You are on page 1of 35

Introduction to Process Plant Start-up

and Commissioning
Plant Start-up and Commissioning

 Plant commissioning is the first of many start-ups


 Potentially hazardous: ability to operate not proven
 Many unknown factors
 First startup & subsequent shutdowns and startups
 Excellent experience and expertise building for
operators and maintenance personnel.
Start-up and Commissioning apply to

 Entire facilities in Greenfield projects


 Major expansions or additions to existing plants
 Re-commissioning of plants and equipment;
 Individual items of plant, eg
 Boilers

 Instrument air compressors etc


Delays in Startup & Commissioning
expensive!
 slow start-ups reduce the Return on Investment
 delayed revenue stream

 Increased cost of delivery

 Financial viability

 ~20-25% of construction time (good planning)


 Causes of delays:
 75% due to equipment failure

 20% from inadequate equipment

 5% from process failure


Details vary depending on plant but
procedure remains the same
 prepare, plan and execute startup
 commissioning management
 Preparation of specific plant procedures
 Management of risks
 Safety & environmental compliance
Construction & Commissioning
How we would like it …..

Mechanical completion
Provisional acceptance
Construction Acceptance

Pre-
commissioning,
Inspection and Start up and
Operational Performance Post
Testing testing commissioning
Construction and Commissioning
How it happens …..

Mechanical completion
Progressive provisional acceptance
Construction Progressive acceptance

Pre-commissioning,
Inspection and Start up and
Operational Testing Performance Post commissioning
testing
Commissioning in practice

 Progressive mechanical completion and concurrent


commissioning creates challenges:
 Coordination and planning

 Safety and risk

 Isolation

 Testing

 Integration into operating plant


From construction to commissioning

 what constitutes mechanical completion?


 on completion, start-up can officially commence
 problems when part of a plant are commissioned
while construction not yet finished.
The Commissioning Process
Key Stages
Preparation and planning

Mechanical Completion
and Integrity checking

Pre-commissioning &
Operational Testing

Start Up & Initial


Operation

Performance and
Acceptance testing

Post Commissioning
The Commissioning Process Detail - 1
 Appointment of Commissioning
Preparation and planning
Manager or Lead Commissioning
Engineer;
Mechanical Completion
and Integrity checking
 Appointment of Commissioning
Team Members and Support Staff;
Pre-commissioning &  Training;
Operational Testing  Information Compilation;
Start Up & Initial  Safety and Risk Assessment;
Operation  Commissioning Strategy
Performance and
Development;
Acceptance testing  Procedures and Checklist
Development;
Post Commissioning  Detailed Plan and Budget Preparation;
The Commissioning Process Detail - 2
Preparation and planning
 Inspection
Mechanical Completion
and Integrity checking
 Pressure testing
 Cleaning and Flushing
Pre-commissioning &
Operational Testing  Machinery checkout
Start Up & Initial
Operation

Performance and
Acceptance testing

Post Commissioning
The Commissioning Process Detail - 3
Preparation and planning

Mechanical Completion
and Integrity checking
 Steam and other utilities
Pre-commissioning & introduced;
Operational Testing
 Dry running trials;
Start Up & Initial
Operation
 Hot running trials;
 Safe-fluid dynamic testing;
Performance and
Acceptance testing
 Solvent dynamic testing;
 Process fluid tests.
Post Commissioning
The Commissioning Process Detail - 4
Preparation and planning

Mechanical Completion
and Integrity checking

Pre-commissioning &
Operational Testing

Start Up & Initial  Introduction of process fluid


Operation
 Start-up and initial operation
Performance and
Acceptance testing
 Trouble-shooting and
problem correction.
Post Commissioning  Plant taken to full operations.
The Commissioning Process Detail - 5
Preparation and planning

Mechanical Completion
and Integrity checking

Pre-commissioning &
Operational Testing

Start Up & Initial


Operation

Performance and  Performance trails;


Acceptance testing  Formal Acceptance test
Post Commissioning
The Commissioning Process Detail - 6
Preparation and planning

Mechanical Completion
and Integrity checking

Pre-commissioning &
Operational Testing

Start Up & Initial


 From plant on-stream to settled
Operation down and in regular production;
 Adjustments, modifications and
Performance and
fault correction;
Acceptance testing
 Completion of outstanding
Post Commissioning punchlist items
What makes commissioning & start-up
difficult ...
 planning, coordination and management;
 massive coordination of construction, contractors,

vendors, commissioning team, operations and


maintenance – all working to aggressive timelines.
 the commissioning team, operations and maintenance must
become familiar with extensive range of equipment and
technology, very quickly.
The Commissioning Process
Management Issues Preparation and planning Technical Issues
 Organisation and roles;
 Plant preparation and
Mechanical Completion
isolation;
 Information
Management; and Integrity checking  Utilities and Electrical
System Commissioning
 Procedure development
Pre-commissioning &  Equipment Specific
 Safety and risk Operational Testing Commissioning Issues
management;
 Machinery/ Rotating
 Permit systems Start Up & Initial
Equipment
 Job safety analysis Operation
 Vessels, Towers and
 Planning and control; Performance and pipe work etc.
 Budgeting and cost Acceptance testing  Removal of hazardous
control; substances and purging
 Commissioning strategy. Post Commissioning  Instrumentation
commissioning
Task force responsibilities
During design stage
 Review design for safety and operability
 Carry out HAZOP and other safety studies
 operating procedures & maintenance manuals
 Familiarization with the plant
 Check compliance with design, intent and standards
 Documentation for commissioning, operation & training;
 Arrange modifications required
 Recruitment, training of operations & maintenance personnel.
Typical Operating Instruction Manual

 The Process
 Conditioning and Special Equipment
 Starting Procedures
 Shutdown Procedures
Maintenance Responsibilities
 Publish work and safety procedures;
 Specify maintenance activities
 Select and purchase maintenance supplies and spare parts;
 Negotiate with vendors and contractors;
 Keep up maintenance records;
 Make detailed designs of any changes and additions made
during commissioning;
 Storage of spare parts and supplies;
 Schedule routine daily work and that for planned shutdowns.
Safety in Maintenance - 1
 Detailed procedures for maintenance work and work to be
done when executing the commissioning procedure
 Need to cover each major piece of equipment & system
 take into account all possible hazards
 Include:
 Instructions for isolating (blinding, draining, venting,

purging) process and utility systems;


 Locking out electrical systems

 Instructions covering atmospheric testing, type of test and

permissible limits of contaminants.


Safety in Maintenance - 2
 Definition of type of permit required to carry out work
 Type of equipment required for maintenance
 Description of personal protection equipment required
 Instructions regarding emergency equipment
 Instructions on potential hazards
 Emergency procedures
Spare Parts and Maintenance
Minimum Inventories for Commissioning and Start-up
 manufacturer’s recommended spare parts for
motive equipment - avoid duplication
 gaskets for vessels and heat exchangers.
 Pipe fittings, valves and gaskets (approx. 5% of
total of each in the plant should be sufficient)
 Instrument air tubing, plus adequate fittings
Spare Parts and Maintenance - 2
Minimum Inventories for Commissioning and Start-up
 Pressure gauges of appropriate ranges
 Thermometers and any special instrument parts
 Rupture disks
 Pipe insulation materials including jacketing
 Lubrication oils and greases
 Spare parts for electronic & analytical equipment.
Process Plant Machinery Commissioning
Failure Problems
in decreasing order of problem frequency

1. Centrifugal compressors
2. Steam turbines
3. Large gear speed increaser units
4. Electric motors in size categories above 1000 HP
5. Reciprocating compressors
6. Gas turbines
7. Gas expanders
Commissioning Team Information Requirements
 Project design file
 Process file

 Engineering data file

 Plant layout file

 Operating instructions

 Analytical procedures

 Log sheets and calculation procedures.


Commissioning Documentation
 Technical manual giving process technology and equipment
 Standard operating procedures giving details of each system
 Safety valve and rupture disk manual, listing the design basis
for each safety device, and giving the procedure for taking it
out of service
 Training manual detailing the program for new personnel
 Safety manual setting policies and procedures
 Emergency response manual, tabulating emergency
procedures and responses to adverse conditions (e.g. weather)
 Maintenance procedures specific to the new plant
Commissioning and Start Up Budget
Cost Estimation
Startup Budgets

 Three categories of cost;


 Costs for normal startup equipment, materials

and personnel;
 Costs for unexpected changes and additions;

 Costs for mechanical equipment breakdowns.


Estimating plant startup & commissioning

 Allow from 5-15% of overall capital cost of the


project for startup and commissioning
 Empirical rules for estimating both startup time
and startup costs, suitable for initial project budget
Estimate Startup Costs
Cost = A(0.10 + B + C + D +NE)
 A = Direct fixed capital cost  D = Labour factor
of project;  0.04 for labour in very short supply
 B = Process factor  0.02 for labour somewhat scarce
 0.05 for radically new process  -0.01 for surplus labour
 0.02 for relatively new  N = Number of process units
 -0.02 for familiar process involved
 C = Equipment factor  E = Dependency factor
 0.07 for radically new  0.04 for interdependent process units
 0.03 for relatively new  0.02 for moderately dependent
 -0.03 for familiar equipment  -0.02 for independent plants.
Estimate Startup Time
Time = a(0.15 + b + c + d +Ne)
 a = Construction Time  D = Labour factor
 b = Process factor  0.15 for labour in very short supply
 0.15 for radically new process
 0.05 for labour somewhat scarce
 0.05 for relatively new
 -0.01 for surplus labour
 -0.01 for familiar process  N = Number of process units
 c = Equipment factor involved
 0.15 for radically new
 E = Dependency factor
 0.08 for very new  0.25 for interdependent process units
 0.05 for relatively new  0.10 for moderately dependent
 -0.01 for familiar equipment  -0.02 for independent plants.
Startup Costs and Time Example
 A Crude Stabilisation Plan is currently under construction.
 Its capital cost is $100 Million and it is expected to take 8
months to complete;
 Because of its remote location it will be difficult to attract skilled
labour for the commissioning;
 The technology is all familiar and proven technology;
 Once operational the plant will be dependent on the existing Gas
Processing facility for smooth operation, but it has been
designed to allow it to be isolated from the gas side given that it
is a single operating unit;
 Estimate the cost and time to commission this unit.
Estimate Startup Costs & Time

 Startup Costs
 Cost = 100 (0.10 -0.02 -0.03 + 0.04 +1*0.02)

= 100 * 0.11 = $11 Million


 Startup Time
 Time = 8(0.15 -0.01-0.01+ 0.15+1*0.1)

= 8 * 0.38 = 3 Months

You might also like