Wind Energy Project

Pasni Balochistan

Group Members

Jalib Naseem
Rana Tariq Zahid

Wind Energy Project


Importance

Hike in the fuel prices need to find renewable resources to produce electricity.
Advantages of Wind Energy

Free source of energy Produce electricity 24 hours 7 days in week Environment Friendly One Time Investment

Wind Energy Project


Project Charter
Scope of Project Installation of wind turbines to produce electricity and construction of grid station to distribute electricity in the local region.
Enterprise Environmental Resources
External or internal factors which influence the success of project.
Internal Factors

Expert Team

External Factors

Weather Conditions Political Environment

Wind Energy Project


Project Charter (cont.) Organizational Process Assets
Historical data of wind speed in the region. Detail diagram of procedures involved in the project Risk involved in the project (positive or negative) Guideline of the experts

Wind Energy Project


Stake Holders
Ministry of Water and Power

Pakistan Electric Power Company (PEPCO) Balochistan Government Local Community

Wind Energy Project


Project Management Plan Work Breakdown Structure
Wind Energy Project

Civil Work

Construction of Roads

Building for Grid Station

Accommodation

Foundation for Turbines

Wind Energy Project


Project Management Plan Work Breakdown Structure (cont.)
Wind Energy Project

Mechanical Work

Installation of Turbines

Generators

Test Run

Wind Energy Project


Project Management Plan Work Breakdown Structure (cont.)
Wind Energy Project

Electrical Work

Installation of Equipments in Grid Station

Control Room

Transmission Lines

Wind Energy Project


Project Management Plan Work Breakdown Structure (cont.)
Wind Energy Project

Supply Chain

Oder Placement of Turbines

Transportation of Turbines

Transportation of Construction Material

Wind Energy Project


Process Id A Process Description Order Placement of Turbines Immediate Predecessor Time Required 90 Days

B
C D E

Construction of Roads
Transportation of Turbines from port to site Construction of Accommodation Foundation of Turbines A, B B D

45 Days
10 Days 30 Days 30 Days

F
G H I

Building for Grid Station


Installation of Turbines Installation of Equipments in Grid Station Installation of Transmission Line

B, D
C, D, E D H

30 Days
60 Days 20 Days 20 Days

J
K

Control Room
Test Run

I
G, H, I, J

30 Days
30 Days

Wind Energy Project Budget


Operations Turbine Cost Construction of Roads and Accommodation Construction of Grid Station & Control Room Operational Cost Cost in Rs. (Millions) 4,550 10 50 300

Wind Energy Project


Human Resource Plan
Work force needed for project is related from fields of

Civil Engineering Mechanical Engineering

Electrical Engineering
Quality Control Supply Chain

Wind Energy Project


Risk Management Plan
Risk Identification Risk of bad weather condition Risk of technical faults Risk of injury and accident Risk of security Risk of change in political environment
Risk matrix
Risk Type High Moderate Low Matrix Score Greater than 3 Between 1 to 2.9 Less than 1

Wind Energy Project


Risk Management Plan (cont.) Risk Response Plan
Risk Plan Transfer Mitigation Accept Type of Risk Risk of Security Threats Risk of Technical Faults and Injury or Accident Risk of Bad Weather

Risk Register

..\Wind Energy\Risk Register.xlsx

Wind Energy Project


Planning of Procurement
All heavy machinery needed for installation of turbines and construction will be procure.

Heavy Duty Cranes Lifters Vibratory Rollers Trucks Cars & Jeeps