Critical Chain Project

Management

BCS Nottingham & Derby


Winter School 2006
Steven Wray, BA, MBA, MBCS, C Eng

Phone: 07951 727 490


e-mail: steve@wrayassociates.com
web: www.wrayassociates.com
What makes a Project ?

• One end-point

• At least two tasks, linked by dependency

• Significant inherent unpredictability in how long


the tasks will take.
What do we want from Project Management ?
What do we want from Project Management ?
• Reliable on time in full to budget delivery performance
More revenue, more Profit, happy customers
• A stable plan
More Productive use of resources
• Simple, objective measures of Project progress
Shorter meetings, better informed
stakeholders - less waste, more productivity
• Simple, objective measures of Project health status
Shorter meetings, better informed
stakeholders - less waste, more productivity
• Clear signals for when corrective action is - and is not - necessary
Better directed recovery efforts - less waste,
more productivity
• Direction for ongoing improvement efforts
The future brings more revenue, more profit, happier
customers than the present
What is our normal experience from today's
way of Project Management ?
What is our normal experience from today's
way of Project Management ?
• Reliable on time in full to budget delivery performance ?
Or A continuous struggle with time, cost and scope ?
• A stable plan
Or Repeated rescheduling ?
• Simple, objective measures of Project progress ?
Or Clarity at the start and end, thick fog in between ?
• Simple, objective measures of Project health status ? Or
Subjective assessments compounded by human factors ?
• Clear signals for when corrective action is - and is not - necessary ?
Or Intervening too much too early, and too little too late ?
• Direction for ongoing improvement efforts ?
Or "We'll improve our methods when things get better"
'Normal' Practice in the planning phase

• We identify the tasks in the Project and specify the resources


needed for each one
• We allocate to each task sufficient time that we are confident
will allow it to be completed with those resources. That is,
the time the task should take on average, plus some
contingency to give us the confidence we seek
• We apply task dependencies, and work out the longest path
of tasks in the Project
• The time along this path is the time-line of the Project
Normal practice in the execution phase

• As long as every task completes on time (within its


contingency), its successors will be started on time
• As soon as any task finishes late (outside its contingency),
its successors will start late, and this normally means they
will finish late
• In order to rescue a Project which shows any lateness, we
have to squeeze the remaining tasks in the Project
• Typically we have to compromise on time, cost or scope
and reschedule
The Estimating Dilemma
• If I allow more time for every task in the plan, each task is
less likely to be late, but the Project end date will be
later...

• If I allow less time, the end date will be earlier, but the
Project is more likely to overrun

• BUT I have to deliver the Project on time


How long should we allow in the plan for
a task ?
• Some staff work more quickly than others
• Sometimes staff are distracted or interrupted
• Sometimes necessary resources are delayed
• Some staff are risk-averse in their commitments
• Some organisations reinforce risk-aversion
How long do we allow in the plan for a
task ?

The average time the task ought to take an average performer


who focuses on it

PLUS The time we expect to be spent on distractions


PLUS A contingency time to take account of:
• The spread between average and low performers
• Our uncertainty in the average time
• Our uncertainty in the time for distractions
• How risk-averse we are or have to be
Some simple maths
If we set our estimates so that we are 90% sure that any
one task will be completed on time

If we have 20 tasks in our Project

The Probability that all the tasks


will be on time is: 0.920 = 12%

For 50 tasks, the Probability of all on time is: 0.950 = 1%


Emphasising

• Doing things by the text-book, with 20 tasks, each of


which we are 90% sure will complete on time, we have an
88% probability of being late for the Project

• With 50 tasks, its a lot worse: its a 99% probability of


being late for the Project
What if we change our estimating to a 95%
confidence level ?

• NB This will inflate the time for every task maybe by 25 - 50%
because we will need more contingency
• For 20 tasks the probability of being late is now 64% (was 88%)
• For 50 tasks we are late now 92% (was 99%)

We have very much extended our Project time-line, and


increased our chances of success from 12% to 36% for
the small Project, and from 1% to 8% for the large Project
Surely, there's a better way...

• Plan A - invest our energy in reducing the extent of the variability:


- Allowing longer in Project planning stage for preparing estimates
- Training staff in estimating
- Use of formal estimating methods
- Measuring progress (CSC tools) and feeding results back into estimating practice
- More detailed specifications
- Less flexibility over changes to specifications
- Training the staff better in their job content
- Using individual performance measures to identify poor performers
- Keeping projects short (c 6 months), breaking larger undertakings into several short
Projects

Doing this can help, but doesn't solve the problem


Plan B - Coping behaviours

• Project Managers fight to be assigned the most viable Projects


• Project Managers fight for the best staff
• Project Managers fight to keep the Project scope down
• Project Managers exploit changes in scope to unduly extend timelines and budgets
• Project Managers sandbag Project plans to create headroom
• Project Managers quit long Projects well before the delivery date
• Project Managers disregard targets they know to be impossible
• Staff work double shifts in the final weeks / months
• Dumping the blame elsewhere

Doing these may help the individual, but not the organisation
Plan C: Approach the problem in a different way

We can reduce variability, but we cannot eliminate


it, because it is inherent to the nature of a
Project

We must manage the variability that remains


How we handle variability in Critical Chain

• We do not build in any contingency at the Task level


• We move all the contingency to the Project level - we call
this the Completion Buffer

Individual Tasks can now be late without affecting the


completion date of the Project
The Project due date is protected as long as
the accumulated lateness along any one
chain is less than the completion buffer
What difference does this make to our
probability of being late ?

Under 'normal' practice, if any task is later than its


contingency allows, we have a problem

Under Critical Chain, we only have a problem if the total


lateness exceeds the total contingency

This second condition is much less likely than the first [ Law
of averages / Central limit theorem] and increasingly so
as the number of tasks increases
The Completion Buffer

• A Buffer is a block of time which protects a deliverable


from being affected by delays upstream. The Completion
Buffer protects the Project completion date

• Over the course of the Project we expect our buffers to


be used up, in proportion to progress made
Scarcity of Resources

• In putting together the plan, we must take into account


scarcity of resources
• In particular, if two tasks want exclusive use of the same
resource, at the same time, they have to be staggered
• This affects the plan in a similar way to the task
dependencies
Scarcity of Resources
Task C depends on both A and B
Each task uses a different resource

Task A – 10 d

Task C – 10 d

Task B – 10 d

Project Time required - 20 d


Scarcity of Resources
Task C depends on both A and B,
Both A and B need exclusive use of the same resource

Task A – 10 d

Resource conflict Task C – 10 d

Task B – 10 d

Project Time required - 30 d


The Critical Chain
We identify the longest chain of dependent tasks by resource through the Project - this is the Critical Chain, at the end we place
• the Completion Buffer

The time taken to complete the


Project is the time taken to complete
the Critical Chain

Any delay in the Critical Chain


delays the Project completion
Completion Buffer

Task A Completion Buffer

Task C

Task B

Committed end date


In Practice
Task A

Task C

Task B

Project duration held constant

Task A Completion Buffer

Task C

Task B

The buffer is 25-33% of


chain length
Feeding Chains

• All the other chains of tasks we call Feeding Chains ,


because each one at some point feeds into the Critical
Chain

• Every task in the Project is part of either the Critical


Chain or a Feeding Chain
Feeding Buffers
• We must not allow anything to delay the Critical Chain

• We must protect the critical chain from being delayed by


lateness in the Feeding Chains

• We start the feeding chains a little early, and insert a


block of time to decouple the Critical Chain from each
Feeding Chain

• We call these blocks of time Feeding Buffers


Feeding Buffers

Task A Completion Buffer

Task C

Task B

FB

Task D
Planning Phase Summary

• There is no contingency at task level


• The Project due date is protected by the a block of time
called the Completion Buffer
• The Critical Chain is the longest chain of tasks through
the Project
• All other chains of tasks are Feeding Chains
• We place Feeding Buffers to decouple the Critical Chain
from the feeding chains
Execution phase....
• We have a great plan - what can happen in execution ?
Critical Chain in the Execution phase....
• No multi-tasking - when someone starts a task they
stick to it until it's completed
Bad Multi-tasking
Whenever I put down one task and pick up another, I lose
productive time

How much time is lost switching depends on how deep or


shallow the task in hand is

Putting a stop to multi-tasking in effect creates extra


capacity
More Bad Multi-tasking

If we have two people, each available 50% to our Project, and they
have to work together, they are effectively 25% available

If we have four such people, it's effectively 6%, so we'll wait on


average 8 working days to get them together for half a day

Real-life case: Ten team leaders, each on 50% availability: Out of two
Project meetings held, 3 came to both, 5 to one or the other, 2 to
neither
Very Bad Multi-tasking

When someone stops doing a task on the Critical Chain,


and starts doing something else, they are delaying the
entire Project
Critical Chain in the Execution phase....
• No multi-tasking - when someone starts a task they stick
to it until it's completed
• We begin each task as soon as resource is available and
prerequisite tasks are complete

The timings in the plan are for planning,


not a commitment on execution
Critical Chain in the Execution phase....
• No multi-tasking - when someone starts a task they stick
to it until it's completed
• We begin each task as soon as resource is available and
prerequisite tasks are complete
• We finish each task as soon as we can
Early finishes on Critical Chain tasks bring
forward the whole Project

Early finishes on Feeding Chains increase the


protection of the Critical Chain

Sometimes we call these three together 'Roadrunner' style


Summarising Practical differences...
• Planning phase:
– The Project is analysed into the Critical Chain and Feeding
Chains
– Contingency is aggregated into a Completion Buffer
protecting the Project end-date, and Feeding Buffers
protecting the Critical Chain
• Execution Phase
– No Multi-tasking
– Early finish / allowing early start of following tasks
– Subordination to the Critical Chain
Measures and Management

• How do we know how the Project is doing ?


Measures and Management
Making less progress than planned will eat into the Completion buffer

Making more progress than planned will add to the Completion buffer

B
At day 5, task A has 8 days
remaining (of 10) - Completion
Buffer is eroded by 3 days

Task D is completed - no effect


D on Completion Buffer
Measures and Management

• Question 1: How many days work until the Project is


completed ?

• Answer = the number of days left on the Critical Chain

It is the time on the Critical Chain that determines the time required to complete the
Project
Measures and Management
• Question 2: How certain are we about the answer to Question 1 ?

• Answer = the proportion of the Completion Buffer that we have left, compared to
the proportion of the Critical Chain still to do

The Completion Buffer protects the end


date. The less (more) it is eroded,
the less (more) the end date is at risk
Corrective Action
We compare the percentage of the Completion Buffer
Remaining (%CBR) with the percentage of the Critical
Chain Remaining (%CCR)

We set trigger points for corrective action, for example:

• When the ratio %CBR / %CCR is 1or more, Project


status is GREEN - Watch
• When %CBR / %CCR is between 1 and 2/3, Project
status is AMBER - Prepare a recovery plan
• When %CBR / %CCR is less than 2/3, Project status is
RED - Implement recovery plan
Measures in 2-D
0%
Completion Buffer Remaining

100 %

100 % Critical Chain Remaining 0%


Don't overreact to buffer erosion

• We expect our buffer to be used up over the course of


the Project

• Our date is not threatened if the buffer is used up in


proportion to progress
– If we have 2/3 of the completion buffer left and only 1/3 of
the Project to do we are doing fine

• Our date is threatened if the buffer is used up


disproportionately
– If we have 2/3 of the Project still to do but have only 1/3 of
the completion buffer left we have a problem
Measures Summary

• We have simple, objective measure of Project progress


• We have a simple, objective measure of Project health
status
• We have a simple rule for triggering - and not triggering -
corrective action

We can redefine the Project progress


meeting as the Buffer Management
Meeting
Buffer Management Meeting
Attendees: Project Manager, Project Sponsor / Owner, Task Managers,
Resource Managers

Agenda:
1. Reminder of what tasks are on the Critical Chain.
2. Review Project status ( % Critical Chain outstanding).
3. Review Completion buffer status (Red, Amber, Green).
If necessary, initiate corrective actions.
4. Review Feeding buffers status (Red, Amber, Green).
If necessary, initiate corrective actions.
5. Review tasks in progress to ensure earliest completion in full.
6. Review tasks not started to ensure earliest start where
appropriate.
Using Buffer Management to drive ongoing
improvement
• Buffer Management measures are fact-based and
objective
• Buffer Management meetings highlight buffer
erosion / Project delays
• Preventing the causes of delay will speed up your
Projects
• Your process of ongoing improvement is simply to
eliminate the causes of delay by following up on the
issues highlighted in Buffer Management meetings
• As your Projects run faster and more reliably,
continue to eliminate more and more causes of delay
How Does Critical Chain help our Project
Management ?
Aggregated contingency and 'Roadrunner' style
 Effective due-date protection and extra effective capacity
 More reliable on time in full to budget delivery performance

Identification of Critical Chain and Feeding Chains  Focus

Buffers  Flexibility  A stable plan

Buffer measures
 Objectivity and clarity
 Better focused meetings, better directed recovery efforts, better informed
stakeholders, less waste and more productivity
 Less encouragement of 'coping behaviours‘

Buffer Management
 Focus for ongoing improvement efforts
Without CCPM
• If the plan is not based on the Critical Chain, it may be infeasible
• If the Critical Chain is not known, the Project Manager cannot focus
on it
• Without contingency the plan is not robust
• If contingency is all in the task estimates, it's still not robust it’s just
longer, and there is no sense of urgency
• Without feeding buffers, an early completion will not help the end
date, because the next task has to wait for its other prerequisites
• With multi-tasking and interruptions > 25% capacity is wasted
• Interruptions on Critical or Feeding Chains delay Project Completion
• Measures are backward-looking or misdirect attention
• Improvement processes lack focus
Multi-Project Pipelines
The Goal is to maximise Project throughput over
some timeframe

The constraint is one of the resources available

The pipeline can be overcommitted

Resources can be used on the wrong Project

Projects can delay one another


Multi-Project Pipelines

• Starting point is that each Project has a fully


defined CCPM plan, and
• We have a defined set of global resources
• Assumption that one of the resource constraints
dominates the others over the timeframe (Pacing
Resource)
• Execute a single pipeline plan which is feasible
and robust
Example
We run the engineering department of a manufacturing company making
custom products
Each product ordered is a new variation on a few standard designs
Typically, for each product ordered, we spend 5 days on the specification, 10
days on the design, 2 days on the test plan, and 3 days on the manual
We have 2 people who do specifications, 3 who do designs, one test planner
and one manual-writer

Which is the Pacing Resource ?


How many Products can we deal with in a 50 day quarter ?
Example
We run the engineering department of a manufacturing company making
custom products
Each product ordered is a new variation on a few standard designs
Typically, for each product ordered, we spend 5 days on the specification, 10
days on the design, 2 days on the test plan, and 3 days on the manual
We have 2 people who do specifications, 3 who do designs, one test planner
and one manual-writer

Specification: 2 x 50 = 100/5 gives 20 products


Design: 3 x 50 = 150, 150/10 gives 15 products
Test Plans: 1 x 50 / 2 = 25 products
Manuals: 1 x 50 /3 = 17 products
Design = Pacing Resource
Example
We run the engineering department of a manufacturing company making
custom products
Each product ordered is a new variation on a few standard designs
Typically, for each product ordered, we spend 5 days on the specification, 10
days on the design, 2 days on the test plan, and 3 days on the manual
We have 2 people who do specifications, 3 who do designs, one test planner
and one manual-writer

What is the consequence if:


The test planner is off for two weeks ?
One of the designers is off for two weeks ?
The documentation task for a product overruns by 50% ?
The design task for a product overruns by 50% ?
The specification task for a product overruns by 50% ?
Answers
Loss of output on the pacing resource has a permanent,
pervasive effect

Loss of output on the other resources has a temporary,


local effect

We need to protect the Pacing Resource


Planning the Pipeline

Stagger Projects on the Pacing Resource

Buffer the Pacing Resource

A feasible and robust due-date for each


Project
Priorities in the pipeline

• In order of net profit per hour of time on Pacing


Resource
• In sequence of strategic priority
• Committed Projects first, then new Projects
• Look at the effects of different sequences
Product 793 Spec Design Test plan /
Schedule Manual

Pacing Resource RB Design RB Design RB Design RB


Schedule 792 793 794

Product 794 Spec Design Test plan /


Schedule Manual
Execution Phase
Hierarchy of subordination:
• Never interrupt the Pacing Resource
• Only interrupt a Critical Chain task to start the Pacing
Resource
• Only interrupt a Feeding Chain task for a Critical Chain
task
Measures in 2-D
0% 3

5
Completion Buffer Remaining

100 %

100 % Critical Chain Remaining 0%


Buffer Management
Management team (Project Managers, Resource Managers)
looks at:
• Pacing Resource schedule
• Resource Buffer status
• Critical Chains vs Completion Buffers picture
• Resources: best resources allocated to most important
Projects ?
• Pacing Resource tasks in Progress - early completions ?
• Pacing Resource tasks due to start - early starts ?

Record buffer erosion to focus improvement effort


Summary - Multi- Project
• Start with all Projects fully-defined in CCPM
• Identify Pacing Resource
• Load the pipeline by staggering Projects on the Pacing
resource
• Buffer the Pacing Resource
• Apply hierarchy of subordination
• Manage by Buffer Management
• Use Buffer Management to drive improvement
Without CCPM

• If we haven't identified the Pacing Resource:


– our pipeline may be infeasible
– we will waste capacity
• Without a resource buffer, the pipeline won't be
robust
• Without good measures, management is
unfocused or wrongly focused
• Without Buffer Management, improvement is
unfocused
In Practice
• The logic of CCPM works
• Many success stories: A50, Lucent, Phillips, US Navy
• Implementation is not a trivial undertaking
• As CCPM brings Projects under control, the constraint
moves to management
• Aggressive reductions in cycle time are both possible
and necessary
Books
"Critical Chain" by Eli Goldratt 0-88427-153-6

"Critical Chain Project Management" by Lawrence P


Leach ISBN 1-58053-903-3

"Enterprise-Focused Management" by Ted Hutchin


ISBN 0-72772-979-9