You are on page 1of 59

CAPITAL BUDGETING

QUESTION (A) What is capital budgeting?

Analysis of potential projects. Long-term decisions; involve large expenditures. Very important to firms future. Evaluate & select long term investment, align with the goal of the firm, maximize s/holder wealth.

QUESTION (B) What is the difference between independent and mutually exclusive projects?

Projects are:

Independent, if the cash flows of one are unaffected by the acceptance of the other.
Mutually exclusive, if the cash flows of one can be adversely impacted by the acceptance of the other.

QUESTION C (1) What is the payback period? Find the paybacks for Franchises L and S.

The payback period is the expected number of years required to recover a project's cost. We calculate the payback by developing the cumulative cash flows
Franchise L 0 1 | | -100 10 -90 Franchise S 0 1 | | -100 70 -30

2 | 60 -30 2 | 50 20

3 | 80 50 3 | 20 40

Payback L: 2 + ($30/$80) = 2.4 years

Payback S: 1 + ($30/$50) = 1.6 years

QUESTION C (2) What is the rational for the payback method? According to the payback criterion, which franchises should be accepted if the firms maximum acceptable payback is 2 years, and if franchises L and S are independent? If they are mutually exclusive?

Payback

represents a type of "breakeven"

analysis: the payback period tells us when the


project will break even in a cash flow sense. With a required payback of 2 years, franchise S is acceptable, but franchise L is not. Whether the two projects are independent or

mutually exclusive makes no difference in this


case.

QUESTION C (3) What is the difference between the regular and discounted payback periods?

Payback period

Discounted payback period

A capital budgeting procedure

the payback period only measure

used to determine the profitability


of a project.

how long it take for the initial cash


outflow to be paid back, ignoring the time value of money

Provides the overall value of a project, a discounted payback period gives the number of years it takes to break even from undertaking the initial expenditure.

QUESTION C (3) What is the main disadvantage of discounted payback? Is the payback method of any real usefulness in capital budgeting decisions?

Time value of money is not considered when you

calculate payback period.

lack of consideration of cash flows beyond the


payback period. discounted payback period does not really give the

financial manager or business owner a solid decision


criterion upon which to make an investment decision. However, payback is not generally used as the primary decision tool. Rather, it is used as a rough measure of a project's liquidity and riskiness.

QUESTION D(1) Define the term net present value (NPV). What is each franchises NPV?

NPV compares the value of a dollar today to the value of that same

dollar in the future. If the NPV of a prospective project is positive, it


should be accepted and vice versa.

Franchise Ls NPV is = $18.79

Franchise Ss NPV is = $19.99

0
| (100.00) 9.09 49.59 60.11

1
| 10

2
| 60

3
| 80

0 | (100.00) 63.64 41.32 15.03

1 | 70

2 | 50

3 | 20

18.79 = NPV L

19.99 = NPV S

QUESTION D (2) What is the rationale behind the NPV method? According to NPV, which franchise or franchises should be accepted if they are independent? Mutually exclusive?

If the NPV of any project is zero then it means that the return from

the project is equal to the outflow of the project. There is no chance

of making a profit from the project.


A positive NPV indicates that project earns more than its cash outflow and is profitable. In the case of negative NPV, the implication

is vice-versa.
If franchises L and S are independent, then both should be

accepted, because they both add to shareholders' wealth, hence to


the stock price. If the franchises are mutually exclusive, then franchise S should be chosen over L, because S adds more to the value of the firm.

QUESTION D(3) Would the NPVs change if the cost of capital changed?

The NPV of a project is dependent


on the cost of capital used. Thus, if the cost of capital changed, the NPV of each project would change. NPV declines as r increases, and

NPV rises as r falls.

QUESTION E(1) (2)


Define the term Internal Rate of Return (IRR). What is each franchise's IRR? How is the IRR on a project related to the YTM on a bond?

Internal Rate of Return (IRR) is the discount rate that will equate the present value of the outflows with the present value of the inflows. By using Financial Calculator, we get IRRL = 18.1% and IRRS = 23.6%. e. (2) How is the IRR on a project related to the YTM on a bond? IRR to a capital project is like YTM to a bond. IRR is the expected rate of return on the project, just as YTM is the promised rate of return on a bond.

QUESTION E(3)
What is the logic behind the IRR method? According to IRR, which franchises should be accepted if they are independent? Mutually exclusive?

IRR measures a project's profitability in the rate of return sense. If IRR = k : cash flows are just sufficient to provide investors with their required rates of return. If IRR > k : economic profit, which accrues to the firm's shareholders. If IRR < k : economic loss, or a project that will not earn enough to cover its cost of capital. If S and L are independent, accept both. IRRs > r = 10%. If S and L are mutually exclusive, accept S because IRRS nor IRRL .

QUESTION E(4) Would the franchises' IRR change if the cost of capital changed?

IRR are independent of the cost of capital. Therefore, neither IRRS nor IRRL would change if k changed. However, the acceptability of the franchises could change; L would be rejected if k was above 18.1%, and S would also be rejected if k was above 23.6%.

QUESTION F(1)

Draw NPV profiles for franchises L and S. At what discount rate do the profiles cross?

Cost of Capital % 0 5 10 15 20

NPV L % 50 33 19 7 (4)

NPV S % 40 29 20 12 5

The crossover point is 8.7 percent. To calculate the crossover rate, by using Financial Calculator: Cash Flow Differences = Cash Flow L Cash Flow S; CF0 = -100 (-100) = 0 CF1 = 10 70 = -60 CF2 = 60 50 = 10 CF3 = 80 20 = 60

QUESTION F(2)
Look at your NPV profile graph without referring to the actual NPVs and IRRs. Which franchise or franchises should be accepted if they are independent? Mutually exclusive? Explain. Are your answers correct at any cost of capital less than 23.6 percent?

NPV and IRR always lead to the same accept/reject decision for independent projects;
k < IRR and NPV > 0 : Accept k > IRR and NPV < 0 : Reject However, for mutually exclusive projects; K < 8.7 : NPVL > NPVS , IRRS > IRRL ; Conflict K > 8.7 : NPVs > NPVL , IRRS > IRRL ; No Conflict

QUESTION G(1) What is the underlying cause of ranking conflicts between NPV and IRR?

A conflict exists if the cost of capital is less than the crossover rate. Two basic condition: When project size (or scale) differences exist When timing differences exist

QUESTION G(2)

What is the reinvestment rate assumption, and how does it affect the NPV versus IRR conflict?

The underlying cause of ranking conflicts is the reinvestment rate assumption Assumed that a project will cost some money up front, and then produce cash flow returns over a period of time Assumed that these cash flows will be reinvested by the firm NPV assumes that the cash flows will be reinvested at the firm's cost of capital (WACC) IRR assumes that cash flows are reinvested at the IRR rate.

QUESTION G (3) Which method is the best? Why?

The best assumption : The projects cash flows can be reinvested at the cost of capital NPV method is more reliable More realistic in real world

QUESTION H(1) Define the term modified IRR (MIRR). Find the MIRRs for Franchise L and S

The discount rate that causes a projects cost (or cash outflows) to equal the present value of the projects terminal value.

Franchise L 0 (100) 1 70 2 50

WACC = 10% 3 20 55 84.7 159.7

TV = MIRRL = 16.50%

Franchise S 0 (100) 1 10 2 60

WACC = 10% 3 80 66 12.1 158.1

TV = MIRRS = 16.89%

QUESTION H(2)

What are the MIRRs advantages and disadvantages vis-avis the regular IRR?

MIRR assumes that cash flows from all the firms projects are reinvested at the cost of capital. MIRR is a better indicator of a projects true profitability. MIRR solves the multiple IRR problems, as a set of cash flows can have but one MIRR.

What are the MIRRs advantages and disadvantages vis-a-vis the NPV? MIRR does not always lead to the same decision as NPV when mutually exclusive projects are being considered NPV remains the single best decision rule NPV also does provides the best indication of how much each project will add to the value of the firm.

QUESTION I

As a separate project (project P), you are considering sponsoring a pavilion at the upcoming world's fair. The pavilion would cost $800,000, and it is expected to result in $5 million of incremental cash inflows during its 1 year of operation. However, it would then take another year, and $5 million of costs, to demolish the site and return it to its original condition. Thus, project P's expected net cash flows look like this (in millions of dollars):
Year Net Cash Flows

0 ($0.8) 1 5.0 2 (5.0) The project is estimated to be of average risk, so its cost of capital is 10 percent.

(1) What are normal and non-normal cash flows?


Normal cash flows begin with a negative or a series of negative cash flows, switch to positive cash flows and then remain positive and vice versa. They have only one change in sign. Non-normal cash flows have more than one sign change. For example, they may start with negative cash flows, switch to positive, and then switch back to negative.

(2) What is project Ps NPV? What is its IRR? Its MIRR?


Here is the time line for the cash flows, and the NPV; 0 10% 1 | -5,000,000 2 | 5,000,000

| -800,000

NPV = -$386,776.86. We can find the NPV by entering the cash flows into the cash flow register, entering i= 10, and then pressing the NPV button. However, calculating the IRR presents a problem. With the cash flows in the register, press the IRR button will give the message "error-soln." This means that project P has multiple IRRs. As you are asked to guess, if you guess 10%, the calculator will produce IRR = 25%. If you guess a high number, such as 200%, it will produce the second IRR, 400%. The MIRR of project P = 5.6%, and is found by computing the discount rate that equates the terminal value ($5.5 million) to the present value of cost ($4.93 million).

i. (3) Does project P have normal or non-normal cash flows? Should this project be accepted?

Project P has non-normal cash flows because it has more than one change of signs in the cash flows. Besides it has two IRRs at 25% and at 400%, multiple IRRs is only possible in nonnormal cash flow pattern.
Since project P's NPV is negative, the project should be rejected, even though both IRRs (25% and 400%) are greater than the project's 10 % of capital. The MIRR of 5.6% also supports the decision that the project should be rejected.

QUESTION (J)

In an unrelated analysis, you have the opportunity to choose between the following two mutually exclusive projects: Expected Net Cash Flows Year 0 1 2 3 4 Project S ($100,000) 60,000 60,000 --Project L ($100,000) 33,500 33,500 33,500 33,500

The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have a 10 percent cost of capital.

(1) What is each project's initial NPV without replication?

The NPVs, found with a financial calculator, are calculated as follows: Input the following: CF0 = -100000, CF1 = 60000, N = 2, AND I = 10 to solve for NPVs= $4,132.23 $4,132. Input the following: CF0 = -100000, CF1 = 33500, N = 4, AND I = 10 to solve for NPVL = $6,190.49 $6,190. However, if we make our decision based on the raw NPVs, we would be biasing the decision against the shorter project. Since the projects are expected to be replicated, if we initially choose project S, it would Be repeated after 2 years. However, the raw NPVs do not reflect the replication cash flows.

(2) Now apply the replacement chain approach to determine the projects extended NPVs. Which project should be chosen?
The simple replacement chain approach assumes that the projects will be replicated out to a common life. Since project S has a 2-year life and L has a 4-year life, the shortest common life is 4 years. Project L's common life NPV is its raw NPVL = $6,190 (since actual duration = 4 years) However, project S would be replicated in year 2, and if we assume that the replicated project's cash flows are identical to the first set of cash flows, then the replicated NPV is also $4,132, but it "comes in" in year 2. We can put project S's cash flow situation on a time line: 10% 1 0 2 3 4

|
4132 3,415 7,547 7547

|
4132

(3) Now assume that the cost to replicate project S in 2 years will increase to $105,000 because of inflationary pressures. How should the analysis be handled now, and which project should be chosen?
If the cost of project S is expected to increase, the replication project is not identical to the original so in this situation, we would put the cash flows on a time line as follows:
0 r = 10% 1 | | 100,000 60,000 2 | 60,000 -105,000 - 45,000 3 | 60,000 4
| 60,000

Common Life NPVS = $3,415

With this change, the common life NPV of project S is less than that for project L, and hence project L should be chosen.

QUESTION K

You are also considering another project which has a physical life of 3 years; that is, the machinery will be totally worn out after 3 years. However, if the project were terminated prior to the end of 3 years, the machinery would have a positive salvage value. Here are the projects estimated cash flows:

Year

Initial Investment End-Of-Year Cash Flows

Operating Net Salvage Value $5,000 3,100 2,000 0

0 1 2 3

($5,000) 2,100 2,000 1,750

Using the 10 percent cost of capital, what is the projects NPV if it is operated for the full 3 years? Would the NPV change if the company planned to terminate the project at the end of year 2, at the end of year 1? And what is the projects optimal (economic) life?

Solution: (i) No Project Termination 3 Years Project Timeline.

0
10%

CF
Salvage Value

($5000)

($2100)

($2000)

($1750)
($0) ($1750)

Therefore, Net Present Value for no project termination is (NPV) = -$123.22/ -$123.

(i) With Termination After 2 Years 2 Years Project Timeline. 0 10% 1 2

CF

($5000)

($2100)

($2000)

Salvage Value

($2000)
($4000)

Therefore, Net Present Value with project termination after 2 years is (NPV) = $214.88/ $215.

(i) With Termination After 1Years 1 Year Project Timeline. 0 10% 1

CF

($5000)

($2100)

Salvage Value

($3100)
($4000)

Therefore, Net Present Value with project termination after 2 years is (NPV) = $-272.73/ -$273.

CONCLUSION:
Based on all NPV value from three different options can be conclude that the optimal economic life is the project should be terminate after years 2 where the NPV value is positive ($215). Moreover, it also indicated that a project engineering life does not

always equal to its economic life.

QUESTION L

After examining all the potential projects, you discover that there are many more projects this year with positive NPVs than in a normal year. What two problems might this extra-large capital budget cause?

Increasing in Cost of Capital


cause company to reject projects that they might otherwise accept

Capital Rationing

THANK YOU Q & A SESSION

You might also like