM
(wet) : 1,900 Kg/CBM
- Plywood : 650 Kg/CBM
- Gold : 19,320 Kg/CBM
WEIGHING of LOAD
Weighing Method
Hanging

Balance
WEIGHING of LOAD
Weighing Method
Jack-up

If Jack can be used synchronize with multi-


numbers, the sum and total number of jacks
CENTER of GRAVITY

Center of slings on CG
Center of hook over CG
Place of Pick Points above CG
CENTER of GRAVITY

Pick points above the CG is more stable.


If pick point can not be placed above center of
gravity, keep sling angle as great as possible
Rigging Equipment & Hardware

SLINGS
SHACKLES
HOOKS
EYEBOLTS
CLAMPS
SPREADER BEAM
SLINGS
SLING CAPACITY
SLINGS
SLING FORCE CALCULATION
SLINGS
SLING ANGLE

Should be length L is grater than S


SLINGS
HITCH

Vertical Basket Choker


SLINGS
Whenever any sling is used, the
following practice shall be observed.
1. Slings that are damaged or defective shall not be
used.
2. Slings shall not be shortened and deformed with
knots or other makeshift device.
3. Sling legs shall not be kinked.
4. Slings shall not be loaded in excess of their rated
capacity.
5. Slings shall be padded or protected from the sharp
edges of their load.
SLINGS
6. Slings used in a Basket and Choker hitch shall have
the load balanced to prevent slippage.
7. Personnel should be kept clear of loads about to be
lifted and suspended load.
8. Hands or fingers shall not be placed between the
sling and its load while the sling is being tightened.
9. Shock loading is prohibited.
10. A sling shall not be pulled from under a load when
the powered force is resting on the sling.
SLINGS
INSPECTION
Everyday before being used, the slings and all
fastenings, attachments shall be inspected for
damage and defects by a competent person
designated by KJP.

Additional inspections shall be performed


during sling use as often as necessary to assure
the safety of the operation.
SLINGS
CLASSIFY
- WIRE ROPE SLING

- ALLOY STEEL CHAIN SLING

- SYNTHETIC WEB SLING


SLINGS
- METAL MESH SLING

- FIBER ROPE SLING


Product by Nylon, Polyethylene, Polypropylene and
other natural fibers.
Fiber rope must not be used for hoist with a powered
hoist and lift.
- FITTINGS
Thimbles, clips, clamps, links, hooks, wedge socket etc.
SLINGS
-Example of wire rope damage ; Reduction of Rope Diameter
SLINGS
-Example of wire rope damage ; KINK
SLINGS
-Example of wire rope damage ; BIRD CAGING
SLINGS
-Example of wire rope damage ;
SLINGS
-Example of wire rope damage ;
SHACKLES
DEE Shackle

BOW Shackle
SHACKLES
USE OF SHACKLE
The pin is up only when using the bell of shackle with hook.
When a choking, the pin goes into the eye formed end of the
sling.

Incorrect Correct
SHACKLES
INSPECTION
HOOKS
HOOKS
A hook must have a safety latch or other means that
will retain slings, chains, other similar parts under
slack condition.
HOOK LOADING (Strength only)
HOOKS
INSPECTION
EYE BOLTS

Right Wrong
- Lift Vertically, the eye is designed for a pull along
the axis of the bolt
- Lift in Plain of Eye
- Make sure Eye Bolt is seated
CLAMP & CLIP

U-Bolt Clamp Double saddle Clamp Double base Clamp

- Not to be used sling


- Clamp can be used safely for strength to 80% of
wire rated capacity.
CLAMP & CLIP

Wrong Way Right Way

The U-bolt part of a wire rope clip must be


installed so that it bears on the unloaded
end
of the wire rope.
CLAMP & CLIP
Installation and use of wire rope clips
SPREADER BEAMS
Spreader and load equalizer beams must be proof
tested, both static and dynamic.
This testing shall be performed by a qualified
person, an as specified basis and confirm to a
written procedure.
Spreader and Load equalizer beams must have their
Working Load Limit (W.L.L) certified by an
established manufacturer or inspection company.
A nameplate or registered mark is required on
spreader beam and display the manufacturers
name, serial number, weight of device, W.L.L. etc...
SPREADER BEAMS

All welded joints are should be full penetration weld


by qualified welder and examined as NDE by
authorized persons.
Proof tested to 125% of Safe Work Load
SHEAVE
A sheave must be correctly sized for the rope, have a
device to retain the rope within the groove, and be
removed from service if it has a damaged groove or
flange.
SITE PREPARATION

Trial Load test


Soil bearing capacity
Overhead
Signal
Weather
Others, such as Barricades, Ladder or
Stair, Fire extinguisher, Lightings, etc.
Demobilization after rigging
SITE PREPARATION
TRIAL LOAD TEST
Prior to critical lift and pre-engineered lift, all
cranes shall be load tested by a KJP
inspector.
A functional test of the crane under a normal
operating load should be made prior to
service.
Test weight shall not be exceeding 110% of
the rated capacity.
A written report shall be furnished by the
inspector showing test procedure.
SITE PREPARATION
SOIL BEARING CAPACITY
- Determine the allowable soil bearing pressure and
underground conditions at the lift location,
including the location of underground utilities.

- Check to see if the lift requires special mat


arrangements to satisfy soil bearing capacity
requirements, and show the number and size of
mats in a detailed layout sketch on procedure.
Stability of Ground for Rigging
SITE PREPARATION
Calculate a Area of Mat under Out-Rigger
Normal Condition
SITE PREPARATION
OVERHEAD
Cranes are used to handle materials or loads stored
anywhere but under electric power lines and
transmitter towers.
SITE PREPARATION
OVERHEAD

Safe Working Distance from Power Lines


SITE PREPARATION
SIGNAL
The operator of a crane or hoist must act only on
directions from a designated and competent signaler
whenever the operator does not have a clear and
unobstructed view of the load hook and load throughout
the whole range of the hoisting operation.

Standard hand signals are shown in Attachment.

Hand Signal Posting is required to conspicuously post at


the job site figures demonstrating standard hand signals
for controlling mobile cranes.
SITE PREPARATION
SIGNAL
In situations where hand signals are not effective, use
other communication equipment as under;
Alternative to hand signals
Two-way radio or other audio or video systems
acceptable to KJP must be used if distance,
atmospheric conditions or other circumstances make
the use of hand signals hazardous or impracticable.
Multi-channel radios are not permitted for use to direct
crane operator.
SITE PREPARATION
STANDARD HAND SIGNAL
(for mobile crane)
SITE PREPARATION
STANDARD HAND SIGNAL
(for mobile crane)
SITE PREPARATION
STANDARD HAND SIGNAL
(for mobile crane)
SITE PREPARATION
WEATHER
Ensure that wind speed and other weather conditions
are considered.

Do not attempt shifts and lifts of load if weather


conditions are adverse to safe load-handling
operations.

Consider weather factors that might reduce crane lift


capacity and adjust the load weight to suit.
SITE PREPARATION
Others, such as Barricades, Ladder or Stair,
Fire extinguisher, Lightings, etc.

Barricades forming a perimeter at least 3


meter away from the working area to prevent
unauthorized personnel from entering the
working radius of crane and working area
shall be utilized.
SITE PREPARATION
Ladder, stairway, scaffolds or other safe means of
access should be prepared for use in reaching the
work place where located in higher place such as
operators cabin, hooking position on the load etc.

An accessible fire extinguisher shall be provided at


work site and cabin of crane.

Lighting systems are to be provided on site.

Stand-by labor as required for removal of temporary


shipping skids prior to lifting is to be provided.
SITE PREPARATION
Demobilization after rigging

Ensure access out of the lift area


considering
equipment that may require disassembly
for
moving.

House keeping & cleaning.


TYPE OF CRANE
Wheel mounted crane (Single-control Station)

Self-propelled, wheel-type cranes are equipped power


and control units for travel and liftcrane operations.
TYPE OF CRANE
Truck mounted crane (Multi-control Station)

Truck mounted cranes may be provided with lattice


booms or self-contained hydraulic telescopic
cantilevered booms.
TYPE OF CRANE
Conventional crawler crane

The crawler mounting does not allow for the cranes


self-transit between job sites.
As such, crawler mounted cranes are moved between
sites in a knocked down condition via truck, rail,
or barge, and are assembled on site.
TYPE OF CRANE

Crawler crane with counter balanced


TYPE OF CRANE

Ringer crane
TYPE OF CRANE

Crawler crane with Luffing Jib


OTHER LIFTING
FACILITIES
DERRICK
- The basic derrick mechanism provides the ability
to hoist a load up or down, and luff up or down over
a range of operating radii.
- With the exception of the shear leg configuration,
most derrick configurations also provide the ability
to slew, or to swing a load over a specific arc of
operation.
- Derricks are typically attached to some existing
infrastructure.
OTHER LIFTING
FACILITIES
DERRICK
OTHER LIFTING
FACILITIES
HOIST WITH BLOCK
- The simple hoist and load block
system consists of a pair of
construction blocks strategically
positioned beyond the final desired
position of the handled component.
- Depending on the rigging weight of
the heaviest handled component,
the construction blocks may consist
of single or multiple sheaves.
OTHER LIFTING
FACILITIES
MONORAIL SYSTEM
Monorail systems consist of a load
block and hoisting system
suspended from a trolley or series
of
trolleys that travel on a beam
suspended from some existing
support structure.
OTHER LIFTING
FACILITIES
CABLE WAY SYSTEM
Taut lines and cableway
systems are very similar to
monorail systems.
DEFINITION
ANSI American National Standards Institute
Designated Person A person selected or assigned by the employer as being
competent to perform specific duties.
Frequent Inspection A visual examination by the operator, user or other
designated persons with documentation not required.
Handled Load The weight of the item to be lifted plus the weight of any required
rigging such as lifting beam, slings, hooks, and blocks.
Handling Hoisting, rigging or transporting of items.
Hoisting Lifting a weights or loads or various kinds by machinery of any kind.
Initial Inspection An inspection performed and documented prior to initial use on
all new, modified, or repaired rigging hardware. Items checked are as itemized
under periodic inspection for the piece of equipment considered. On new rigging
hardware, which was purchased with certificates of compliance, this may be a
visual inspection.
Non-Destructive Examination A test that does not destroy the functional use of
the piece of equipment, such as, but not limited to, visual, dye penetration test,
magnetic particle test, radiography test, and ultrasonic test.
DEFINITION
OSHA Occupational Safety and Health Administration
Operational Test A test, with or without a load, that determines the operating
capability of the rigging hardware.
Periodic Inspection An inspection performed by a designated person who
documents the apparent external conditions to provide the basis for continuing
use of the piece of rigging hardware and also after use. It may also include
disassembly for internal examination, non-destructive examination (MT or PT), or
rated load testing. Written records are to be retained. For the purpose of this
procedure, periodic inspections will be done on an annual basis. Additional
inspections may be required by manufacturers recommendations or as directed
by the Project Field Engineer.
PFE Project Field Engineer
PIC Person in Charge
Qualification (Personnel) The characteristics or abilities gained through training
or experience or both that enable an individual to perform a required function.
Rated Capacity The maximum load for which the piece of rigging hardware was
designed and built, as determined by the manufacturer. It provides the minimum
factor of safety as specified by OSHA and ANSI B30 Safety Standards. Safe
Working Load (SWL) and Working Load Limit (WLL) are interchangeable terms
with rated capacity.
DEFINITION
Rated Capacity The maximum load for which the piece of rigging hardware was
designed and built, as determined by the manufacturer. It provides the minimum
factor of safety as specified by OSHA and ANSI B30 Safety Standards. Safe
Working Load (SWL) and Working Load Limit (WLL) are interchangeable terms
with rated capacity.
Rated Load Test A proof test designed to confirm the load rating of handling
rigging hardware.
Rigging Hardware A mechanical device used to move equipment or materials.
Rated Load Test A proof test designed to confirm the load rating of handling
rigging hardware.
Rigging Hardware A mechanical device used to move equipment or materials.
Testing The determination or verification of the capability of equipment to meet
specified requirements by subjecting the rigging hardware to a set of physical,
environmental, non-destructive examination, or operating tests.
SAFE RIGGING
PRACTICE

THANK YOU
VERY MUCH

You might also like